Capital Improvement Project Phase 3 and Capital Outlay Project Updates Tuesday ~ April 17 th , 2018 Board of Education Meeting Cheektowaga ~ Sloan Union Free School District
Capital Improvement Project Phase 3 Renovations 2019 Theodore Roosevelt Woodrow Wilson * Roof Replacement * Door Replacements * Roof Exhaust Replacement * Locker Room Upgrades * Floor Replacement * Gym Wall Pad Installation * Gym Wall Pad Installation * Hallway Locker Removals * Emergency Lighting and Sensor * Emergency Lighting and Sensor Upgrades Upgrades * Finish Upgrades * Nurse’s Office Renovation * Library and District Office Carpet Replacement
Capital Improvement Project Phase 3 Renovations 2019 JFK Middle / High School Maintenance Garage / Team Room * Tennis Court Replacement * Roof Exhaust Fan Replacement * Shower Room Finish Upgrades * Ceiling Replacements * Roof Top Unit Replacement * Door Replacements * Toilet Room Renovations * Pool Ceiling Upgrades * Art Room Renovations * Music Suite Renovations * Main Office Renovations
Cheektowaga ~ Sloan UFSD Schedule
Cheektowaga ~ Sloan UFSD Budget • There is currently $3,641,935 remaining from Phase 1 and Phase 2 for this project.
Theodore Roosevelt Elementary Capital Improvement Project Phase 3 Gym Wall Pad Installation
Woodrow Wilson Elementary Capital Improvement Project Phase 3 Nurse’s Office Renovation
Woodrow Wilson Elementary Capital Improvement Project Phase 3 Gym Wall Pad Installation
JFK Middle / High School Capital Improvement Project Phase 3 Middle School Art Room Renovations
JFK Middle / High School Capital Improvement Project Phase 3 High School Art Room Renovations
JFK Middle / High School Capital Improvement Project Phase 3 High School Art Room Renovations
JFK Middle / High School Capital Improvement Project Phase 3 Music Suite Renovations
JFK Middle / High School Capital Improvement Project Phase 3 Toilet Room Renovations
JFK Middle / High School Capital Improvement Project Phase 3 Main Office Renovations
JFK Middle / High School Capital Improvement Project Phase 3 Middle School Main Office Renovations
JFK Middle / High School Capital Improvement Project Phase 3 Middle School Main Office Renovations
JFK Middle / High School Capital Improvement Project Phase 3 Middle School Main Office Renovations
JFK Middle / High School Capital Improvement Project Phase 3 High School Main Office Renovations
JFK Middle / High School Capital Improvement Project Phase 3 High School Main Office Renovations
JFK Middle / High School Capital Improvement Project Phase 3 High School Main Office Renovations
Woodrow Wilson Elementary Capital Outlay Project 2017-2018 Woodrow Wilson * Finish upgrades to stairwells * Hallway handrails * Gym balcony handrails * Completion by June 2018
Woodrow Wilson Elementary Capital Outlay Project 2017-2018 Gymatorium Before:
Woodrow Wilson Elementary Capital Outlay Project 2017-2018 Gymatorium After:
Woodrow Wilson Elementary Capital Outlay Project 2017-2018 Stairwells Before:
Woodrow Wilson Elementary Capital Outlay Project 2017-2018 Stairwells After:
Thank You !!! We look forward to making great progress as we address your District’s needs.