October 1, 2019 Water Quality Updates
Public Notification of PFOS/PFOA Notification Level Exceedances
Division of Drinking Water Regulatory Update • Revised Notificat ion Levels (NL) for PF AS (August 22, 2019) • PFOS = 13 ng/ L lowered to 6.7 ng/L • PFOA = 14 ng/ L lowered to 5.1 ng/L • Response Levels (RL) for PF AS • PFOS + PFOA = 70 ng/ L • PFOS & PFOA individual RLs expected Fall 2019
SCV Water Response to Date • Received DDW Order to sample 15 wells for 4 Quarters • 14 of the 15 wells were sampled (one was out of service) • 1 well exceeded the RL and was taken out of service • 8 wells exceeded one or both NLs for PFOS and PFOA • Notifications were provided • All wells are being sampled for PFAS (41 in August 2019) • S CV Water PF AS S trike Team Formed • Bench S cale S tudy • Preliminary design and specifications for treatment • Identified and prioritized treatment locations • Public outreach
SCV Water PFAS Results May 2019 (Qtr 1) Prior August 2019 (Qtr 2) Current # S ampled # Exceeded NL/ RL* # S ampled # Exceeded NL/ RL* PFOS 14 7 13 41 23 6.5 PFOA 14 8 14 41 28 5.1 PFOS +PFOA 14 1 70* 41 1 70* • One well which has exceeded the RL remains off • Currently 28 wells have exceeded one or both revised NL • Results pending on 4 wells
N Wellfield PFAS Treatment - Bidding/Purchasing Vessels - Design Work Authorization
SCV Water Response to Date • Received DDW Order to sample 15 wells for 4 Quarters • 14 of the 15 wells were sampled (one was out of service) • 1 well exceeded the RL and was taken out of service • 8 wells exceeded one or both NLs for PFOS and PFOA • Notifications were provided • All wells sampled for PF AS (41 in August 2019) • SCV Water PFAS Strike Team Formed • Bench Scale Study • Preliminary design and specifications for treatment • Identified and prioritized treatment locations • Public outreach
N Wellfield Treatment • Three wells pump up to 6,250 gpm • No property issues or easements needed • Meets CEQA Notice of Exemption requirements
N Wellfield Treatment Item Schedule Engineer Estimate Order Vessels & Pre-Filters October 2019 – March 2020 $1,500,000 Construction February 2020 – June 2020 $2,650,000 Filter Media June 2020 $850,000 Final Design October 2019 – March 2020 $260,000 TOTAL $5,260,000 • Vessel lead time approximately 20 weeks • Bench scale results pending • Additional chloramination system included • CEQA – NOE • Authorization for vessels and final design only at this time
Well Q2 Perchlorate Treatment - Bidding/Purchasing Vessels - Design Work Authorization
Well Q2 Perchlorate History & Timeline • April 2005 Current Results • Results exceeded maximum Date Results Action contaminant level (MCL) (ug/L) May 2019 6 Notified DDW, removed well • October 2005 from service until treatment • Treatment installed Jun 2019 6 Began monthly monitoring • October 2007 Jul 2019 9 • Treatment Removed Aug 2019 13 • Quarterly monitoring S ept 2019 9
Well Q2 Treatment Item Schedule Engineer Estimate Order Vessels & Pre-Filters October 2019 – March 2020 $440,000 Construction March 2020 – June 2020 $260,000 Filter Media June 2020 $330,000 Final Design October 2019 – March 2020 $115,000 * TOTAL $1,145,000 • Vessel lead time approximately 20 weeks • CEQA – NOE • Authorization for vessels and final design only at this time • Updated design estimate of $115,000 is reflected in revised agenda item • S oliciting proposal for Bench S cale testing to look at perchlorate and PF AS
Well Q2 Treatment • Pumps up to 1,250 gpm • No property issues or easements needed • Meets CEQA Notice of Exemption requirements