US 20 & SR 601 STAKEHOLDER MEETING JUNE 17, 2020
AGENDA Updates Since April 2019 Meeting Design and Maintenance of Traffic (MOT) Considerations Project Schedule and Next Steps Questions/Discussion 2 | Huron County| US 20 & SR 601
UPDATES April 2019 – Applied for Safety funds for roundabout May 2019 – Received approval for roundabout June 2019 – TranSystems hired to design project 3 | Huron County| US 20 & SR 601
PROPOSED ROUNDABOUT 4 | Huron County| US 20 & SR 601
GEOMETRIC DESIGN CONSIDERATIONS Truck Apron Curb Cross Slope 2” Rolled Curb 1% instead of 2% (typically 3”-4”) 5 | Huron County| US 20 & SR 601
DESIGN VEHICLE CONSIDERATIONS WB-62 Semi-Truck Standard Design Truck • Race Track Vehicles Measured 5 different truck/camper/trailer • vehicle combinations NASA – Transport Vehicle Farm Machinery 6 | Huron County| US 20 & SR 601
WB-62 SEMI-TRUCK 7 | Huron County| US 20 & SR 601
RACE TRACK TRUCK/TRAILER COMBO 8 | Huron County| US 20 & SR 601
RACE TRACK TRUCK/TRAILER COMBO 9 | Huron County| US 20 & SR 601
RACE TRACK TRUCK/TRAILER COMBO 10 | Huron County| US 20 & SR 601
RACE TRACK TRUCK/TRAILER COMBO 11 | Huron County| US 20 & SR 601
NASA – TRANSPORT VEHICLE 12 | Huron County| US 20 & SR 601
MOT CONSIDERATIONS Full intersection closure Partial intersection closure Impact to local businesses Constructability Weather Full intersection closure chosen to minimize construction timeframe 13 | Huron County| US 20 & SR 601
DETOUR ROUTES 14 | Huron County| US 20 & SR 601
CONSTRUCTION/MOT PLAN Intersection will close in September (after Labor Day) 70-day closure Intersection will open mid-November Minimizes impacts to large events and tourist destinations 15 | Huron County| US 20 & SR 601
SCHEDULE/NEXT STEPS Activity Begin End Design 2019 2021 Public Involvement June 22, 2020 July 31, 2020 Right-of-Way 2020 2021 Utility Relocations 2020 2021 Construction 2021 2022 16 | Huron County| US 20 & SR 601
QUESTIONS ? 17 | Huron County| US 20 & SR 601
PROJECT INFORMATION & COMMENT Project Information can be found at: https://www.transportation.ohio.gov/wps/portal/gov/odot/proje cts/projects/110357 Comments can be submitted in writing after the meeting to: Don Rostofer at: Donald.Rostofer@dot.ohio.gov or On the Project Card at: https://www.transportation.ohio.gov/wps/portal/gov/odot/proje cts/projects/110357 18 | Huron County| US 20 & SR 601
NEXT STEPS Public Involvement Comment Period – June 22 nd to July 31 o Detailed Design – 2019 to 2021 o Real Estate Acquisition – Fall of 2020 to Spring of 2021 o Utility Relocations – 2020 to 2021 o Construction – August 2021 to June 2022 o 19 | Huron County| US 20 & SR 601
ODOT CONTACTS Bob Weaver, District Deputy Director– (419) 207-7002 Bob.Weaver@dot.ohio.gov o Julie Cichello, District Traffic Engineer – (419) 207-7168 Julie.Cichello@dot.ohio.gov o Kenny Knapp, Project Manager – (419) 207-7175 Kenneth.Knapp@dot.ohio.gov o Dustin Vousden, District Design Engineer – (419) 207-7136 Dustin.Vousden@dot.ohio.gov o Brad Corder, District Real Estate Administrator, (419) 207- 7111 o Bradley.Corder@dot.ohio.gov Don Rostofer, District Environmental Coordinator – (419) 207-7178 o Donald.Rostofer@dot.ohio.gov Kaitlyn Thompson, District Public Information Officer – (419) 281-0513 o Kaitlyn.Thompson@dot.ohio.gov Crystal Neelon, District Public Information Officer – (419) 281-0513 o Crystal.Neelon@dot.ohio.gov 20 | Huron County| US 20 & SR 601