Hurricane Matthew Damage: Arlington Lions Club Fishing Pier • Substantially complete; open to public
Hurricane Matthew Damage: County Dock Pier • Under construction; substantial completion in early 2020
Hurricane Matthew Damage: Jim King/Sisters Creek Boardwalk • Under construction; substantial completion in early 2020
Hurricane Matthew Damage: Arlington Lions Club/Blue Cypress Boardwalk • Under construction; substantial completion in Spring 2020
Hurricane Matthew Damage: Northbank Riverwalk – Floating Docks • Currently advertised; bids open Nov. 2019 • Next step: award project to a contractor
Hurricane Irma Damage: Dames Point Fishing Pier • Received Damage Assessment/Repairs Report • Next step: design set to proceed
Hurricane Irma Damage: Ringhaver Park ‐ Gangway • Received Damage Assessment/Repairs Report • Next step: advertisement for bid
Hurricane Irma Damage: St. Johns Marina – Wood Riverwalk • Damage Assessment/Repairs Report in Nov. 2019 • Next step: design/permitting
Hurricane Irma Damage: Metro Park – Fixed Timber Docks • Damage Assessment/Repairs Report – Nov. 2019 • Next step: design/permitting
Joe Carlucci Boat Ramp – Dock Expansion • Project complete and open to public.
Harborview Boat Ramp – Fishing Pier • Project complete and open to public.
Ribault River Preserve – Fishing Pier • Project complete and open to public.
Half Moon Island Boat Ramp • Under construction; substantially complete by end of 2019
Betz ‐ Tiger Point Preserve – Fishing Pier & Kayak Launch • Under construction; substantially complete by Spring 2020
Cedar Point Preserve/Black Hammock Island Trailheads • South Trailhead & Bridge open to public • North Trailhead to be complete in Nov. 2019
Palms Fish Camp – Dock Expansion • Phase 1 complete. • Phase 2 Construction to complete in early 2020
Ribault River – Channel Markers • Design/permitting complete. Bids opened Nov. 2019. Installation anticipated in Spring 2020.
Mandarin Park – Dock Expansion & Kayak Launch • Design/permitting complete. Received 2019 FIND grant for construction. Advertise to bid in Spring 2020.
Oak Harbor Boat Ramp ‐ Dredge • Design/permitting complete. Received 2019 FIND grant for construction. Advertise to bid in Spring 2020.
Zoo Dock • New dock location with water taxi stop; coordinating design with zoo staff. • Potential construction project for next FIND grant cycle.
Downtown Facility: St. Johns Marina ‐ Dredge • Dredge nearing completion; ramp to reopen by end of Nov. 2019
Downtown Facility: Southbank/School Board Kayak Launch • Construction to be completed by Spring 2020
Downtown Facility: Friendship Fountain – 180’ Dock Extension • Anticipate construction in Spring of 2020
Downtown Facility: Riverplace Tower – 210’ Dock Expansion • FY 19/20 City Budget provided additional funding to proceed; anticipate construction in 2020
Downtown Facility: Jackson Street – New Floating Dock • FY 19/20 City Budget provided additional funding to proceed; anticipate construction in 2020
Downtown Facility: Post Street – New Floating Dock • In design/permitting; FY 19/20 City Budget provided additional funding to proceed; anticipate construction in 2020