Vision One91 BURNSVILLE HIGH SCHOOL BOARD UPDATE MAY 28, 2015 Mark Hayes Mark Hovelson Eric Anderson Andy Hoffmann ATS&R Wenck
Vision One91 – B.H.S. AGENDA Construction Phasing / Bid Packages Bid Package #1 – Scope Project Update Site West Classroom / Tech. Addition Activity Center Addition Science / Classroom Addition Preliminary Milestone Dates
Construction Phasing / Bid Packages Bid Package Issue Bid Award #1 – Annex Alts./ 4/30/15 5/21/15 5/28/15 Demo./ Site Utilities #2 - Precast Wall 5/15/15 6/4/15 6/11/15 Panels #3 - Footings / Conc. 7/1/15 7/28/15 8/13/15 / Steel / Conc. Blk. #4 - Finishes / Mech. 9/1/15 9/24/15 10/8/15 / Elec. / Tech.
Burnsville High School – Bid Package #1 Classroom Construction Auto Trades Body Auto Shop Tech Lab
Burnsville High School – Bid Package #1 Tech Lab Elevation Existing Elevation
Construction Staging Loss of 360 – 400 parking spaces during construction
Existing Site Site Plan
Site Plan 111 8 18 245 PARKING STAFF 250 101 STUDENT 637 VISITOR 14 26 BCTV 10 TOTAL 911 BUSES 31 402 SP. ED. 11
Site Plan WEST ADDITION
Site Plan ACTIVITY CENTER
Site Plan SCIENCE ADDITION
Burnsville High School – Project Scope Science Addition -Classrooms West Addition -Science -Classrooms Labs -Commons -FTLA -Tech Ed -Staff Planning -CNA Lab -FTLA -Pool Locker Update Piano Lab Mechanical -Sheet Music -Ice Storage Storage -Chiller -Instrument Storage Activities Addition B.E.S.T. -Health Classrooms -PE Lockers -Community Lockers -Athletic/ PE
Burnsville High School – West Addition Main Level
Burnsville High School – West Addition Tech Ed House
Burnsville High School – West Addition Administration
Burnsville High School – West Addition Classroom/ FTLA
Burnsville High School – West Addition Upper Level
Burnsville High School – West Addition Lower Level
Burnsville High School – West Addition Perspective
Burnsville High School – West Addition Perspective
Burnsville High School – West Addition Perspective
Burnsville High School – Activities Addition Main Level
Burnsville High School – Activities Addition Upper Level
Burnsville High School – Activities Addition Perspective
Burnsville High School – Activities Addition Perspective
Burnsville High School – Science Addition Main Level
Burnsville High School – Science Addition Upper Level
Burnsville High School – Science Addition Perspective
Preliminary Milestone Dates Task Start Finish Bid Package #1 Mobilization 6/15/15 Site Demolition 6/20/15 8/21/15 Annex Renovations 6/20/15 10/23/15 Reloc. of Underground Utilities 6/20/15 8/7/15 Reloc. of Long Jump/Pole Vault 6/20/15 8/21/15 Precast Wall Panel Erection 12/15/15 1/15/16 Roofing 1/4/16 2/15/16 Building Enclosure 2/15/16 3/15/16 Rough Interior Work 1/15/16 5/15/16 Interior Finishes 3/1/16 8/18/16 Parking Lots/Site Improvements 6/1/16 8/18/16 Project Substantial Completion 8/19/16