WASHINGTON BOULEVARD SLIDE STABILIZATION WELCOME to an UPDATE on the Washington Blvd Slide Stabilization Project September 19, 2019 WASHINGTON BOULEVARD SLIDE STABILIZATION Agenda Items We Plan to Cover Introduction of project team


  1. WASHINGTON BOULEVARD SLIDE STABILIZATION WELCOME to an UPDATE on the Washington Blvd Slide Stabilization Project September 19, 2019

  2. WASHINGTON BOULEVARD SLIDE STABILIZATION Agenda – Items We Plan to Cover • Introduction of project team • Project Objective • Overview of decisions made to date • Design Process & Schedule Updates • Next Steps • Questions and Answers

  3. WASHINGTON BOULEVARD SLIDE STABILIZATION Project Team • Tim Beachy, PE – Kitsap County Project Manager • Andy Holmson, PE – Aspect Consulting, Consultant Project Manager • Phil Struck – Struck Environmental, Consultant Environmental and Permitting Lead • David Dinkuhn, PE (not attending) – Parametrix, Consultant Civil Design Lead • Tina Nelson and Doug Bear*

  4. WASHINGTON BOULEVARD SLIDE STABILIZATION Project Objective: • Provide a functional roadway for access to the parcels served by the roadway. • Assurance to residents of an all-weather, stable, and predictable access; meeting the needs of emergency responders and reasonable deliveries. • At a cost justifiable for a local access road.

  5. WASHINGTON BOULEVARD SLIDE STABILIZATION DECISIONS MADE TO DATE: 1. Implement full-slope dewatering: Install horizontal drains near the bottom of the slope to lower the groundwater table 2. Remove load restriction 3. Maintain current roadway geometry 4. Confirmation of decision regarding property acquisitions 5. Construction schedule (late summer 2021)

  6. WASHINGTON BOULEVARD SLIDE STABILIZATION Design Updates • 30% Plans developed • Site plan for permitting and preliminary horizontal drain layout completed • Key decisions made/confirmed – property acquisitions, including derelict home at south side of the project • Permitting issues are controlling and the focus of the design team right now. • 60% Plans expected in November* • 90% Plans in Quarter 1 of 2020*

  7. WASHINGTON BOULEVARD SLIDE STABILIZATION Next Steps • Permitting • Property Acquisitions • Complete Design • Update meeting • Construction late summer 2021

  8. WASHINGTON BOULEVARD SLIDE STABILIZATION In the meantime • Continue monitoring of movements • Aspect - collection of groundwater data • County survey – monitor control points • County maintenance – monitor roadway • Maintain roadway • Electronic Notifications • Who to contact for maintenance?

  9. WASHINGTON BOULEVARD SLIDE STABILIZATION … more Questions … THANKS for COMING Please Sign the SIGN-IN Sheet