woombye crg may 2016
play

Woombye CRG May 2016 Project update May 2016 Construction - PowerPoint PPT Presentation

SEQ Stabling Program Woombye CRG May 2016 Project update May 2016 Construction activities underway: Drainage (Culvert) Earthworks Installation of electrical conduits Concrete foundations for overhead line equipment (OHLE)


  1. SEQ Stabling Program Woombye CRG – May 2016

  2. Project update – May 2016 Construction activities underway: • Drainage (Culvert) • Earthworks • Installation of electrical conduits • Concrete foundations for overhead line equipment (OHLE) • Works pad for turn-out install • Removal of decommissioned power pole

  3. Culvert works

  4. Culvert works – install 4 x 2100 pipes

  5. Culvert works – install 4 x 2100 pipes

  6. Culvert backfill

  7. Drilling for OHLE foundations

  8. Formwork for OHLE foundation

  9. OHLE foundations

  10. UTX conduit install

  11. Decommissioned power pole removal

  12. Earthworks

  13. Earthworks

  14. Project update – May 2016 Upcoming construction works: • Install water and sewerage services • Bulk earthworks continuing • During QR’s pre -scheduled track closure over 4-5 June, CPB will undertake works to: o Install the new turn-out for the facility o OHLE works – including standing masts o Signal works

  15. Project update – May 2016 Upcoming construction works: • Security fence - footings and install • Capping - import and placement • Access road and car park • Track install

Recommend


More recommend