final design presentation
play

FINAL DESIGN PRESENTATION 13 th St N Kirkwood Rd to N. Johnson St - PowerPoint PPT Presentation

FINAL DESIGN PRESENTATION 13 th St N Kirkwood Rd to N. Johnson St (Lyon Village Neighborhood) Angela Marshall, Neighborhood Conservation Planner Community Planning, Housing, & Development Neighborhood Conservation Program Final Design


  1. FINAL DESIGN PRESENTATION 13 th St N – Kirkwood Rd to N. Johnson St (Lyon Village Neighborhood) Angela Marshall, Neighborhood Conservation Planner Community Planning, Housing, & Development Neighborhood Conservation Program

  2. Final Design N560 13th Street N (N Kirkwood Rd to N Johnson St)

  3. Agenda: 1. Overview of the Project 2. Street Improvement Design Plan 3. Sign and Pavement Markings Plan 4. Landscape Plan

  4. Presentation Purpose: Present final design to property owners in preparation for construction of the street improvement project on 13 th St N, Kirkwood Rd to N. Johnson St. Project Goal: Pedestrian Safety project to include a 5-foot wide sidewalk, curb and gutter on the south-side, and curb and gutter only on the north-side of 13 th St N between Kirkwood Rd to N. Johnson St and a retaining wall at one property. All improvements within existing right-of-way; ADA compliant accessible curb ramps at the intersection of 13 th Street N and N Kirkwood Rd. Parking on either side of 13 th St N will not be permitted.

  5. Temporary Easements • Temporary easements and construction agreements allow the County contractor to access private yards to perform construction-related work, including the relocation of fences, replacement of disturbed sod, and making grade adjustments. • The County agrees to restore the disturbed area on and adjacent to the Temporary Easement Area as nearly as practicable to its original condition . • Temporary easements become null and void at the end of the project .

  6. Next steps 1. Questions and comments • Relative to the overall project design • Relative to individual lots 2. Final design plan 90% → 100% 3. Temporary easements complete 4. Utility relocation complete 5. On-call contractor/Prepare for construction

Recommend


More recommend