ae senior thesis on mechanical system redesign
play

AE Senior Thesis on Mechanical System Redesign: Applying Chilled - PowerPoint PPT Presentation

AE Senior Thesis on Mechanical System Redesign: Applying Chilled Water VAV and DOAS HVAC system to the Medical Office Building at Johns Hopkins Hospital in Baltimore, MD Presentation Outline Introduction of Building and Thesis


  1. AE Senior Thesis on Mechanical System Redesign: Applying Chilled Water VAV and DOAS HVAC system to the Medical Office Building at Johns Hopkins Hospital in Baltimore, MD

  2. Presentation Outline • Introduction of Building and Thesis – Current HVAC Equipment • HVAC Equipment Selection – Alternative #1, Chilled Water VAV w/ Hot Water Reheat – Alternative #2, DOAS w/ active chilled/heated beams – Parallel System Selection – Enthalpy Wheel Selection • IAQ Comparison • Economic Analysis • Breadth #1, Electrical Distribution Redesign • Breadth #2, Constructability Review • Thesis Conclusion

  3. Building Introduction • New Medical Office Building for JHH Introduction Exist HVAC • Area of 88,000 sq ft Alt #1 VAV • Approximate cost of 15.5 million dollars Alt #2 DOAS Parallel Sys • Four floors, one below grade, three above E-Wheel • Stratified Use IAQ Comp – Basement and First Floor contain examination Economic rooms as well as phlebotomy, radiation, Breadth #1 dialysis etc. Breadth #2 Conclusions – Second and Third Floor contain mostly JHH staff offices and conference rooms. Questions

  4. Building Location

  5. Existing HVAC Equipment • Six rooftop DX packaged units Introduction Exist HVAC – 21,000cfm each at 10% OA Alt #1 VAV – 61 Tons of cooling each Alt #2 DOAS – Ducted together in third floor plenum to serve Parallel Sys entire building E-Wheel • Heating by terminal electric reheat VAV IAQ Comp boxes Economic Breadth #1 – 118 fan power boxes with reheating capability Breadth #2 • One 7.5 Ton FCU & ACCU Conclusions – Serves the elevator mechanical room Questions – Not considered for change in redesign

  6. Alternative #1 VAV system with six rooftop AHUs Introduction • Chilled water used for cooling Exist HVAC – Generated at the South of Orleans Energy Plant Alt #1 VAV – Supply temperature of 38F Alt #2 DOAS – Cost of $10.33 per MMBTU Parallel Sys E-Wheel • Hot water used for terminal reheat IAQ Comp – Steam generated at the South of Orleans Energy Economic Plant Breadth #1 – Cost of $1.08 per therm Breadth #2 Conclusions Questions

  7. Alternative #2 DOAS with three rooftop AHU s Introduction • AHU Differences Exist HVAC – 19,000cfm per unit max Alt #1 VAV – 86 Tons of cooling each Alt #2 DOAS – Temp of SA is 45 F Parallel Sys E-Wheel • Chilled water used for cooling IAQ Comp • AHUs paired with Enthalpy Wheel Economic – Lessens impact of treating all outdoor air Breadth #1 Breadth #2 • Heating and supplementary cooling Conclusions accomplished through parallel system . Questions

  8. Trox Active Beam Section

  9. Parallel System • Active heated and chilled beams Introduction Exist HVAC – Induces room air through a hydronic coil with high Alt #1 VAV velocity supply air within the unit Alt #2 DOAS – Mounted Flush to acoustical ceiling Parallel Sys – Four pipe system allows for heating and cooling E-Wheel • Hot water (150F) supplied from steam to water IAQ Comp HTX in lower level mechanical room Economic Breadth #1 • Cold water (60F) tapped from AHU return line Breadth #2 (52F) and mixed to proper temp. Conclusions Questions

  10. Enthalpy Wheel • DOAS needs heat recovery/rejection device Introduction due to high volumes of OA treated Exist HVAC Alt #1 VAV • Enthalpy Wheel Modeled on Alt #2 DOAS Semco TE3-43 (Total Energy, 43”) Parallel Sys E-Wheel • 80% transfer efficiency for latent and sensible IAQ Comp energy Economic • No measured cross contamination for Breadth #1 Breadth #2 common pollutants (Georgia Tech Research Institute) Conclusions • Able to treat OA to within 2 degrees of Mixed Questions air in standard system

  11. IAQ Comparison • MOB host to many ill patients Introduction Exist HVAC • Many spaces purposely over-ventilated Alt #1 VAV – Waiting rooms Alt #2 DOAS – Examination rooms Parallel Sys E-Wheel • Graphs of CO2 in two sample rooms IAQ Comp – Generation rate of .31 l/s Economic – VAV system at 10% OA Breadth #1 – DOAS at 100% OA Breadth #2 Conclusions Questions

  12. CO 2 Levels in Office 3037

  13. CO 2 Levels in Conference 3080

  14. Economic Analysis • First Cost Introduction Exist HVAC – RS Means used for all equipment Alt #1 VAV – Parallel system priced from similar English units Alt #2 DOAS • Operating Cost Parallel Sys – HAP generated the costs for the Existing System E-Wheel and Alternative #1 IAQ Comp Economic – Alternative #2 was scaled from Alternative #1 by Breadth #1 comparing the amount of fan, pump and chilled Breadth #2 water energy used annually Conclusions Questions

  15. Economic Analysis • Operating Cost • First Cost Introduction – Existing System Exist HVAC – Existing System Alt #1 VAV • $165,509 • $353,460 Alt #2 DOAS – VAV w/ chilled water – VAV w/ chilled water Parallel Sys • $130,004 (-35,500) • $519,881 (+166,000) E-Wheel – DOAS w/ parallel – DOAS w/ parallel IAQ Comp system system Economic • $106,603 (-58,900) • $560,514 (+207,000) Breadth #1 Breadth #2 Conclusions Questions

  16. Payback Period Analysis • Alternative #1 vs. Existing System Introduction Exist HVAC – 4.7 years Alt #1 VAV • Alternative #2 vs. Existing System Alt #2 DOAS Parallel Sys – 3.5 years E-Wheel • Alternative #2 vs. Alternative #1 IAQ Comp – 1.7 years Economic Breadth #1 Breadth #2 Conclusions Questions

  17. Breadth #1 Electrical Distribution System Redesign • Changing away from all electric HVAC Introduction Exist HVAC • Existing Equipment Alt #1 VAV – Two 800Amp panel boards serve the six AHUs Alt #2 DOAS – Seven 225 Amp panel boards are dedicated to the Parallel Sys fan powered VAV boxes E-Wheel • DOAS w/ Parallel System IAQ Comp Economic – Supported equipment lowered to three water Breadth #1 pumps and a three AHU fans Breadth #2 – Require only two 100 Amp panel boards Conclusions • Cost savings of $21,860 Questions

  18. Breadth #2 Constructability Review • Chilled Water and Steam Piping Introduction Constructability Exist HVAC Alt #1 VAV – Connection of the MOB to the South of Orleans Alt #2 DOAS Energy Plant Parallel Sys – Feasibility E-Wheel – Location of piping IAQ Comp – Impact on Construction Economic Breadth #1 Breadth #2 Conclusions Questions

  19. MOB Block Layout

  20. Pipe Location Options • Option one, Buried Piping Introduction Exist HVAC – Formerly vacant block facilitates installation Alt #1 VAV – Will not impact construction of loading dock Alt #2 DOAS • Option two, Above Ground Piping Parallel Sys Recommended E-Wheel IAQ Comp – No conflict with existing buried utilities Economic – Piping is accessible Breadth #1 – Installation cost may be lower without excavation Breadth #2 Conclusions Questions

  21. Schedule Impact of Piping • Minimal schedule impact for the following Introduction reasons Exist HVAC Alt #1 VAV – Easy to coordinate construction since the whole Alt #2 DOAS was block planned as one extension of the JHH Parallel Sys campus E-Wheel – Source of Chilled Water and Steam is very close IAQ Comp to the MOB Economic – Structure between the Energy Plant and the MOB Breadth #1 is very utilitarian Breadth #2 Conclusions Questions

  22. Thesis Conclusions • Alternative #1 Chilled water VAV w/ hot water Introduction reheat Exist HVAC Alt #1 VAV – Initially more expensive but lower operating cost Alt #2 DOAS yields a pay back period of only 4.7 years Parallel Sys – Can use same number and layout for AHUs and E-Wheel VAV boxes IAQ Comp Economic Breadth #1 Breadth #2 Conclusions Questions

  23. Thesis Conclusions • Alternative #2 DOAS with parallel system Introduction Exist HVAC – Highest first cost but lowest operating cost of all Alt #1 VAV systems considered, yields a pay back period of Alt #2 DOAS 3.5 years Parallel Sys – Uses only three AHUs E-Wheel – Paired with enthalpy wheel and parallel system IAQ Comp – Capable of significantly improving IAQ Economic Breadth #1 Breadth #2 Conclusions Questions

  24. Thesis Conclusions • Enthalpy Wheel Introduction Exist HVAC – Lowers overall cooling need dramatically Alt #1 VAV – No risk of cross contamination Alt #2 DOAS • Parallel System Parallel Sys E-Wheel – Active heated and chilled beams IAQ Comp – Can either heat or cool a space Economic • Electrical System Redesign Breadth #1 – With deletion of all electrical HVAC equipment Breadth #2 panel boards drop from nine to two in number Conclusions Questions – Cost savings of $21,860 in equipment

  25. Thesis Conclusions • Constructability Review of steam and chilled Introduction water piping from the energy plant to the MOB Exist HVAC Alt #1 VAV – Minimal schedule impact Alt #2 DOAS – Two easily constructed options Parallel Sys – Block development facilitates coordination with E-Wheel surrounding buildings IAQ Comp Economic Breadth #1 Breadth #2 Conclusions Questions

  26. Questions

Recommend


More recommend