cigre us national committee 2014 grid of the future
play

CIGRE US National Committee 2014 Grid of the Future Symposium - PowerPoint PPT Presentation

CIGRE US National Committee 2014 Grid of the Future Symposium Initial Field Trials of Distributed Series Reactors and Implications for Future Applications I GRANT J COUILLARD Tennessee Valley Authority Smart Wire Grid Inc. USA USA J SHULTZ F


  1. CIGRE US National Committee 2014 Grid of the Future Symposium Initial Field Trials of Distributed Series Reactors and Implications for Future Applications I GRANT J COUILLARD Tennessee Valley Authority Smart Wire Grid Inc. USA USA J SHULTZ F KREIKEBAUM Tennessee Valley Authority Smart Wire Grid Inc. USA USA Ian Grant S OMRAN R BROADWATER Tennessee Valley Authority Virginia Tech Electrical Distribution Design (EDD) USA USA Presented by: BRUCE ROGERS, Director, Technology Innovation, TVA 1

  2. Distributed Series Reactor 2

  3. Background The Distributed Series Reactor is a self contained device, powered by induction from a transmission line conductor, that increases the series impedance of a circuit by injecting series reactance. The concept was first demonstrated in 2002 – 2003 and has been demonstrated in pilot installations on HV transmission lines. 3

  4. Equivalent Circuit With secondary winding shorted, injection is negligible 4

  5. DSR Characteristics (typical) Model Rated Injection Reactance added per DSR* (p.u.) Current Mode (A) Inductance at Rated Current (μH) 115 kV 138 kV 161 kV 230 kV 1.34e-4 9.30e-5 6.84e-5 3.35e-5 750 750 47 1.20e-4 8.31e-5 6.11e-5 2.99e-5 1000 1000 42 1.05e-4 7.32e-5 5.38e-5 2.64e-5 1500 1500 37 For a 161 kV line, assume 5 spans per mile and a device at each end of each span i.e. 10 devices per mile. Approximate impedance increase = 20% 5

  6. Example Application in Meshed Grid G8 39 BUS SYSTEM G10 37 26 25 28 29 30 38 – 2 Baseline MW: 18 27 1 17 G9 24 1904 MW 16 – Increase in ATC G6 G1 3 15 35 possible: 638 MW (33.5%) 21 22 39 4 14 – Increase in line availability 5 19 6 12 23 31 13 20 from 59% to 93% 11 7 36 8 10 G2 34 9 32 G7 G5 G4 G3 6

  7. Communication and Control Manual or automatic control through preset trigger points (e.g. line current), Power Line Carrier, Cell phone Individual information display available in control center for each DSR 7

  8. Pilot Test at TVA 100 DSRs installed on 17 spans of 21 mile 161 kV line at TVA Approximately 10 minutes to install each DSR 8

  9. Prototype DSR Installation at TVA TVA - 14.5 Miles of ACSR 795.0-26/7 9

  10. DSR Installation Clamshell construction. The two halves are positioned on the line and secured together with a torque wrench The devices run self diagnostics and can be remotely tested Each module can be triggered at a predefined set point or controlled remotely 10

  11. Pilot Test Results • Total Impedance Increase (33 DSRs / Phase @ 47 µH / DSR): .226 % (degree of control limited by number of available devices and a test line that was longer than optimal for the demonstration) • Devices performed as expected over 4-step range • Devices also successfully used to adjust phase imbalance • Single point failure of communication system identified for necessary design upgrade • DSRs presently considered unsuitable for bundled conductor use, although technically feasible 11

  12. Future Applications • Success of pilot opens path to more critical applications • Simplest application is reduction of maximum contingency load for postponement of line uprate • Ability to quickly relocate DSRs reduces cost to individual projects • Extreme case for portion of HV grid to have dynamically assigned line loading for selected goals, e.g. minimize system losses • Future designs may provide capacitive injection to reduce reactive impedance • Future designs with high speed controls may be low cost alternative to FACTS 12

  13. The IEEE 39 bus standard test system converted to a three phase system with 345kV lines 13

  14. The 345kV Line Configuration Structure Type: 3L11  Utility: Houston Lighting & Power Company Reference: EPRI, Transmission Line Reference Book - 345kV and above 14

  15. Line Impedance Models Unbalanced: Positive Sequence: Positive Sequence Z is derived from the Unbalanced Model Z using the symmetrical components transformation 15

  16. DSR Design for Load Growth Line5-6 Line6-7 Line13-14 Total 6000 5550 5000 No. of DSRs deployed 4000 3750 3525 3000 1950 2000 1650 900 1000 675 75 0 141% 143% 145% 147% 149% 141% 143% 145% 147% 149% Positive Sequence Unbalanced System Loading (%) 16

  17. Unbalanced vs. Positive Sequence Impedance Model Positive Sequence Unbalanced 40 35 30 Slope (MW/DSR) 25 20 15 10 5 0 141% 143% 145% 147% 149% System Loading (%) Slope (MW/DSR) for different System Loading % 141% 143% 145% 147% 149% Positive Sequence 33.60 2.93 1.41 0.81 0.54 Unbalanced 4.09 1.75 0.80 17

  18. DSR Design for Single Contingency: Unbalanced Impedance Model 18

  19. DSRs Deployed and Load Supplied 19

  20. The Selected Design at 140% System Loading Reinforced Lines with DSRs Lines 1500 DSR 75 DSR on on line5-6 line13-14 20

  21. DSR Design vs. Line Reinforcement for Single Contingency and Load Growth: Economic Evaluation 21

  22. Economic Evaluation • Determine the maximum MW supplied to load while handling all single contingencies – Case1: Three Lines Reinforced with No DSR – Case2: Three Lines Reinforced with DSR • Economic assessment of both cases 22

  23. Economic Evaluation Results • Case1: With Three Lines Reinforced • 125% loading is reached • Case2: With Three Lines Reinforced and DSRs Deployed • 140% loading is reached and selected as a desired DSR Design due to its technical merits – Fewer number of DSRs deployed. – Least % change in lines impedance. 23

  24. Data for the Economic Study • Max MW supplied at different % loading: Max MW MW Case % Loading supplied increase Base 100% 6309.4 Case1 125% 7886.6 1577.2 Case2 140% 8833.1 946.5 • Total length of the reinforced lines = 95 miles. Reinforced Line Length (miles) Line2-3 37 Line6-7 29 Line15-16 29 • Cost of 345 kV, single circuit = 1298 $k /mile 24

  25. Line Reinforcement Cost • Cost of 95 miles of line = 95 x 1298 k$ = 123.31 $M • Cost for 1577.2 MW of load increase = 123.31 $M • Cost per MW of load increase for reinforcing lines = 123.31 $M/1577.2 MW = 78,182 $/MW 25

  26. DSR Design Cost: Unbalanced Model • For the selected DSR design, a loading of 140% is achieved using 1575 DSR modules. • DSR worth in terms of transmission line value: – Cost of 946.5 MW of load increase = 946.5 MW x 78,182.8 $/MW = 74 $M – Thus the equivalent value of 1 DSR = 74 $M/1575 DSRs = 46,984 $/DSR 26

  27. Questions 27

Recommend


More recommend