121 3 4 linac hwr half wave resonator
play

121.3.4 Linac HWR (Half-Wave Resonator) SC Acceleration Modules and - PowerPoint PPT Presentation

121.3.4 Linac HWR (Half-Wave Resonator) SC Acceleration Modules and Cryogenics In partnership with: Zachary Conway India/DAE Italy/INFN PIP-II DOE Independent Project Review UK/STFC France/CEA/Irfu, CNRS/IN2P3 12-14 December 2017


  1. 121.3.4 Linac – HWR (Half-Wave Resonator) SC Acceleration Modules and Cryogenics In partnership with: Zachary Conway India/DAE Italy/INFN PIP-II DOE Independent Project Review UK/STFC France/CEA/Irfu, CNRS/IN2P3 12-14 December 2017

  2. Outline • Argonne National Laboratory Organization • Half-Wave Resonator (HWR) cryomodule requirements. • HWR cryomodule design overview. • Scope/deliverables. • Interface control document for the HWR cryomodule. • Fabrication and testing status. • FNAL ESH&Q and Argonne HSE (Health, Safety and Environment) • Risk assessment. • Cost. • Future schedule. • Summary. Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 2 12/12/2017

  3. Argonne National Laboratory - Accelerator Development Group: • Designing, building and commissioning superconducting accelerators since 1977. – All retired group members still work 1+ days per week. • My relevant experience: – Superconducting resonators spanning ion/electron velocities from 0.05c to c. – All superconducting device ancillary hardware. – 6 different types of superconducting resonator cryomodules operating at 2.0 or 4.5 K. – Superconducting accelerator commissioning. Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 3 12/12/2017

  4. Project Organization • Cryomodule and subcomponents designed by FNAL and ANL. • ANL is fabricating and assembling the half-wave resonator (HWR) cryomodule. • At ANL: – Group Leader = Mike Kelly. – Technical Lead = Zack Conway. • FNAL: – Project Liaison: Andrei Lunin (attends weekly status meetings at ANL and provides interface between FNAL/ANL). – Project Engineer: Allan Rowe (L3 & CAM) Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 4 12/12/2017

  5. WBS 121.3.4 Linac – HWR System Req. Charge #2 TC# ED0001313 Tech. Spec. for HWR Cryomodule Cryomodule CM length Q 0 Cavities per # CMs CM type (m) at 2K (10 10 ) 5.93 0.5 HWR 8 1 5.2 0.6 SSR1 8 2 6.5 0.8 SSR2 5 7 3.9 2.15 LB650 3 11 9.5 3 HB650 6 4 The half-wave resonator (HWR) cryomodule contains 8 b = 0.11 HWRs • and 8 solenoids (6 T) with integrated x-y dipole steering coils. • The HWR cryomodule will operate continuous wave with a beam current of 2 – 5 mA to accelerate the beam from 2.1 – 10.3 MeV. Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 5 12/12/2017

  6. 121.3.4 Interfaces – Technical/Schedule Charge #2 Argonne HWR Activities: Top 4 system interfaces with 121.3.4: RF WBS 121.3.10 WBS 121.3.9 Couplers RF Integration RF Power LLRF, including Schedule risk if RF Tuners resonance control FNAL sources are not may impact CM available. Support qualification. WBS 121.3.11 • Cryo Systems Schedule risk if Argonne National D ressed cryo inoperable. Laboratory Internal Cavities • Technical risk if Controls WBS cryo system Bare LMS-PROC-305 Cold Tests introduces Cavities 121.3.4 microphonics Linac/HWR Helium String Vessels Integration HWR CM WBSs interface with nearly all systems and support WBSs. The HWR CM has a detailed interface specification which was used to design and build the module. ANL is providing a fully assembled cryomodule. Dressed cavity interfaces with all critical components in the cryomodule. Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 6 12/12/2017

  7. Charge #2 Interfaces - Technical/Schedule WBS 121.3.4 interface across the PIP-II WBS Matrix • The HWR Cryomodule has a controlled document fully elaborating each interface, TC# ED0001313: Technical Specification for the Interfaces, signed 9 April 2014. Interfaces for the HWR Cryomodule 121.3.4 – HWR Cryomodule 121.3.18 – Vacuum 121.3.9 – RF Power 121.3.19 – General Supt. Serv. 121.3.10 – RF Integration 121.3.20 – Safety Systems 121.3.11 – Cryo Systems 121.3.21 – Test Infrastructure 121.3.16 – Beam Instrum. 121.3.22 – Install., Integ., and Comm 121.3.17 – Control Systems 121.5 – Conventional Facilities • Interfaces extend from the up- to the down-stream beam line flanges. • Technical specification for the interfaces is supplemented with documented ~weekly integration meetings. Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 7 12/12/2017

  8. HWR Cryomodule Design Conduction Cooled Leads (FNAL) Sub-Atmospheric HTXG Output Helium Relief Port Helium Manifold Cooldown Manifold Ti Strong-Back Slow Tuner Gas Heat Half-Wave Resonator Exchanger SC Solenoid Vacuum Manifold 2.2 m X 2.2 m X 6.2 m Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 8 12/12/2017

  9. HWR Cryomodule Reviews Charge #2 • Design/safety reviews for the HWRs and cryomodule were held at Argonne (ANL) with HWR Cryomodule Mock Assembly FNAL and ANL subject matter experts performing the reviews: – HWR review 5/17/2012, and – cryomodule review 5/16/2013. • All design reviews were conducted in compliance with ANL’s procedures, LMS -PROC- 305. • Procurement readiness reviews were carried out at ANL per ANL controls. Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 9 12/12/2017

  10. Cryomodule Testing Cryomodule Alignment Alignment Measurements  D y D x  Cryomodule Assembly Cool Down Data Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 10 12/12/2017

  11. HWR Testing 2 W, Cavity Power Goal Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 11 12/12/2017

  12. HWR Microphonics and RF Power Measured HWR1 Microphonic  All HWR tested have a df df/dP dP ~ Frequency Detuning 11 Hz/mbar . 11  With a helium pressure stability of 0.1 mbar → D f = 1.1 Hz. Hz s rms = 2.5 Hz HWR Cavity Power Time (Seconds) Mechanical Vibration Frequency (Hz) Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 12 12/12/2017

  13. HWR/Solenoid Testing HWR with Solenoid  To decrease the accelerator lattice length we have integrated x-y steering coils into the focusing solenoid package.  Important design issue: – Minimize stray field @ the RF cavity to prevent performance degradation due to trapped magnetic flux.  Measured RF surface resistance with a sensitivity of ± 0.1 nOhm Cavity quenched x10 before and after each quench of the at this field level. cavity.  The cavity was quenched with the solenoid and the steering coils energized.  No quantifiable change to the cavity RF surface resistance. Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 13 12/12/2017

  14. Coupler Hardware Power Coupler Progress  Dressed HWR testing starting soon.  Offline measurements of plated components have been good and are in progress. • Q ~ 10000 or > 80% of calculated Copper Plating Purity Measurement value for pure copper • 10 bellows assemblies are being fabricated and plated at AJ Tuck. Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 14 12/12/2017

  15. Slow Tuners HWR with Slow Tuner  The HWR cryomodule will use → pneumatic slow tuners pneumatic slow tuners have been in operation at Argonne on superconducting cavities since the 1970s.  Slow tuners are install on all HWRs during offline testing. – Slow tuners are actuated through Slow Tuner their full range to verify response. – 162.5 MHz ± 60 kHz is exceeded for all HWRs. – The tuner resolution is < 0.1 Hz, our measurement limit.  Slow tuners are operating as planned and testing has demonstrated this. Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 15 12/12/2017

  16. ESH&Q Charge #5 • Safety is our highest priority. • Work at Argonne is done in compliance with ANL ES&H. • Providing a working piece of hardware goes hand-in-hand with work planning and control at ANL. • FNAL and ANL collaboration on SRF is documented in the FNAL/ANL MOU on SRF Cavity Surface Processing, signed 4/21/2006 with addendum added on 8/15/2014. • Hazards addressed at ANL include: – Chemical safety, – Cryogenic safety, – Pressure systems safety, – Radiation safety, and – Cryomodule component testing and assembly work control documents. Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 16 12/12/2017

  17. Risk: HWR Cryomodule • Risk = HWR Cryomodule does not meet technical performance requirements P * P * Impact WBS / Ops Lab Activity RI-ID Title Technical Impact Impact (months) Probability (k$) 121.03 Linac RT-121-03-06-001 HWR Cryomodule does not meet technical performance 1 (L) - somewhat substandard 217 2.4 20.00% • Risk Mitigation: – The cryomodule is fully tested in PIP2IT prior to use in PIP-II. – All HWRs are tested off-line prior to installation in the cryomodule. • Performance testing: – all HWRs are tested with a high-external-Q coupler to characterize the RF losses, then – all HWRs are tested while fully dressed. • Solenoid field operation: – Two HWRs have been tested with a cryomodule solenoid. No performance limitations found, see slide 12. – All components are tested in a real cryomodule environment prior to installation in the cryomodule. Z. Conway | 121.3.4 Linac – HWR | SC Acceleration Modules and Cryogenics 17 12/12/2017

Recommend


More recommend