Board Meeting - Project Status Update Hastings-on-Hudson Union Free School District Monday, 9 September 2019 Presented by: Veronica Byrnes - Assistant Vice President – Westchester Office Director Thomas Danis – Project Manager
Hillside ES Infrastructure Project Scope of work: Replace flooring in select classrooms and corridors, replace select windows and storefronts, repoint exterior brick veneer and replace select roofing. Schedule: 60% - Week of 9/2/19 90% - Week of 10/14/19 SED Submission – Week of 11/11/19 Construction duration: Summer 2020
Farragut MS & HS Infrastructure Project Scope of work: Replace boiler, replace select flooring, replace select roofing, repair cornice and parapets, repoint exterior brick veneer and replace the loading dock elevator. Schedule: 30% - Week of 9/9/19 60% - Week of 11/4/19 90% - Week of 12/23/19 SED Submission – Week of 1/13/20 Construction duration: Summer 2020
Hillside ES Addition and Alterations Schedule: 30% - Week of 9/9/19 60% - Week of 11/11/19 90% - Week of 4/13/20 SED Submission – Week of 5/18/20 Construction duration: Fall 2020 – Fall 2021
Farragut MS Auditorium and HS Music Suite Renovations Schedule: 30% - Week of 11/25/19 60% - Week of 2/3/19 90% - Week of 4/13/20 SED Submission – Week of 5/18/20 Construction duration: Fall 2020 - Fall 2021
Questions?