East Division Elementary School GC/CM March 7 th , 2018 Board Update
Agenda for this evening Madison Elementary School – Design Update – Gerry Pless Design Progress Cost Estimating and Value Engineering Permitting Land Use/Master Plan East Division Elementary School – Construction Update – Kevin Fromm, Joe Ness, Craig Greene Look at updated progress photos Review Schedule and what's ahead Review potential Risks the Team is working through
MADISON ELEMENTARY STATUS UPDATE Design Progress Construction Documents Progressing Permit Documents Submitted Finalizing Phase 1 Bid Package Final DAC meeting regarding Interior Design Remainder of bid packages in June/July
MADISON ELEMENTARY STATUS UPDATE Cost Estimating and Value Engineering Cost Reconciliation Complete Value Engineering/Cost Control Completed Within 1.4% of Construction Budget Target
MADISON ELEMENTARY STATUS UPDATE Cost Estimating and Value Engineering Alternates 4 Classroom Addition Pick-up Canopy Outdoor Amphitheater Unforeseen Issues (addressed in estimate) 8 th Street Water Main Replacement Contaminated Soils
MADISON ELEMENTARY STATUS UPDATE Permitting Submitted for building permits to the City of Mount Vernon Submitted for water service permit to Skagit PUD
MADISON ELEMENTARY STATUS UPDATE Land Use / Master Plan Progress Submitted response to City Staff report. City reviewing response. Likely Hearings Examiner and City Council in Late March.
Site Progress and Stabilization 1-17-18 Presentation to Board 3-7-18 Presentation to Board
Off-Site Utility and Pond work 1-17-18 3-7-18
Area D Classroom Wing/Main Entrance Progress Looking North 1-17-18 Presentation to Board 3-7-18 Presentation to Board
Area B Classroom Wing Progress 1-17-18 Presentation to Board 3-7-18 Presentation to Board
Outdoor Learning Area 1-17-18 Presentation to Board 3-7-18 Presentation to Board
Library Progress Interior Looking to the South 1-17-18 Presentation to Board 3-7-18 Presentation to Board
Area B Classroom Wing Interior Progress 1-17-18 Presentation to Board 3-7-18 Presentation to Board
Area C Classroom Wing Interior Progress 1 st and 2 nd Floor 1-17-18 3-7-18
Upcoming Schedule Milestones Mar APR MAY JUNE 2018 2018 2018 2018 - Exterior Envelope - Wings A, B, C & D - Finishes in B Complete. - All Finishes Complete Complete Finishes Ongoing A, C & D ongoing - Owner/Architect Punch - Wing A, B & C Finishes - Window Installation - Exterior Finishes - Project Demobilization ongoing, start Wing D Complete Complete - Finalize Elevator Finishes - Substantial work - MVSD I.T. Begins Move- - Final Inspections - Prep for final curb and underway on the exterior in sidewalk of the site - Curb and Sidewalk - Permanent Power to - Begin MEP Startup and Complete Building Commissioning
Ongoing Risk Mitigation • One recordable safety incident • Structure 100% Complete • Building 100% Dried in • Submittals 99% complete • MACC Contingency use still less than $300,000