Westbury UFSD Capital Improvements Program Construction Update July 10, 2019
Presentation Overview • High School Program – Review of Project Scope – Renderings of Facility – Construction Update – Minority / Women / Local Business Involvement • Middle School Program – Review of Project Scope – Renderings of Facility – Construction Update (Roofing Project / Additions & Alterations)
Project Scope for HS • 14 classroom addition • Cafeteria addition with warming kitchen and connecting link to existing building • Science Lab Alterations • Boilers, pumps and controls • Floors and ceilings • Site Work – parking lot modifications • Masonry Restoration – areas of work impact • Upgrade Electrical Service
T-1 T2 T3 T4 TERRAZZO BASIS OF DESIGN Terrazzo Basis of Design 1 3884 FROST -FORBO MARMOLEUM FRESCO 2 3708 FOSSIL -FORBO MARMOLEUM CONCRETE 33736 GREEN SHIMMER -FORBO MARMOLEUM CONCRETE T-4 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE Enhance Vinyl Tile EVT-1 AD521 LIMO -ALTRO DOLCE TILE EVT-2 AD512 LECHE -ALTRO DOLCE TILE EVT-1 EVT-2 EVT-3 EVT-2 EVT-3 EVT-3 AD605 CILANTRO -ALTRO DOLCE TILE
T-1 T2 T3 T4 TERRAZZO BASIS OF DESIGN Terrazzo Basis of Design 1 3884 FROST -FORBO MARMOLEUM FRESCO 2 3708 FOSSIL -FORBO MARMOLEUM CONCRETE 33736 GREEN SHIMMER -FORBO MARMOLEUM LS-1 LS-2 LS-3 CONCRETE T-43711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE Sheet Linoleum LS-1 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE LS-2 3240 WILLOW -FORBO MARMOLEUM CONCRETE LS-3 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE
Cladding Panel System PRODEX CREAM -PRODEMA PANELS Brick Veneer / Thin Brick PENNSYLVANIA MOLDED -BERKS WATSONTOWN BRICK COMPANY Thin Cast Limestone SMOOTH OAK RIDGE RENAISSANCE MASONRY UNITS ARRISCRAFT INTERNATIONAL BUILDING STONE
Construction Update • Poured concrete for footings and foundation walls for Classroom Addition • Installed in-ground sanitary plumbing piping and electrical conduits in preparation of concrete slab at Classroom Addition • Placed and compacted soil and stone bed in preparation for concrete slab pour • Installed vapor barrier and slab reinforcement • Poured concrete slab for Classroom Addition • Received delivery for cold metal framing and commenced work on perimeter walls
Construction Update • Performed abatement and demolition of boilers: 66% • Formed and poured concrete pads for new boilers: 66% • Received boiler sections and relocated material to boiler room for assembly • Existing sanitary system at Cafeteria Addition remediation: 100% • Installation of new sanitary structures and interconnecting piping at Cafeteria Addition: 95% • Commenced excavation for foundation walls at Cafeteria Addition
Construction Update • Termination of feeders at new transformer in driveway: 60% • PSEG installed pole for new electrical service to transformer • Delivered new panelboards to electric room in basement • Commenced asbestos abatement operations at 2 nd floor classrooms • New Storm Drainage Installation: 60% • Working on drainage system for new courtyard by locker room • Completed foundations and concrete slab for East Connecting Corridor
Classroom Addition – Prep for Pour
Classroom Addition – Slab Pour
Cafeteria Addition – Sanitary System
Boiler Room Operations – Demo & Assembly
Classroom Addition – Interior and Exterior Wall Framing
Electrical Service – Installation of New Transformer Vault
Electrical Service – Switchgear and Conduit Runs
Minority / Women / Local Business Involvement
Minority / Women / Local Business Involvement Elite Construction has been actively meeting with each contractor on a weekly basis to examine their contract and workforce program. The contractors and consultants affiliated with the project are making a “Good Faith Effort” to achieve the District’s goals. • As the project continues, different skills will be required and personnel currently assigned to the project will be modified accordingly. • Individuals are required to obtain their OSHA 10 hour certification and provide to our office. • Individuals are also required to be part of the Local Unions that will man this project: (Carpenters, Brick Masons, Laborers, Abatement, Plumbing, Mechanical, Electrical )
Minority / Women / Local Business Involvement • VRD Contracting, Inc. – General Construction (WBE) – A&S Rebar, Inc. – Rebar Supplier (WBE) – Baybrent Construction – Ceramic Tiling (MBE) – Linda Lee Construction - Taping (WBE) – Park Ave Building Materials – Bldg Materials (MBE) – Island Nursery – Landscaping (WBE)
Minority / Women / Local Business Involvement • Thermo Tech Combustion – Mechanical (HVAC) – DemoTec Mechanical – Boiler Demolition (WBE) • WHM Plumbing & Heating, Inc.– Plumbing – AMG Demolition – Hot Water Tank Removal (WBE) • Roland’s Electric, Inc. – Electrical & Fire Alarm – Advance Sound Co – PA/ Clocks / Smartboards (WBE) – CMT Lighting Co. – Lighting Supplies (WBE)
Project Scope for MS • 12 classroom addition with connection to existing building • Café addition-standard construction • Alterations to existing kitchen/cafeteria • Roof replacement and masonry • Mechanical system: replacement and abatement • Plumbing with abatement • Alterations-Increase corridor width, handicapped toilets and handicapped access throughout building
Project Scope for MS • P/A intercom, clocks, security, F/A • Ceilings, floors, and casework in all spaces • Site Work to include parking lot reconstruction • Upgrade Electrical Service • Abatement in Crawl Space, Floors & Ceilings
Wiedersum Associates Architects PERSPECTIVE VIEW 1
Wiedersum Associates Architects PERSPECTIVE VIEW 2
Wiedersum Associates Architects PERSPECTIVE VIEW 3
Construction Update • Middle School Existing Roof Replacement Project – Contract was awarded to Niko K Construction – Work is scheduled to commence on July 15, 2019 – Contract is scheduled for Summers of 2019 and 2020 – Contract requires abatement, masonry reconstruction and roof replacement of all existing surfaces – Requires coordination with prime contractors on Middle School Additions and Alterations Project • Middle School Additions and Alterations Project – Project is currently out of bidding – Bids due date to be established; Anticipate bid opening prior to August 31, 2019
Westbury UFSD Capital Improvements Program Construction Update Question and Answer
Recommend
More recommend