clic feasibility demonstration at ctf3
play

CLIC Feasibility Demonstration at CTF3 Roger Ruber Uppsala - PowerPoint PPT Presentation

CLIC Feasibility Demonstration at CTF3 Roger Ruber Uppsala University, Sweden, KVI Groningen 20 Sep 2011 20 Sep 2011 The Key to CLIC Efficiency NC Linac for 1.5 TeV/beam Main Linac accelerating gradient : 100 MV/m C.M. Energy 3


  1. CLIC Feasibility Demonstration at CTF3 Roger Ruber Uppsala University, Sweden, KVI Groningen 20 Sep 2011 20 Sep 2011

  2. The Key to CLIC Efficiency • NC Linac for 1.5 TeV/beam Main Linac – accelerating gradient : 100 MV/m C.M. Energy 3 TeV – RF frequency: 12 GHz 2x10 34 cm -2 s -1 2x10 34 cm 2 s 1 Peak luminosity Peak luminosity • Total active length for 1.5 TeV: 15 km Beam Rep. rate 50 Hz  individual klystrons not realistic Pulse time duration 156 ns • Two-beam acceleration scheme Average gradient 100 MV/m • Luminosity of 2x10 34 cm -2 s -1 # cavities 2 x 71,548 – short pulse (156ns) p ( ) – high rep-rate (50Hz) – very small beam size (1x100nm) • 64 MW RF power / accelerating structure of 0.233m active length  275 MW/m • Estimated wall power 415 MW at 7% efficiency Estimated wall power 415 MW at 7% efficiency Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 KVI, 20-Sep-2011 2

  3. CLIC Layout Drive Beam Drive Beam Generation Generation Complex Complex Drive Beam Drive Beam Main Beam 3 TeV (CM) Main Beam 3 TeV (CM) Main Beam Main Beam Generation Generation Complex Complex Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 KVI, 20-Sep-2011 3

  4. CLIC Two-beam Acceleration Scheme Drive Beam Accelerator Delay Loop (2x) efficient acceleration in fully loaded linac gap creation, pulse compression & frequency multiplication Combiner Ring (4x) RF Transverse pulse compression & Deflectors frequency multiplication Combiner Ring (3x) C bi Ri (3 ) pulse compression & frequency multiplication RF Power Source Drive Beam Decelerator (24 in total) Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 KVI, 20-Sep-2011 4

  5. CLIC Test Facility CTF3 • Drive beam generation , with – appropriate time structure, and – fully loaded acceleration • Two-beam acceleration , with CLIC prototype (TBTS) CLIC prototype (TBTS) Delay Loop – accelerating structures Combiner – power production power production Ring Ring Drive Beam D i B structures (PETS) Linac • Deceleration stability CALIFES Probe Beam Linac Probe Beam Linac (TBL) Two-beam Test Stand • Photoinjector (PHIN) Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 KVI, 20-Sep-2011 5

  6. CTF3 Experimental Program • Two-beam acceleration – conditioning and test PETS and accelerating structures – breakdown kicks of beam breakdown kicks of beam – dark (electron) current accompanied by ions – install 1, then 3, two-beam modules • Drive beam generation • Drive beam generation TBTS is the only place – phase feed forward for phase stability available to investigate – increase to 5 Hz repetition rate effects of RF breakdown – coherent diffraction radiation experiments coherent diffraction radiation experiments on the beam on the beam • Drive beam deceleration – extend TBL to 8 then 16 PETS – high power production + test stand • 12GHz klystron powered test stand – power testing structures w/o beam – significantly higher repetition rate (50 Hz) Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 KVI, 20-Sep-2011 6

  7. The CTF3 Facility as CLIC Test Bench 48.3 km 48 3 km Delay loop Drive beam Combine X4 r ring Probe beam Probe beam 12 GHz Stand alone Test-stand Test Beam Line 12 GHz Stand-alone Test Stand Two-beam Test Stand Test beam Line 140 m Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 KVI, 20-Sep-2011 7

  8. CTF3 Drive Beam • Several operation modes possible, • Tail clipper (TC) after the CR to adjust the pulse length, length • Upgrade possible to 150 MeV at 5 Hz repetition rate. Mode #1 #2 #3 Energy 120 [MeV] Energy spread Energy spread 2 2 [%] [%] Current (1) 30 15 4 [A] Pulse length (2) 140 240 1100 [ns] DBA frequency DBA frequency 1 5 1.5 3 3 3 3 [GHz] [GHz] Bunch frequency 12 12 3 [GHz] Repetition rate 0.8 [Hz] PETS power PETS power 200 200 61 61 5 5 [MW] [MW] Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 KVI, 20-Sep-2011 8

  9. Demonstration Fully Loaded Operation Efficient power transfer • “Standard” situation: • • small beam loading small beam loading • power at exit lost in load • “Efficient” situation: V ACC ≈ 1/2 V unloaded • high beam loading high beam loading • no power flows into load 95.3% RF % ut Pou power to beam field builds up linearly (and stepwise, for point-like bunches) Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 LINAC'10 (13-Sep-2010) 9

  10. Recombination Principle D l Delay Loop L even buckets odd buckets RF deflector C Combiner Ring bi Ri 4 th Turn DELAY LOOP 4 A – 1.2  s COMBINER 150 Mev RING DRIVE BEAM LINAC 32 A – 140 ns 150 Mev CLEX 10 m CLIC Experimental Area  /4  o /4 Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 KVI, 20-Sep-2011 10

  11. Bunch Re-combination DL + CR • Streak camera From DL Turn 1 images from CR Turn 2 Turn 2 • bunch spacing: – 666 ps initial Turn 3 – 83 ps final 83 fi l Turn 4 • circulation time correction by wiggler adjustment by wiggler adjustment • Signal from BPMs from Linac Signal from BPMs in DL DL CR after DL 30A 30A in CR Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 KVI, 20-Sep-2011 11

  12. Ongoing Work • Beam current stabilization LINAC DL CR – CLIC requires stability at 0.075% level 0.13% 0.20% 1.01% Variation – ok from linac and DL ok from linac and DL need improvement in CR • Phase stabilization – temperature stabilization t t t bili ti pulse compressor cavity • Transfer line commissioning – transport losses from CR to experiment hall RF phase stability along pulse l l klystron off (for different ambient temperatures) Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 KVI, 20-Sep-2011 12

  13. CALIFES Probe Beam • A standing-wave photo-injector g p j Energy 200 MeV Energy spread 1% (FWHM) • 3 travelling-wave structures, the first one Pulse length 0.6–150 ns used for velocity bunching Bunch frequency 1.5 GHz Bunch length 1.4 ps • A single klystron (45 MW – 5.5 ms) with • A single klystron (45 MW 5 5 ms) with Bunch charge Bunch charge 0.085 0.6 nC 0 085–0 6 nC Intensity pulse compression (120 MW – 1.3 ms) - short pulse 1 A - long pulse 0.13 A • A RF network with splitters, phase shifters, Repetition rate 0.833 – 5 Hz attenuator, circulator and couplers tt t i l t d l Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 KVI, 20-Sep-2011 13

  14. Two-beam Test Stand S Spectrometers t t Experimental area and beam dumps Construction supported by the Swedish Research Council and the Council and the Knut and Alice Wallenberg Foundation Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 KVI, 20-Sep-2011 14

  15. Two-beam Test Stand Prospects Versatile facility • two-beam operation – 28A drive beam [100A at CLIC] 28A drive beam [100A at CLIC] – 1A probe beam [like CLIC ] • excellent beam diagnostics, long lever arms • easy access & flexibility for future upgrades Unique test possibilities • power production in prototype CLIC PETS p p p yp • two-beam acceleration and full CLIC module • studies of – beam kick & RF breakdown beam kick & RF breakdown – beam dynamics effects – beam-based alignment Roger Ruber (Uppsala University) - CLIC Feasibility Demonstration at CTF3 KVI, 20-Sep-2011 15

  16. TBTS Test Area 1x PETS w/ recirculation 11 March 2010 11 March 2010 RR201003110009 1x accelerating g structure Roger Ruber (Uppsala University) - Two-beam Test Stand CTF3 Collaboration Meeting (05- 16 May-2010)

  17. Structures Test Program • Drive Beam Area – Installed: • TBTS PETS, 1m long • external RF power recirculation – Next test foreseen: • PETS On/Off option (active reflector) A C A. Cappelletti (04-May-2010) ll tti (04 M 2010) 4 th X-band Workshop Courtesy A. Cappelletti http://indico.cern.ch/event/75374 • Probe Beam Area Probe Beam Area – Installed: • TD24 = disks, tapered, damped, 24 cells A. Samoshkin (07-Apr-2010) CLIC RF struct. dev. meeting http://indico.cern.ch/event/72089 – Next test foreseen: • TD24 with wakefield monitor • TD24 with wakefield monitor Courtesy A. Samoshkin Roger Ruber (Uppsala University) - Two-beam Test Stand CTF3 Collaboration Meeting (05- 17 May-2010)

  18. PETS Power Recirculation • PETS length 1m, to compensate for lower to load beam current compared to CLIC variable splitter variable (coupling: 0  1) phase shifter • External recirculation loop External recirculation loop PETS output – increase PETS power in long pulse, PETS input drive low current mode #3 beam • power recirculation i l ti through external feedback loop: – electron bunch generates field burst generates field burst – field burst returns after roundtrip time t r = 26ns PETS operates as amplifier (LASER like) • phase shifter to adjust phase error in the loop Roger Ruber (Uppsala University) - Two-beam Test Stand CTF3 Collaboration Meeting (05- 18 May-2010)

Recommend


More recommend