faulkner wheeler joint
play

Faulkner-Wheeler Joint Ditch Petition Logan County Commissioners - PowerPoint PPT Presentation

Faulkner-Wheeler Joint Ditch Petition Logan County Commissioners Shelby County Commissioners Joe Antram Julie Ehemann John Bayliss Bob Guillozet Paul Benedetti Tony Bornhorst Logan County Engineer Shelby County Engineer Scott C. Coleman,


  1. Faulkner-Wheeler Joint Ditch Petition Logan County Commissioners Shelby County Commissioners Joe Antram Julie Ehemann John Bayliss Bob Guillozet Paul Benedetti Tony Bornhorst Logan County Engineer Shelby County Engineer Scott C. Coleman, P.E., P.S. Robert B. Geuy, P.E., P.S.

  2. Summary of the schedule of events  Petition and bond submitted December 10, 2018, by Mary L. Kreglow in Logan County  Viewing held March 7, 2019  First hearing June 6, 2019  Commissioners approve or deny petition  If denied, any owner may appeal within 21 days  If approved, county engineer files his report (including surveys, plans and a schedule of assessments) with the commissioners  Commissioners set date of final hearing, which must be set 25 to 90 days after receiving the engineering report

  3. Summary of the schedule of events ( con’t )  Final hearing  Commissioners either reaffirm their order to grant the petition or dismiss the petition  If denied, any owner may appeal within 21 days  If approved, any owner may appeal within 21 days  No further action taken until appeal period is over  If reaffirmed, bids are set to be received within 25 days  If there are no appeals, the Logan County Commissioners, on behalf of the joint board, receive bids and construction is performed  Ditch is maintained by the county with funds obtained by an annual assessment upon benefitted owners

  4. Project Location (between CR 23 and TR 78)

  5. Watershed • Contains 1257.268 acres • Involves 71 parcels • Includes Shelby and Logan County • Includes Indiana/Ohio Railway, who will be contacted to correct their drainage issues

  6. Watershed

  7. Existing drainage structures 2,230’ of twin 27” tiles Concrete headwall 500’ of 22” tile 1540’ of 24” tile

  8. Looking east at the beginning of Faulkner (CR 23)

  9. Looking north at the beginning of Wheeler (TR 78)

  10. Typical ditch view of Faulkner-Wheeler

  11. 27” tile blowout in Faulkner -Wheeler

  12. Twin 27” tile blowout in Faulkner -Wheeler

  13. Looking east near project termini

  14. Proposed structures: As petitioned 2,230’ of twin 30” tiles Concrete headwall 500’ of 24” tile 1540’ of 24” tile

  15. Cost Estimate: As petitioned

  16. Proposed structures: Alternate Proposal 2,230’ of open ditch 500’ of 24” tile Farm drive with 30’x7’x4’ box culvert 1540’ of 24” tile

  17. Cost Estimate: Alternate Proposal

  18. Opinion of the engineer The completion of this proposed ditch petition would: immediately increase the land value of cropland by increasing cropland production, limit the possibility of flooding, and proactively prevent a future major drainage failure of the watershed. Thus, it is the opinion of the engineer that the benefits of this proposed ditch petition would outweigh the costs.

  19. Questions and Open Discussion For more details on the ditch petition process, copies of ‘The Ohio Drainage Laws Petition Procedure’ are available. This presentation has been prepared by the Logan County Engineer’s Office and can be found online at www.lceo.us under the tabs Ditches > Ditch Improvements.

Recommend


More recommend