walkers line and no 2 side road intersection improvements
play

Walkers Line and No.2 Side Road Intersection Improvements and - PowerPoint PPT Presentation

Walkers Line and No.2 Side Road Intersection Improvements and Gravel Parking Lot Construction Public Information Centre (PIC) September 28, 2016 Project Team City of Burlington John Taylor , Councillor, Ward 3 Scott Hamilton , Manager of


  1. Walkers Line and No.2 Side Road Intersection Improvements and Gravel Parking Lot Construction Public Information Centre (PIC) September 28, 2016

  2. Project Team City of Burlington John Taylor , Councillor, Ward 3 Scott Hamilton , Manager of Design and Construction Dave Meyer , Project Manager Tom Georgiadis , Contract Administrator Ana Maria Troncoso , Senior Design Technician Kaylan Edgcumbe , Senior Transportation Planner Conservation Halton Angela Mourao , Parks Planner/Landscape Architect Craig Machan , Area Manager, Hilton Falls, Rattlesnake Point and Mount Nemo

  3. Walkers Line and No.2 Side Road Intersection Improvements and Gravel Parking Lot Construction 2. PROJECT OVERVIEW

  4. Project Overview • Road reconstruction with minor intersection realignment and proposed new stop signs on the west intersection. • Proposed new gravel parking lot for 20 cars, with 3 vegetated swales. • Replacement of the 450mm CSP culvert and ditch realignment. • Proposed 1.50m gravel and paved shoulders, erosion control, re-grading and seeding existing shoulder.

  5. Existing Conditions Prop ropos osed T- Inte ntersectio tion and St an Stop op Si Sign Prop ropos osed E Eros rosion C Con ontrol rol Prop ropos osed R Re-gradi ding ng and S d Seed d Area ea

  6. Cross-Section

  7. Vegetated Swale

  8. Project Budget Road Intersection $290,000 Gravel Parking Lot $100,000 TOTAL BUDGET $390,000 Tentative Schedule Public Information Centre: September 2016 Road Construction: 2017 Parking Lot Construction 2017 Timing subject to co-ordination with Niagara Escarpment Commission permit.

  9. PIC LOCATION Date: Wednesday, September 28, 2016 Location: Conservation Halton, Grindstone Room 2596 Britannia Road West Time: 6:00 pm to 7:30 pm.

  10. Communications • Keep up to date on the project by: – Visiting project webpage (Coming Soon) – Project updates by ad mail – Sign up for email notifications – Contact project team

  11. Project Team Contacts City of Burlington John Taylor 905-335-7600 Ext. 7459 Councillor Ward 3 John.Taylor@burlington.ca Dave Meyer 905-335-7600 Ext. 7818 Project Manager Dave.Meyer@burlington.ca Ana Maria Troncoso 905-335-7600 Ext. 7665 Senior Designer AnaMaria.troncoso@burlington.ca Conservation Halton Angela Mourao 905-336-1158 Ext. 2332 Parks Planner/Landscape Architect amourao@hrca.on.ca Craig Machan 905-854-0262 Ext. 3104 Area Manager, Hilton Falls cmachan@hrca.on.ca

  12. Comments • Take a project information package: – Fill out comments form here or submit later • Project team contacts provided in handout