Trial Assembly Structure at Ash River TASAR Summary William Miller University of Minnesota March 11 th , 2016
Status TASAR • We have a preliminary design completed for the TASAR • Final design and approval by the project and UMN May • Structure completed by September WHM- March 10, 2016 2
Trial Assembly Schedule • Goal is to test assembly procedures and mechanical connections and materials handling equipment – June-Design review for Rail system – October-Install rail system – Mid-October ready for prototype CPA and field cage to trail assembly – Flexibility in the schedule as parts become available • Need to adjust current schedule to show that full scale trial assembly will not happen with production pieces in May/June 2017 all testing will be with prototype/pre-production pieces that meet approved design specification (No APA’s) WHM- March 10, 2016 3