ec c overview and scrutiny panel
play

EC&C Overview and Scrutiny Panel Coral Reef Update September - PowerPoint PPT Presentation

EC&C Overview and Scrutiny Panel Coral Reef Update September 2016 Project Update Contract signed & sealed 4 th July Pre-start meeting 7 th June BFC Brymor Van Egdom Atkins Site mobilisation started 16 th May


  1. EC&C Overview and Scrutiny Panel Coral Reef Update September 2016

  2. Project Update Contract signed & sealed 4 th July • Pre-start meeting 7 th June • – BFC – Brymor – Van Egdom – Atkins Site mobilisation started 16 th May • • Contract is on time and within budget • Budget pressure reduced by circa £226k (secondments) • Cost avoidance of £25k through reduced redundancies Scheduled completion date 18 th August 2017 •

  3. Current Construction Work • Complete drainage diversion works to rear of site • Demolition of the Splash Pool enclosure and walls Commence 1 st Fix Mechanical & Electrical to new reception area • • Begin excavation for new flume tower basement 1 st Fix plumbing to toilet areas • • Commence replacement ceiling to Coconut Grove

  4. Coconut Grove

  5. Splash Pool

  6. Flume Tower & Flumes

  7. Flume Tower

  8. Main Pool Scaffold

  9. Main Pool Roof

  10. Next Phase • Start removal of main pool roof • Construct ground floor of flume tower • Flume manufacturing • Commence reception area and entrance ceilings • Changing Village ceiling work • Construct foundations for new splash pool area

  11. Questions?

Recommend


More recommend