craney island eastward expansion hydraulically
play

-Craney Island Eastward Expansion Hydraulically Constructed Dikes - PowerPoint PPT Presentation

-Craney Island Eastward Expansion Hydraulically Constructed Dikes 40 Years of Dredging and Environmental Innovation P R E S E N T E D B Y: I R A B ROT M A N , P E M O F FAT T & N I C H O L O C T O B E R 2 5 , 2 0 1 2


  1. -Craney Island Eastward Expansion Hydraulically Constructed Dikes “40 Years of Dredging and Environmental Innovation” P R E S E N T E D B Y: I R A B ROT M A N , P E M O F FAT T & N I C H O L O C T O B E R 2 5 , 2 0 1 2

  2. Craney Island Eastward Expansion

  3. CIEE Layout I CIEE Main Dike CIDMMA East Dike Existing CIDMMA CIEE Cross Dike (typ)

  4. Subsurface Stratigraphy

  5. CIDMMA Dikes (1954)

  6. CIDMMA Dikes (1954)

  7. CIDMMA Dikes (1954)

  8. Cross Dike Objectives  Experiences with CIDMMA (built to +5’)  Minimize Mud Waves  Minimize Deformation  Minimize Instability – Now and Future  Minimize Ultimate Sand Volume  Predictable Schedule

  9. Cross Dike Alternatives  High strength geotextile/geogrid  Pre-dredge  Deep Soil Mixing  Prefabricated Vertical Drains (PVD)  Build dikes in lifts/stages  Allow increase in shear strength  Achieve by specifying lift thicknesses and hold times

  10. Selected Low Cost, Low Risk Cross Dike  Final target elevation = +18 ft (MLLW)  900 ft Wide  Built in 3 Stages Hydraulic Sand Fill 60 Zone of 40 PVDs Elevation in feet (MLLW) 20 0 -20 -40 Marine PVDs Marine PVDs Land PVDs -60 Upper Norfolk Clay (Qnu) -80 -10 0 -12 0 Pleistocene/Pliocene Sands (Qnl/Tys) -14 0 -16 0 0.50 -0.45 -0.40 -0.35 -0.30 -0.25 -0.20 -0.15 -0.10 -0.05 0.0 0 0.0 5 0.1 0 0.1 5 0.2 0 0.2 5 0.3 0 0.3 5 0.4 0 0.4 5 Distance in feet (x 1000) PVDs

  11. Construction Sequence  Place Initial Lift  Install Marine PVDs  Initiate Strength Gain  Place Second Lift  Allow Additional Strength Gain  Place Third Lift

  12. South and Division Cross Dikes

  13. Cross Dikes – Stage 1 Hydraulic Sand Fill, Stage 1

  14. Cross Dikes Stage 1 – Marine PVDs PVDs Outer 3rd PVDs PVDs

  15. Cross Dikes Stage 2A – Sand Fill Hydraulic Sand Fill, Stage 2A

  16. Rendering Post Stage 3

  17. Rendering Southeast Cell Closed

  18. Borrow Source Atlantic Ocean Channel CIEE

  19. GLDD – Stage 1

  20. Sand Placement

  21. GLDD – Stage 1 – Marine PVDs

  22. PVD Installation Record

  23. PVD Tip Elevations

  24. Multibeam Survey

  25. Multibeam Survey

  26. Geotechnical Instrumentation

  27. Instrumentation Website

  28. Settlement

  29. Summary  Schedule Challenges  TOY: Turtles  Contractor Innovation  Spillbarge  Specialized Barge for PVDs  Positioning /Tracking System  Observational Method Success  Measure behavior of foundation during filling  Validate Lift placement schedule and hold times  PVD installation verification  Control project risk

  30. Thank You Special thanks to:  Virginia Port Authority  Corps of Engineers, Norfolk District

Recommend


More recommend