CEA PROCUREMENT FOR SARAF PHASE 2 HALF-WAVE RESONATOR TTC2017 - PowerPoint PPT Presentation

CEA PROCUREMENT FOR SARAF PHASE 2 HALF-WAVE RESONATOR TTC2017 meeting C. Madec, G. Ferrand, L. Boudjaoui, N. Misiara February 22nd, 2017 www.cea.fr www.cea.fr | PAGE 1 SARAF PHASE 2 CEA DELIVERABLES SARAF Phase II: accelerator built


  1. CEA PROCUREMENT FOR SARAF PHASE 2 HALF-WAVE RESONATOR TTC2017 meeting C. Madec, G. Ferrand, L. Boudjaoui, N. Misiara February 22nd, 2017 www.cea.fr www.cea.fr | PAGE 1

  2. SARAF PHASE 2 – CEA DELIVERABLES SARAF Phase II: accelerator built in Israel for nuclear physics application producing 40MeV p+ or 35MeV deuterons. Phase I : already in operation with a source, LEBT, RFQ, Cryomodule For Phase II, CEA has been contracted to deliver MEBT and SCL including diagnostics and LCS SARAF-LINAC-SNRC SARAF-LINAC-CEA LCS P.S. P.S. LCS Source HEBT RFQ + LEBT + targets cooling cryogenics C. Madec - CEA procurement for SARAF phase 2 half-wave resonator | PAGE 2

  3. SARAF PHASE 2 CEA SCL DELIVERABLES Cryomodules : 2 low- β 0.091 +2 high- β 0.181 housing – - • SC HWR cavities: 6-7 low- β and 7 high- β with associated couplers and tuners • Solenoid Packages: 6 – 4 - Local Control System - Warm section - Valves box Couplers/Tuners (×26+1) Low- β cavity (×12+1) High- β cavity (×14) SC Magnets (×20) C. Madec - CEA procurement for SARAF phase 2 half-wave resonator | PAGE 6

  4. FULLY EQUIPPED CAVITY - LB Equipped cavity Frequency With helium tank. Tuning System Power coupler C. Madec - CEA procurement for SARAF phase 2 half-wave resonator | PAGE 4

  5. PROCUREMENT The call for tender was divided in 2 lots : - Manufacturing of a prototype Low beta cavity and of 12 (+1) Low beta cavities - Manufacturing of a prototype high beta cavity and of 14 high beta cavities The 2 lots could be ordered to 2 different companies or one. C. Madec - CEA procurement for SARAF phase 2 half-wave resonator | PAGE 5

  6. PROCUREMENT Foreseen manufacturing plan for prototypes : - manufacture of the bare cavities - chemistry, HPR, Test at CEA - Heat Treatment at company - chemistry, HPR, Test at CEA - jacketting of the cavities at company - chemistry, HPR, Test at CEA - acceptance of the cavity Once prototype are accepted, the Production Readiness Review launches the manufacturing of the serie cavities. C. Madec - CEA procurement for SARAF phase 2 half-wave resonator | PAGE 6

  7. PROCUREMENT PLAN • International call for tender • Choice of the vendor on technical and financial offer with validation of SARAF project management (1 or 2 vendor) • Kick off • Review of manufacturing file • Manufacturing of a prototype of each beta • Test and validation of the two prototypes at CEA • Production Readiness Review to launch the serie • Manufacturing of the cavities • Test and validation of the cavities at CEA before assembly in the cryomodule C. Madec - CEA procurement for SARAF phase 2 half-wave resonator | PAGE 7

  8. THANKS FOR YOUR ATTENTION QUESTIONS SARAF-LINAC EDR Cavities | June 20th . 2016 | PAGE 8