Water and Waste Department Water and Waste Department 2012 CAPITAL WORKS CONSTRUCTION PROGRAM Presentation to Manitoba Heavy Construction Association, March 7 th , 2012 Capital Budget 2012 Capital 2013 to 2017 Capital Projects Summary


  1. Water and Waste Department Water and Waste Department 2012 CAPITAL WORKS CONSTRUCTION PROGRAM Presentation to Manitoba Heavy Construction Association, March 7 th , 2012

  2. Capital Budget 2012 Capital 2013 to 2017 Capital Projects Summary Budget Capital Forecast Land Drainage and Flood Control $10,540,000 $81,981,000 General Capital Fund (Refuse Carts) $7,250,000 - Waterworks System $35,190,000 $149,700,000 Sewage Disposal System $51,400,000 $872,486,000 Solid Waste Disposal System $15,400,000 $122,400,000 Total $119,780,000 $1,144,586,000 2

  3. 3 Capital Budget

  4. Major Projects / Programs 1. Rehabilitation / Renewal a) Watermains, b) Wastewater Sewers, 2. Implementation of Wastewater Treatment System Upgrades, 4. Basement Flood Relief / Combined Sewer Overflow Mitigation. 4

  5. 2012 CAPITAL WORKS CONSTRUCTION PROGRAM Estimated Estimated Tender Land Drainage and Flood Control Project Description Project Contract Closing Date Amount Amount (M/Y) Beaujolais Gate Chamber and Primary Dike Upgrades $3,200,000 $2,500,000 May-12 Pumps Land Drainage and Combined Sewers Woodhaven LDS - Gate Chamber $1,700,000 $1,400,000 Fall 2012 Outfall Gate Structures Land Drainage and Combined Sewers River Gate LDS - Gate Chamber $1,700,000 $1,400,000 Fall 2012 Outfall Gate Structures Wellington Crescent, Chataway, Outfall Rehabilitation $500,000 $400,000 Fall 2012 Empress Outfall Rehabilitation Renfrew, Cornish, Marion, Church $1,600,000 $1,300,000 Fall 2012 Stormont Land Drainage Outfall Outfall Rehabilitation $500,000 $400,000 Fall 2012 Relocation Total $9,200,000 $7,400,000 * TBD To be determined This program summary is provided for information purposes only and is subject to change without notice. Notices of Bid Opportunities will be published at ww.winnipeg.ca/matmgt/bidopp.asp 5

  6. 2012 CAPITAL WORKS CONSTRUCTION PROGRAM Estimated Estimated Tender Land Drainage and Flood Control Project Description Project Contract Closing Date Amount Amount (M/Y) Combined Sewer Flood Relief Jefferson East Combined Sewer Summer $3,000,000 $2,700,000 (Basement Flood Relief) Relief Project Contract # 1 2012 Combined Sewer Flood Relief Jefferson East Combined Sewer $3,300,000 $3,000,000 Fall 2012 (Basement Flood Relief) Relief Project Contract # 2 Ferry Road & Riverbend Combined Sewer Flood Relief Fall / Winter Combined Sewer Relief Project $4,500,000 $4,200,000 (Basement Flood Relief) 2012 / 2013 Contract # 1 Combined Sewer Overflow (CSO) Mager District - Combined / Land Fall / Winter Management Strategy and Drainage Sewer Separation $3,800,000 $3,500,000 2012 / 2013 Miscellaneous Mitigation Works under the CSO program Flood Pumping Station Rehabilitation Control Gate Refurbishments $500,000 $375,000 TBD Flood Pumping Station Rehabilitation Breaker Assessment and Repairs $220,000 $200,000 TBD Structural and Ventilation Flood Pumping Station Rehabilitation $200,000 $165,000 TBD Upgrades Total $15,520,000 $14,140,000 * TBD To be determined This program summary is provided for information purposes only and is subject to change without notice. Notices of Bid Opportunities will be published at ww.winnipeg.ca/matmgt/bidopp.asp 6

  7. 2012 CAPITAL WORKS CONSTRUCTION PROGRAM Estimated Estimated Tender Waterworks System Project Description Project Contract Closing Date Supply & Treatment Amount Amount (M/Y) Aqueduct Bridge and Shoal Lake Aqueduct - Deacon Bridging Foundations where the GWWD $600,000 $550,000 Apr-12 Structure Railway crosses over the Aqueduct Retaining wall construction on Shoal Lake Aqueduct - Riverbank the east riverbank where the $850,000 $750,000 Oct-12 Stabilization at the Seine River Shoal Lake Aqueduct crosses under the Seine River Lining of the interconnecting box Deacon Box Culvert Rehabilitation $2,500,000 $2,000,000 May-12 culverts between Cells 1 and 2 Shoal Lake Aqueduct and Falcon River Aqueduct Bridge and Fall / Winter $1,000,000 $800,000 Diversion Bridges Foundations 2012 Shoal Lake Aqueduct Intake Facility Intake gates and works $800,000 $500,000 TBD Rehabilitation Shoal Lake Aqueduct Underdrain Approx. 11.3 km of pipe to be $200,000 $150,000 Mar-12 Cleaning and Inspection cleaned & inspected Total $5,950,000 $4,750,000 * TBD To be determined This program summary is provided for information purposes only and is subject to change without notice. Notices of Bid Opportunities will be published at ww.winnipeg.ca/matmgt/bidopp.asp 7

  8. 2012 CAPITAL WORKS CONSTRUCTION PROGRAM Estimated Estimated Tender Waterworks System Project Description Project Contract Closing Date Supply & Treatment Amount Amount (M/Y) Water Treatment Plant - Protected Valve chamber modifications and $700,000 $600,000 Apr-12 Connections installation of valves Power Reliability: MacLean Pump MCCs, transformers, transfer Spring / $1,200,000 $800,000 Station MCC Replacement switches, cables Summer 2012 Water Supervisory Control and Data PLCs, installation, programming $2,000,000 $1,500,000 TBD Acquisition (SCADA) Upgrades upgrades Fencing and automated access Waterworks System Security Upgrades gates at 552/598 Plinguet and 360 $700,000 $600,000 Apr-12 McPhillips Total $4,600,000 $3,500,000 * TBD To be determined This program summary is provided for information purposes only and is subject to change without notice. Notices of Bid Opportunities will be published at ww.winnipeg.ca/matmgt/bidopp.asp 8

  9. 2012 CAPITAL WORKS CONSTRUCTION PROGRAM Estimated Estimated Tender Waterworks System Project Description Project Contract Closing Date Distribution Amount Amount (M/Y) Watermain Renewals Contract 1 $1,900,000 $1,600,000 Mar-12 Watermain Renewals Contract 2 $1,650,000 $1,400,000 Mar-12 Watermain Renewals Contract 3 $1,500,000 $1,300,000 Mar-12 Watermain Renewals Contract 4 $1,700,000 $1,400,000 Mar-12 Watermain Renewals Contract 5 $1,900,000 $1,600,000 Mar-12 Watermain Renewals Contract 6 $1,700,000 $1,500,000 Mar-12 Watermain Renewals Contract 7 $1,800,000 $1,500,000 Apr-12 Watermain Renewals Contract 8 $1,300,000 $1,100,000 Apr-12 Total $13,450,000 $11,400,000 * TBD To be determined This program summary is provided for information purposes only and is subject to change without notice. Notices of Bid Opportunities will be published at ww.winnipeg.ca/matmgt/bidopp.asp 9

  10. 2012 CAPITAL WORKS CONSTRUCTION PROGRAM Estimated Estimated Tender Sewage Disposal System Project Description Project Contract Closing Date Treatment Amount Amount (M/Y) North End Water Pollution Control Digester 11 Rehabilitation $5,000,000 $4,500,000 Jul-12 Centre North End Water Pollution Control $300,000 Summer / Fall Grounding Upgrades $400,000 Centre 2012 North End Water Pollution Control Holding Tanks Restoration $2,550,000 $2,550,000 Jul-12 Centre North End Water Pollution Control Main Building Overhead Crane $400,000 $280,500 Jul-12 Centre Replacement North End Water Pollution Control Raw Sewage Pump Supply and $2,500,000 $2,000,000 Mar-12 Centre Delivery North End Water Pollution Control Raw Sewage Pump Installation $8,700,000 $6,900,000 Dec-12 Centre North End Water Pollution Control Refurbishment of Secondary $1,500,000 $400,000 Sep-12 Centre Clarifiers Total $21,050,000 $16,930,500 •TBD To be determined •This program summary is provided for information purposes only and is subject to change without notice. Notices of Bid Opportunities will be published at ww.winnipeg.ca/matmgt/bidopp.asp 10

  11. 2012 CAPITAL WORKS CONSTRUCTION PROGRAM Estimated Estimated Tender Sewage Disposal System Project Description Project Contract Closing Date Treatment Amount Amount (M/Y) South End Water Pollution Control Reliability Upgrades - Electrical $835,000 $592,000 Apr-12 Centre Classification Upgrades South End Water Pollution Control Reliability Upgrades - Ventilation $1,604,000 $1,110,000 Jul-12 Centre & Misc. Upgrades Upgrade/Expansion Project - Design Build Contract for the South End Water Pollution Control Fall / Winter Biologically Active Filtration and $100,000,000 $100,000,000 Centre 2012 High Rate Clarification Process Areas Biosolids - Alternative Disposal Delivery Composting Facility $5,000,000 $4,200,000 TBD and Management System Total $107,439,000 $105,902,000 * TBD To be determined This program summary is provided for information purposes only and is subject to change without notice. Notices of Bid Opportunities will be published at ww.winnipeg.ca/matmgt/bidopp.asp 11

  12. 2012 CAPITAL WORKS CONSTRUCTION PROGRAM Estimated Estimated Tender Sewage Disposal System Project Description Project Contract Closing Date Collection Amount Amount (M/Y) Perimeter Road Pumping Station - Arc Flash Hazard Analysis and Arc Flash Hazard Analysis and $300,000 $250,000 TBD Remediation Mitigation Arc Flash Hazard Analysis and Arc Flash Hazard Analysis and Mitigation Flood and Wastewater $300,000 $225,000 TBD Remediation Pumping Stations Lift Station Upgrading Montcalm Lift Station upgrading $1,800,000 $1,500,000 Mar-12 Waverley West Interceptor - Waverley West Interceptor Sewer $635,000 TBD Closed Phase 4 South Leg Total $3,035,000 $1,975,000 * TBD To be determined This program summary is provided for information purposes only and is subject to change without notice. Notices of Bid Opportunities will be published at ww.winnipeg.ca/matmgt/bidopp.asp 12