SEQ Stabling Program Woombye CRG – May 2016
Project update – May 2016 Construction activities underway: • Drainage (Culvert) • Earthworks • Installation of electrical conduits • Concrete foundations for overhead line equipment (OHLE) • Works pad for turn-out install • Removal of decommissioned power pole
Culvert works
Culvert works – install 4 x 2100 pipes
Culvert works – install 4 x 2100 pipes
Culvert backfill
Drilling for OHLE foundations
Formwork for OHLE foundation
OHLE foundations
UTX conduit install
Decommissioned power pole removal
Earthworks
Earthworks
Project update – May 2016 Upcoming construction works: • Install water and sewerage services • Bulk earthworks continuing • During QR’s pre -scheduled track closure over 4-5 June, CPB will undertake works to: o Install the new turn-out for the facility o OHLE works – including standing masts o Signal works
Project update – May 2016 Upcoming construction works: • Security fence - footings and install • Capping - import and placement • Access road and car park • Track install
Recommend
More recommend