crsp 10 plan presentations
play

CRSP 10-Plan Presentations November 9, 2015 Rocky Mountain Region - PowerPoint PPT Presentation

CRSP 10-Plan Presentations November 9, 2015 Rocky Mountain Region Ten Year Plan Version Control R0 -version of Ten Year Plan submitted to customers and to headquarters for consolidation of Western-wide budget; late October-November R1


  1. CRSP 10-Plan Presentations November 9, 2015

  2. Rocky Mountain Region Ten Year Plan Version Control • R0 -version of Ten Year Plan submitted to customers and to headquarters for consolidation of Western-wide budget; late October-November • R1 -version of Ten Year Plan with any corrections or changes after customers and senior management review; mid-January • RFINAL -final version submitted to headquarters for consolidation of Western-wide budget submission to the Dept. of Energy; April

  3. FY 15 Rocky Mountain Region Maintenance Project s • New System Operation Methodology • Completed Projects • New Projects • Changed Projects • Ongoing Projects

  4. Transmission Operator Methodology Changes • September 2011 Western grid outage • Revised System Operating Limit (SOL) Methodology-August 2013 – If the next single contingency will result in a voltage or thermal overload, PEAKRC requires pre-mitigation: • Load shedding • Generation curtailment (or increase); reactive device changes including generation redispatch • Reduction of scheduled power, may require purchase of power at spot market prices

  5. Transmission Operator Methodology Changes • Western plans and designs its system to operate through a single contingency without loss of load (TPL standards). • Western Operations studies and controls the system to perform through multiple contingencies. (TOP standards) • Potential projects to address operational compliance standards – Curecanti 2 nd 230/115 kV transformer – Midway 230 kV bus configuration

  6. FY 15 Rocky Mountain Region Maintenance-Completed Project s • Flaming Gorge 69 kV Switch Replacements – Replaced 7 switches, 1963 vintage – In-Service Date: Q2 2015 – Total Cost: $195k, excludes IDC – Budget: $243k • Gore Pass-Hayden 230 kV Uprate Term Eqmnt – Replaced 2 switches, 2 CTs to 2000 A rating – In-Service Date: Q4 2015 – Total Cost: $58k JJCR, $257k JJCR/Trust, excludes IDC – Budget: $69k JJCR, $291k JJCR/Trust

  7. FY 15 Rocky Mountain Region Maintenance-Completed Project s • Hayden KZ2A 230/138 kV, 250 MVA Transformer – Replaced 150 MVA to match KZ1A at 250 MVA – In-Service Date: Q4 2015 – Total Cost: $7,374k, excludes IDC – Budget: $6,909k • Montrose Digger Derrick – Replaced 1981 digger truck, 26k miles, worn/dysfunctional outriggers, hazardous use – Budget/total cost: $610k

  8. FY 15 Rocky Mountain Region Maintenance-Completed Project s • Buffalo Pass Communications Building Replacement – Replaced aging end of life building – In-Service Date: Q4 2015 – Total Cost: $1,010k, excludes IDC – Budget: $350k

  9. New JJCR Projects in the FY16-25 TYP • Archer Station Service Replacement – Replace 1964 vintage switchgear and controls; auto-throw over switch non-functional – Est. Cost: $585k – Est. In-Service Date: Q2 2018 • Ault Station Service Replacement – Replace 1980 vintage station switchgear, controls, and transformers which has a history of failures and nonfunctional equipment – Est. Cost: $940k (JJCR $183k) – Est. In-Service Date: Q4 2016

  10. New JJCR Projects in the FY16-25 TYP • Ault KW1F/KW1G, 2-25 MVAR Reactor Replacement – Replace failed KW1F and twin KW1G prior to KU1A replacement (AM supported) – Est. Cost: $711k (JJCR cost $455k) – Mitigation: Replacement – Est. In-Service Date: Q4 2017 • Ault 345 kV Surge Arrestors (AU-CRG 345 kV line) – Needed for minimum approach distances(new OSHA) and aids in fault location determination – Est. Cost: $50k (JJCR cost $18k) – Mitigation: Replacement – Est. In-Service Date: Q4 2016

  11. New JJCR Projects in the FY16-25 TYP • Shiprock Substation-new Control Building – Existing building has full cable trays, is at maximum capacity, and has asbestos; includes 345 kV yard and transformer; batteries, air control, communication – Est. Cost: $2,581k potential trust of $500k – Mitigation: Replacement, with/without Trust support – Est. In-Service Date: Q4 2019

  12. New JJCR Projects in the FY16-25 TYP • Shiprock Substation-Move 230 kV Eqmnt & Controls – Purchase panels and controls, install in new building – Est. Cost: $1,861 – Mitigation: Replacement – Est. In-Service Date: Q4 2020 • Shiprock Substation-Move 115 kV Eqmnt & Controls – Purchase panels and controls, install in new building – Est. Cost: $1,158 – Mitigation: Replacement – Est. In-Service Date: Q4 2021

  13. New JJCR Projects in the FY16-25 TYP • Weld Substation 230 kV Breaker & Half – Modify the four terminal main/transfer configuration to breaker and half to increase system reliability for the N-1 that overloads 2-115 kV lines. – Est. Cost: $2,580k – Est. In-Service Date: Q4 2023 • UHF Radio Replacements – Replace existing polling radios at the end of their useful life. – Est. Cost: $850k, JJCR $35k – Mitigation: Replacement – Est. In-Service Date: Q4 2021

  14. New JJCR Projects in the FY16-25 TYP • MOC Pressure Digger Truck Replacement – Replace 1994 pressure digger truck, 15k miles and low usage as incorrect truck for high voltage t-lines; will trade in – Est. Cost: $325k – Mitigation: Replacement – Est. In-Service Date: Q4 2018 • SHR 72 ft Manlift Aerial Elbow Bucket Truck(Repl. 40 ft) – Replace 1979 elbow bucket truck, worn/sloppy hydraulics, 21k miles, at end of life – Est. Cost: $125k – Mitigation: Replacement – Est. In-Service Date: Q4 2018

  15. Changed JJCR Projects in the FY16-25 TYP Total JJCR Project Change Cost Shared Cost x1000 x1000 Slid a year to Dolores Transformer Project (TRUST) $1350 $0 FY 16 ‐ 17 Shiprock 230 & 345 kV POD (TRUST Slid a year to $3,781 $0* TSGT Interconnection and 3 Rivers) FY 20; *land use Project slid to FY18 to align Ault 230 kV CB 1482 & 1586 $564 $285 replacement with Ault KU1A (high/low side CBs) Shiprock (3262, 3362, 3462) PCB 115 ‐ Breakers purchased in FY15, $577 $577 kV Replacement ISD FY16 $38k increase with updated Ault ‐ Weld West OPGW $566 $566 estimate

  16. Changed JJCR Projects in the FY16-25 TYP Total JJCR Project Change Cost Shared Cost x1000 x1000 $250k increase of estimate based Island Lake Comm Building $750 $750 on recent bid openings $155k increase in JJCR costs spread IT General Support Systems $622 $622 over FY14 ‐ 23 Mobile Radio Infrastructure Slid to FY17 to accommodate $1,300 $650 Replacements shifting COMM projects

  17. Changed and Ongoing JJCR Projects in the FY16-25 TYP Total JJCR Project Change Cost Shared Cost x1000 x1000 Ault 345 kV CB 692, 696, 1096 Customer funding slid schedule and In design, CB ordered $1,802 $270 • in ‐ service date, shifted ISD to 2017 ISD Q4 FY16 • Shiprock Stage 07 230 kV Main $720k decrease with bid; $400k and Transfer Bus Uprate $1,208 $1,208 shifted to FY16 for project In construction • completion ISD Q3 FY16 • Waterflow PST KU1A ‐ KU1B and CB replacement In construction $450k shifted to FY16 for project • $15,058 $15,058 Delay of PST delivery to completion and closeout. • 1/16 ISD Q2 FY16 •

  18. Changed and Ongoing JJCR Projects in the FY18-25 TYP Total JJCR Project Change Cost Shared Cost x1000 x1000 Weld 362,1262 (115 ‐ kV) CB, 182, 286, 482 (230kV) $954k increase added construction Replacement $1,669 $1,669 contract for installation in FY16 due In design to maintenance resource limitations • ISD • Archer KV2A 230/115 kV, 200 MVA Xfmr $282k increase to include high/low 90% spec review $3,200 $3,200 side CB 482 & 1762; 1980 vintage, • Delay ‐ xfmr procurement high PCB bushings • ISD Q1 FY17 • Curecanti KZ1A 230/115 kV 150 MVA Replacement $471k decrease, utilizing a used $2,287 $2,287 In construction xfmr from Hayden. • ISD Q4 FY16 •

  19. Changed and Ongoing JJCR Projects in the FY18-25 TYP Total JJCR Project Change Cost Shared Cost x1000 x1000 Montrose ‐ Mexican Hat MW Rep. $132k increase, funds shifted for Resource limited $1,601 $1,601 • FY16 completion and closeout ISD Q4 FY16 • Poncha ‐ Midway OPGW $566k increase due to assembly Raptor nesting delayed issue in design and raptor delays; • $3,156 $1,598 construction shift in ISD and funds to FY16 for ISD Q2 FY16 completion/closeout • Blue Mesa ‐ Montrose OPGW Restriction in construction due Shifted $25k to FY16 for project • $1,883 $758 to sage grouse/bird nesting completion and closeout. ISD Q1 FY16 •

  20. Changed and Ongoing JJCR Projects in the FY18-25 TYP Total JJCR Project Change Cost Shared Cost x1000 x1000 $469k increase for stage 3 & 4, MOC Station Service Upgrade construction contract, excavation of In design $909 $909 1965 vintage conduit for • ISD Q1 FY17 replacement, transformer • installation Central PMOC Communications Loop $126k increase, funds shifted to Resource limited delayed $2,713 $666 • FY16 for completion and closeout completion ISD Q3 FY16 •

  21. Changed and Ongoing JJCR Projects in the FY18-25 TYP Total JJCR Project Change Cost Shared Cost x1000 x1000 Collbran 115 kV CB 362 Replacement $90k increase, underground Delay from underground conduits were asbestos, required • cable issue $231 $231 new conduit/excavation installation; Resource limited funds in FY16 for completion and • ISD Q4 FY16 closeout • $63k increase, difficulty with Blue Mesa 115 kV CB 1066,1162 removal due to tight physical layout Replacement $357 $357 of substation; funds in FY16 for ISD Q4 FY15 • closeout

Recommend


More recommend