Update on ORPC Alaska Projects Alaska Hydrokinetic Technical Conference October 26, 2011 Monty Worthington, Director – Project Development, ORPC Alaska
Ocean Renewable Power Company Overview • Maine-based developer of Founded in 2004 with executive • hydrokinetic power systems and offices in Portland, Maine and projects that turn ocean and project offices in Eastport river currents into reliable supplies of clean, predictable Maine, and Anchorage, AK electricity • 28 employees, 4 in Alaska Proprietary technology • including OCGen™, TidGen™, and RivGen™ power systems Project sites in Cook Inlet and • Nenana, AK, and Eastport, ME, and partnering on projects in Nova Scotia • Beta Turbine Generator Unit (TGU) deployed March 2010 - October 2011 2 2
Beta TidGen ™ Power System Largest ocean energy power device ever installed in the U.S. 3 3
ORPC Power Systems Beta TGU 600 kW OCGen™ 150 kW TidGen™ 50 kW RivGen™ 2012 2014 2012 4 4
Why Cook Inlet? • 4 th largest tidal range in the world up to 12 meters (40 feet) Current velocities up to 10 knots Tidal resource is in the vicinity of electrical infrastructure - the Railbelt Grid Staggered tidal phases can lead to continuous power production Univ. of Alaska-Anchorage Modeling 5 18
Cook Inlet Tidal Current Phases 6 6
ORPC Alaska’s Cook Inlet project sites • Began Project in northern Cook Inlet 2007, narrowed focus to Fire Island in 2009 • Began East Foreland Project in 2010, now the priority Pilot Project site 7 7
• Cook Inlet Tidal Energy Project 2 nd FERC • East Foreland Tidal Energy Project FERC Preliminary Permit received 10/10 Preliminary Permit received 3/11 8 8
Fire Island 9 9
Resource at Fire Island Site Summary Statistics Reported at middle of water column Site ADM-1 ADM-2 ADM-3 Cook Velocity NaN NaN NaN NaN Mean speed (m/s) 1.05 1.08 1.12 1.28 Max sustained speed (m/s) 2.73 2.93 2.91 2.78 Ebb/flood asymmetry 0.97 0.95 0.96 0.85 Vertical shear (m/s per m) 0.0108 0.0236 0.0178 0.028 Power NaN NaN NaN NaN Mean power density (kW/m 2 ) 1.28 1.51 1.34 1.71 Ebb/flood asymmetry 0.91 0.91 0.88 0.55 Direction NaN NaN NaN NaN Principle axis (deg) 139 132 137 66 Standard deviation (deg) 11 6 12 4 Ebb/flood asymmetry (deg) 15.1 4.1 26.3 6.2 10 10
Cook Inlet Environmental Studies Pre and post deployment fish studies Pre and post deployment Beluga monitoring • Visual monitoring • Passive Acoustic Monitoring Sediment transport modeling • Working with UAA researchers to develop modeling and study plan 11 11
Passive Hydroacoustic Monitoring • ORPC Project, DOE funded • Directional Autonomous Seafloor Acoustic Recorders (DASARs) - localize beluga vocalizations • Team CIBA collaboration (ADF&G, NMML, UAF, UH) • Ecological Acoustic Recorder (EAR) and C- POD • used by Team Cook Inlet Beluga Acoustics Whale photo credit: NMFS, AK regional office 12 12
East Foreland, Alaska Tidal Energy Project 13 16
Work Completed at East Foreland in 2011 • Circulation modeling performed at UAA • Stationary ADCP survey for full lunar cycle performed at five locations Have two weeks of data from • one site • 2 ADCPs yet to be recovered. They contain more than six weeks of data. • Potential interconnect sites have been identified. • Collaborating with HEA on project development • UAA flume work continues. 14 17
ADCP Data from Northernmost Site 15 19
Work Planned for 2011-2012 at East Foreland • Recover ADCPs and analyze data • Do additional modeling calibration at UAA with ADCP data • Work with NOAA/AEA on modeling effort and provide input on ADCP locations for spring 2012 deployment at 10 sites • Scope and initiate environmental studies including beluga monitoring and pre-deployment fish studies • Collect geophysical and geotechnical data using multi-beam and side scan sonar, sub-bottom profiler, magnetometer etc. • Test RivGen™ bottom support frame at Nikiski and initiate local contractor relationships through this work • Work with HEA towards Power Sales Agreement • Submit FERC Draft Pilot License Application 16 22
East Foreland Tidal Energy Project Deployment Schedule, 2013-2016 2013 2014 2015 2016-2017 Number Project of TGUs Output Cook Inlet (1) TidGen™ (3) TidGen™ 4 600 kW TidGen™ device devices Array Project Cook Inlet (1) 4-TGU 4 600 kW OCGen™ OCGen™ Project module or (2) 2-TGU OCGen™ module East (22) 175kW TGU’s 22 3,850 kW Beta TiGen ™ Power System Foreland in Array of Pilot OCGen™ modules Project and/or TidGen™ Largest ocean energy device Buildout devices ever installed in the U.S. Additional 150kW 450kW 600 kW 3,850kW 30 5.05 MW capacity installed 17 23
RivGen™ Commercialization Project 18 www.orpc.co 25
RivGen™ Commercialization Project • Bottom Support Frame (BSF) and Anchor fabrication complete, testing in next two weeks at Nikiski • RivGen™ TGU under construction and scheduled for testing in Eastport in March 2012 • Investigating potential sites for “clean water” RivGen™ Power System testing in 2012 19 26
RivGen™ Commercialization in Nenana • 2008-2010 • Site Characterization • 2011 • Baseline Fish Study Debris Detection System Test • • Anchor Deployment Bottom Support Frame (BSF) • • 2012 Baseline Fish Study • • Debris Diversion Device • 2013 • RivGen TM Power System Deployment 20 20
Anchor Deployment & Debris Detection System Validation • The bottom-mounted Debris Detection System, designed by AHERC, was built, deployed, and calibrated • The RivGen TM anchoring system was designed and built. Initial anchor tests exceeded design criteria 21 21
RivGen TM Commercialization Schedule Conditions Year Location Activities and Tests High suspended sediment and Fabrication of bottom support frame and anchoring system, debris load, fresh water, Tanana River at 2011 baseline fish studies, deployment and retrieval of anchors, design, seasonal ice cover Nenana, Alaska build, and validation of debris detection system High suspended sediment load, Initial testing of the bottom support frame in 2011-2012; possible low debris load, marine, bi- East Foreland near location for 2011-2012 Nikiski, AK directional flow RivGen TM device test in 2012 Clear water, no debris, ice-free Testing of first RivGen TM TGU at ORPC’s Maine testing facility; year round, marine, bi- Cobscook Bay near 2012 verification of TGU performance in marine environment; surface Eastport, Maine directional flow deployment High suspended sediment and debris load, fresh water, Testing of a bottom-mounted debris diversion device and debris Tanana River at 2012 seasonal ice cover detection system; sedimentation studies; baseline fish studies Nenana, Alaska Low suspended sediment load, Testing and verification of RivGen™ Power System for low low debris, ice-free except 2012-2013 Igiugig, AK (or other clear water river site) breakup, freshwater suspended sediment river sites High suspended sediment and Testing and Verification of RivGen™ Power System for high debris load, fresh water, Tanana River at 2013-2014 Nenana, AK seasonal ice cover suspended sediment and debris river sites 22 22
UAA Suspended Sediment Flume $240,000 DOE grant to • ORPC is funding flume studies at UAA to circulate high silt content water and test critical device components Will test several types • of bearings/seals in Cook Inlet water samples Will determine best • suited bearing/seals and maintenance cycles 23 21
Economic Impact Central Alaska Partners, Contractors and Consultants Fairbanks Region Fairbanks MatSu Borough ABS Alaskan, Inc. TerraSond Ltd. Airport Equipment Rentals Nenana Alaska Rubber & Rigging Inc. Boat Shop Fairbanks Paint and Glass Co. Jon’s Machine Shop Municipality of Anchorage University of Alaska Fairbanks ORPC Alaska Office Alaska Industrial Hardware Alaska Serigraphics Arctic Office Products GCI 40 40 HDR/DTA Holloway Associates, LLC Kinetic Laboratories Inc LGL Limited Marsh Creek, LLC Anchorage Northwest Arctic Aviation PND Engineers, Inc. Restoration Science & Engineering Kenai The UPS Store Kenai Peninsula Borough Aquacoustics, Inc. Homer Engineering and Technical Service, Inc. Homer Electric Association Specialty Electric Supply 24 24
Thank You! 25 www.orpc.co 33
Recommend
More recommend