US 20 & SR 601 STAKEHOLDER MEETING JUNE 17, 2020 AGENDA Updates Since April 2019 Meeting Design and Maintenance of Traffic (MOT) Considerations Project Schedule and Next Steps Questions/Discussion 2 | Huron County| US 20 & SR 601


  1. US 20 & SR 601 STAKEHOLDER MEETING JUNE 17, 2020

  2. AGENDA Updates Since April 2019 Meeting Design and Maintenance of Traffic (MOT) Considerations Project Schedule and Next Steps Questions/Discussion 2 | Huron County| US 20 & SR 601

  3. UPDATES  April 2019 – Applied for Safety funds for roundabout  May 2019 – Received approval for roundabout  June 2019 – TranSystems hired to design project 3 | Huron County| US 20 & SR 601

  4. PROPOSED ROUNDABOUT 4 | Huron County| US 20 & SR 601

  5. GEOMETRIC DESIGN CONSIDERATIONS Truck Apron Curb Cross Slope 2” Rolled Curb 1% instead of 2%   (typically 3”-4”) 5 | Huron County| US 20 & SR 601

  6. DESIGN VEHICLE CONSIDERATIONS  WB-62 Semi-Truck Standard Design Truck •  Race Track Vehicles Measured 5 different truck/camper/trailer • vehicle combinations  NASA – Transport Vehicle  Farm Machinery 6 | Huron County| US 20 & SR 601

  7. WB-62 SEMI-TRUCK 7 | Huron County| US 20 & SR 601

  8. RACE TRACK TRUCK/TRAILER COMBO 8 | Huron County| US 20 & SR 601

  9. RACE TRACK TRUCK/TRAILER COMBO 9 | Huron County| US 20 & SR 601

  10. RACE TRACK TRUCK/TRAILER COMBO 10 | Huron County| US 20 & SR 601

  11. RACE TRACK TRUCK/TRAILER COMBO 11 | Huron County| US 20 & SR 601

  12. NASA – TRANSPORT VEHICLE 12 | Huron County| US 20 & SR 601

  13. MOT CONSIDERATIONS  Full intersection closure  Partial intersection closure  Impact to local businesses  Constructability  Weather Full intersection closure chosen to minimize construction timeframe 13 | Huron County| US 20 & SR 601

  14. DETOUR ROUTES 14 | Huron County| US 20 & SR 601

  15. CONSTRUCTION/MOT PLAN  Intersection will close in September (after Labor Day)  70-day closure  Intersection will open mid-November  Minimizes impacts to large events and tourist destinations 15 | Huron County| US 20 & SR 601

  16. SCHEDULE/NEXT STEPS Activity Begin End Design 2019 2021 Public Involvement June 22, 2020 July 31, 2020 Right-of-Way 2020 2021 Utility Relocations 2020 2021 Construction 2021 2022 16 | Huron County| US 20 & SR 601

  17. QUESTIONS ? 17 | Huron County| US 20 & SR 601

  18. PROJECT INFORMATION & COMMENT Project Information can be found at: https://www.transportation.ohio.gov/wps/portal/gov/odot/proje cts/projects/110357 Comments can be submitted in writing after the meeting to: Don Rostofer at: Donald.Rostofer@dot.ohio.gov or On the Project Card at: https://www.transportation.ohio.gov/wps/portal/gov/odot/proje cts/projects/110357 18 | Huron County| US 20 & SR 601

  19. NEXT STEPS Public Involvement Comment Period – June 22 nd to July 31 o Detailed Design – 2019 to 2021 o Real Estate Acquisition – Fall of 2020 to Spring of 2021 o Utility Relocations – 2020 to 2021 o Construction – August 2021 to June 2022 o 19 | Huron County| US 20 & SR 601

  20. ODOT CONTACTS Bob Weaver, District Deputy Director– (419) 207-7002 Bob.Weaver@dot.ohio.gov o Julie Cichello, District Traffic Engineer – (419) 207-7168 Julie.Cichello@dot.ohio.gov o Kenny Knapp, Project Manager – (419) 207-7175 Kenneth.Knapp@dot.ohio.gov o Dustin Vousden, District Design Engineer – (419) 207-7136 Dustin.Vousden@dot.ohio.gov o Brad Corder, District Real Estate Administrator, (419) 207- 7111 o Bradley.Corder@dot.ohio.gov Don Rostofer, District Environmental Coordinator – (419) 207-7178 o Donald.Rostofer@dot.ohio.gov Kaitlyn Thompson, District Public Information Officer – (419) 281-0513 o Kaitlyn.Thompson@dot.ohio.gov Crystal Neelon, District Public Information Officer – (419) 281-0513 o Crystal.Neelon@dot.ohio.gov 20 | Huron County| US 20 & SR 601