wheelabrator parc adfer
play

Wheelabrator Parc Adfer Community Liaison Group Meeting 11 Julian - PowerPoint PPT Presentation

Wheelabrator Parc Adfer Community Liaison Group Meeting 11 Julian Harrison, Chair of Community Liaison Group Apo Sarandidis, Senior Project Manager Phil Preece, Plant Manager 24 October 2018 CLG Meeting 11 Agenda 1. Welcome and introductions


  1. Wheelabrator Parc Adfer Community Liaison Group Meeting 11 Julian Harrison, Chair of Community Liaison Group Apo Sarandidis, Senior Project Manager Phil Preece, Plant Manager 24 October 2018

  2. CLG Meeting 11 Agenda 1. Welcome and introductions (chair) 2. Agreement of minutes and actions from the last meeting (chair, all) 3. Project progress update (Wheelabrator technologies) 4. Focus Topic – commissioning operations (Wheelabrator technologies) 5. North Wales Residual Waste Treatment Project – progress update (Steffan Owen, Regional Contracts Manager) 6. Community Benefit Fund – progress update (Steffan Owen, Regional Contracts Manager) 7. Agreement of actions and date of next meeting 8. A.O.B 2

  3. Project Overview Environment & Education  Environmental Benefits  Process ~200K tonnes per year  Renewable energy to power 30,000 homes  Divert 98% of post-recycled waste from landfill  Recycle over 15% of authority waste through metals and aggregate recovery, directly increasing North Wales recycling rates by 7%  Capacity to export heat or steam energy to nearby industrial, commercial or residential users  Achieve the demanding R1 efficiency standard  Educational Facilities & Support (Visitors’ Centre)  For use by the Authority at their discretion and educational groups such as schools, colleges & environmental interest groups 3

  4. Project Overview Economic Benefits  Target Economic Benefits  ~500 construction jobs at peak  30+ full-time jobs once operational  £50,000 Community Benefit Fund during construction; £51.6K Allocated  £230,000 Community Benefit Fund annually once operational  Millions of pounds of positive economic impact, utilising local businesses and suppliers during annual major and routine maintenance projects  £40 million supply chain value over contract term  Reduction in waste disposal costs & Welsh Government funding  Potential for local authority profit sharing 4

  5. Project Progress Update

  6. Project Progress Health & Safety Performance Over 1,000,000 construction hours completed without reportable incident 0 High Risk Working at height, lifting Mandatory operations, interfacing 1 (plant/people), confined spaces, excavations, electrical, 16 Low Risk commissioning 67 Voluntary HSE Observation Cards Manual handling, eye injuries, cuts, abrasions, dropped objects, co- Influence Behaviour ordination of activities, By targeting Unsafe Acts & Conditions, whilst rewarding good knocks, bumps, slips & practices trips 6

  7. Project Update Progress To Date Progress to Date Month Month Month 32 35.5 0 Expected 28/11/2019 99% Complete 7

  8. Project Update First Year - 2017 October 2016 May 2017 September 2017 December 2017 8

  9. Project Update Second Year - 2018 April 2018 January 2018 July 2018 October 2018 9

  10. Project Update Third Year 2019 April 2019 July 2019 September 2019 September 2019 10

  11. Project Update Key Project Achievements  Boiler hydrostatic (pressure) test passed – 2 nd Aug 2018  Bunker completed – 3 rd Sep 2018  Mains electrical connection energized – 23 rd Sep 2018  Start of Cold Commissioning – 20 th Nov 2018  Start of Hot Commissioning – 12 th Jun 2019 11

  12. Project Update Key Project Achievements  Construction Completion Certificate – 21 st Aug 2019  Readiness Test Certificate – 24 th Aug 2019  First Waste Delivery – 27 th Aug 2019  First Waste Fire – 3 rd Sep 2019 12

  13. Project Update Latest Drone Footage 13

  14. Focus Topic - Operations

  15. Operations Staff 15

  16. Operations Staff 63% of appointments are located within a 20 mile radius of Parc Adfer 22% live within the Flintshire Area 16

  17. Operations First Waste Received – Tue 27th August 2019 17

  18. Operations First Fire – 11am Tue 3 rd September 2019 18

  19. Operations Priorities & Key Facts Safety & Environmental compliance remain of the highest priority! There have been no accidents or environmental release incidents Now some key Operational facts & figures . . . 19

  20. Operations Key Facts & Figures  Vehicles movements: • 749 Heavy Goods Vehicles in Sept (less than 30 per day) • Planning estimated a worst case of 67 HGV vehicles per day  Waste characteristics: • Authority waste inputs – 8,080 tonnes • Commercial waste inputs – 5,996 tonnes • Composition and calorific value (‘CV’) close to optimal  Air Pollution Control Residues – 277 tonnes removed  Incinerator Bottom Ash – none removed in Sept during sampling & testing  Boiler performance: • 14,170t of waste = 50,870t of steam production (410°C, 61bar/900psi • 32,960MWth of recovered energy 20

  21. Operations Key Facts & Figures  Emissions to Air: • All CEMS readings within commissioning limits and monthly average for IED compliance . . . more on this later  IBA sampling & testing: • IBA removal commenced for processing into aggregate by offtaker • Commenced using ESA protocol – 12 (of 24) samples taken so far of which 10 results (all passes) have been received . . . more on this later  Flue Gas Treatment (FGT) APCr removal to offtaker commenced – recycling trials also commenced  Rainwater run-off and capture released from attenuation pond after sampling and checking  NRW (EA) has approved R1 status by design 21

  22. Operations IBA – Bottom Ash (Non-Hazardous material)  IBA ≡ c.25% of waste tonnes (3,542t in Sept = c.50,000t/pa)  Metals are separated & recycled  Remaining ash is graded & used as aggregate in road building 22

  23. Operations Continuous Emissions Monitoring (‘CEMS’) Sept 2019 Emissions to Air 100 (as % of Daily ELV) 90 80 70 60 50 50 50 38 40 30 20 20 16 10 1.9 1.3 0 HCl CO Particulate NH3 T.O.C. NOx SO2 23

Recommend


More recommend