water and wastewater
play

Water and Wastewater FY21 Operating Budget FY21-25 Capital Program - PowerPoint PPT Presentation

Water and Wastewater FY21 Operating Budget FY21-25 Capital Program B ~ '' ~ ARD I cou TY 1 FLORIDA Capital Program B ~ '' ~ ARD I cou TY 2 FLORIDA Program Elements System Reliability/Quality/Sustainability Septic Tank Elimination


  1. Water and Wastewater FY21 Operating Budget FY21-25 Capital Program B ~ '' ~ ARD I cou TY 1 FLORIDA

  2. Capital Program B ~ '' ~ ARD I cou TY 2 FLORIDA

  3. Program Elements • System Reliability/Quality/Sustainability • Septic Tank Elimination • Regulatory Rule Impacts • Water Supply • Ocean Outfall/Reuse • Biosolids B ~ '' ~ ARD I cou TY 3 FLORIDA

  4. System Reliability/Quality/Sustainability Infrastructure system improvements including water and wastewater treatment, water distribution and wastewater collection and transmission support reliable service goals for our customers. • Reduce sewer backups. • Reduce water and sewer main breaks from aging failures. New fine structures by FDEP for sewer main breaks make this even more critical. • Reduced system-wide boil water events as a result of 4 log virus removal system at water treatment plants 1A, 2A and 3A. • Ensure long term sustainability for water treatment, water distribution, wastewater collection and biosolid disposal. B ~ '' ~ ARD I cou TY 4 FLORIDA

  5. Water Service Reliability Broward County Water and Wastewater Services experienced 82 boil water events due to broken water mains or scheduled maintenance: • 31 were due to pipe failures. • 23 caused by Contractor’s damaging pipes • 28 by scheduled maintenance or tie-ins. There were no system wide boil water alerts. • These breaks affect less than 12.9% of the Broward County’s customer base. • Median impact of 5 service connections per event. Customers affected by scheduled maintenance were notified in advance. • Repairs made within 4 hours average. Boil water notification typically cleared within 48 hours. B ~ '' ~ ARD I cou TY 5 FLORIDA

  6. County-wide Sewered/Unsewered Areas • There are 28 sewer service providers in Broward County. • BC WWS customers make up 11% of the County-wide sewer customers. • The average cost to eliminate septic is between $10,000 to $20,000 per property. 6

  7. Septic Tank Elimination • County wide there are approximately 50,000 parcels on septic tank. • In Broward County’s service areas 2,518 remain. • 5% of our total customer base. • 5% of all septic tanks County wide. • 16,183 septic tanks eliminated since 2001. • Design and construction currently underway for an additional 280 septic tank eliminations. • Design underway for 3BC septic tank elimination project. This project will eliminate 1,840 septic tanks. • Most eliminated by 2024 . B ~ '' ~ ARD I cou TY 7 FLORIDA

  8. Regulatory Rule Impacts 2006 Water Availability Rule • Limits Biscayne Aquifer withdrawals to April 2006 historical withdrawals. • Creates stranded (excess) treatment capacity of 19 MGD. • Requires the County to seek alternative water supplies to meet future demands. • The County has selected the C-51 Reservoir for their alternative water supply needs. 8

  9. Alternative Water Supply C-51 Reservoir • Agreements are in place for the following capacity allocations with Phase I sold out: • Broward County 6 MGD • Sunrise 5 MGD • Hallandale 1 MGD • Dania Beach 1 MGD • Pompano Beach 2 MGD • Margate 2 MGD • Fort Lauderdale 3 MGD • Miami-Dade 15 MGD (pending approval of capacity agreement) • Would capture and store storm runoff that normally flows to the ocean which would recharge Biscayne Aquifer through network of canals. • Received first Consumptive Use Permit (CUP) from South Florida Water Management good for 48 years with an additional allocation of 3 MGD from the South Regional Wellfield. Meets demand for future water supply in the County’s 3A/3BC service area. Consumptive Use Permits in application phase for water service Districts 1A and 2A. • Palm Beach Aggregates finalizing FDEP Loan for $30 million from 2017 SB10. Construction financing commitment was received July 2020. Construction by Palm Beach Aggregates anticipated to begin September 2020. B ~ '' ~ ARD I cou TY 9 FLORIDA

  10. Reuse Successes • Broward County currently has agreements with Palm Beach County, Coconut Creek and North Springs Improvement District to sell reclaim water on a wholesale basis. Broward County has a current agreement with Pompano Beach to purchase wholesale reclaimed water. • The Pompano Beach agreement allows the County to provide retail reclaimed water service for Pompano Highlands and future expansion of reclaimed into Lighthouse Point. A consultant contract has been awarded for the design of the LHP reclaimed line. • Reclaimed treatment plant expansion from 10 MGD to 26 MGD is in construction. The $54 million project has an estimated completion of September 2021. • Reclaimed transmission main construction has started for Palm Beach and North Springs Improvement District. The $27 million, two-phase construction project has an estimated completion of August 2021. 10

  11. Biosolid Disposal • Biosolids are nutrient-rich organic materials obtained from wastewater treatment and can be beneficially used for fertilizer and soil nutrient enhancement. • Broward County will issue a Request for Information (RFI) to determine alternative disposal options and costs associated with biosolids. • The County currently sends its Class B Biosolids to select FDEP-approved land farm sites as well as Waste Management. • A new 3-year sludge hauling contract was issued in January 2020 and increased to $38/ton from $36/ton. B ~ '' ~ ARD I cou TY 11 FLORIDA

  12. RECOMMENDED FY21-FY25 CAPITAL PROGRAM Water Treatment 31 M Distribution and Collection 183 M Wastewater Transmission 27 M Wastewater Treatment 157 M Misc. Projects 64 M Total $462 M 12

  13. Operating Budget B ~ '' ~ ARD I cou TY 13 FLORIDA

  14. System Costs 108.87 106.76 106.94 100.81 100 95.61 94.89 90.73 88.20 87.51 83.61 80.23 78.27 80 73.31 72.20 69.76 $ Millions 60.66 60 System costs = operating + debt service + capital program costs 40 20 0 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 14

  15. Rate Survey Comparative Rate Survey as of 12/31/2019 (Based On Usage of 5,000 Gallons Per Month for a 5/8" meter) Utility Water Sewer Total Davie 40.58 75.68 116.26 Sunrise (outside City) 1,2 51.64 63.10 114.74 Wilton Manors 48.54 50.94 99.48 1 These providers did not have a rate Oakland Park 1, ** 49.49 49.90 99.39 increase in calendar year 2019 Dania Beach 1 35.00 58.82 93.82 Sunrise (inside City) 1 41.32 50.48 91.80 2 These providers charge a 25% surcharge Hollywood 28.74 56.36 85.10 Parkland ** 25.96 58.44 84.40 for supplying customers outside their Fort Lauderdale (outside City) 2 31.18 52.74 83.91 municipal limits. North Lauderdale 1, ** 32.30 47.25 79.55 Note: (Broward County does not apply any Margate (outside City) 2 38.81 39.53 78.34 surcharges to their customers) Hillsboro Beach (Sewer by Broward County) 34.41 41.84 76.25 Average Water & Sewer for Broward Utilities 32.42 43.28 75.70 ** Wholesale wastewater customer of Cooper City 28.64 42.52 71.16 Broward County. Miramar 33.28 37.50 70.78 Coconut Creek 1, ** 40.22 30.56 70.78 Current Broward County (WWS) 27.81 41.84 69.65 Pompano Beach (outside City) 2** 34.13 35.21 69.34 Broward Plantation 24.34 44.70 69.04 County Coral Springs ** 23.60 44.94 68.54 Hallandale Beach 26.06 41.28 67.34 Rate Fort Lauderdale (inside City) 2 24.94 42.19 67.13 Pembroke Pines 30.88 35.74 66.62 North Springs Improvement District 1** 36.09 30.28 66.37 Tamarac 1** 22.39 42.75 65.14 Royal Waterworks ** 27.98 35.92 63.90 Margate (inside City) 2 31.06 31.62 62.68 Lauderhill 1, ** 21.32 37.36 58.68 Pompano Beach (inside City) 2** 27.30 28.17 55.47 Deerfield Beach 1 ** 28.25 24.53 52.78 Coral Springs Improvement District 26.26 26.26 52.52 15

  16. Change for Average WWS Residential Customer 5,000 gallons 5/8” per month In light of the financial impacts from the Covid-19 crisis, staff is recommending no retail rate increases for this year. 16

  17. Recommended FY21 Retail Rates Current Proposed % Δ % Δ % Δ $ Δ Rate Impacts 1,000 gals Total Total Water Sewer Total Total Water/Sewer Customers Residential 5/8 inch 0 $37.67 $37.67 0% 0% 0% $0 $55.31 3 55.31 0% 0% 0% $0 Residential 5/8 inch 69.65 5 69.65 0% 0% 0% $0 Residential 5/8 inch 121.13 10 121.13 0% 0% 0% $0 Residential 5/8 inch 243.40 20 243.40 0% 0% 0% $0 Residential 5/8 inch 356.75 25 356.75 0% 0% 0% $0 Residential 1 inch $117.94 7 $117.94 0% 0% 0% $0 Commercial 5/8 inch 310.46 20 310.46 0% 0% 0% $0 Commercial 1 inch 669.99 44 669.99 0% 0% 0% $0 Commercial 1.5 inch 1,777.67 116 1,777.67 0% 0% 0% $0 Commercial 2 inch Water only Irrigation 5/8 inch 13 $116.33 $116.33 0% 0% $0 Irrigation 1 inch 28 235.70 0% 0% $0 235.70 Irrigation 1.5 inch 72 607.03 607.03 0% 0% $0 Irrigation 2 inch 160 1,321.52 0% 0% $0 1,321.52 $203,301.0 Resale to Coconut Creek 52,370 5 $203,301.05 0% 0% $0 17

Recommend


More recommend