North Beach Area Road Improvements and Area Beautification and North Beach Breakwater, Plaza, North Shoreline Repair and Enhancement (Bond 2012, Proposition 8) Council Presentation October 16, 2018 1
Project Location 2
Project Vicinity 3
Project Scope Two North Beach Bond 2012 projects combined to minimize disruptions to this key tourist destination and maximize construction competition. This construction contract includes a Base Bid and two Additive Alternates. Base Bid, Part 1: • Pavement restoration N. Shoreline Blvd (Pearl St to Coastal Ave) • Crosswalk markings on Surfside Blvd at Coastal Ave and Elm St Cleaning existing storm water and wastewater pipes, manholes, • and inlets on Breakwater Ave and Coastal Ave 4
Project Scope (cont.) Base Bid, Part 2: • New curb and gutter, sidewalks, ADA ramps, markings, signage, seating, on-street parking enhancements, and illumination improvements on N. Shoreline Blvd (Pearl St to Coastal Ave) • Paved surface for Breakwater Plaza between N. Shoreline Blvd and Breakwater structure; plaza re-designated as pedestrian area only • Cleaning existing storm water pipes, manholes, and inlets, and minor upgrades/adjustments for storm water on N. Shoreline Blvd Additive Alternate 1: Repair Breakwater concrete cap • Additive Alternate 2: Replace wastewater and water infrastructure on N. Shoreline Blvd • 5
Project Schedule 2018 2019 A S O N D J F M A Bid/ Construction Award Estimated Construction: 150 Calendar Days = 5 months Projected Schedule reflects City Council award in October 2018 with anticipated completion in April 2019. 6
Questions? 7