Tideway Community Liaison Working Group Heathwall Pumping Station Kirtling Street Tunnels 1
Agenda • Tideway Central Project Overview – if required • Heathwall Site Progress and Programme • Kirtling Street Site Progress and Programme • Site Air Quality and Noise Data – shortened • Community Relations • Other items / Actions from Last Meeting - Notifications - Greenwall - Settlement 2
Tideway Central – Project Overview Justin in Feltham ham – Environment ironmental al Ad Adviser iser 3
Bazalgette’s interceptor sewers 4
5
Project Overview • Heathwall Pumping Station - Existing Combined Sewer Outfall into Thames. - Diversion of existing CSO to allow it to operate while we work. - Construction of cofferdam and placement of infill material to construct interception chamber and shaft. - Construction of CSO Shaft to connect new Tunnel. • Kirtling Street - Drive site for construction of tunnel - Services and materials for TBM. - Removal of excavated material from TBM. 6
HEATHWALL PUMPING STATION UPDATE Nick k Rowlan wland d – Marine ine Works ks Sub Agent ent Landside Works and Marine Works 7
Heathwall Pumping Station Works SWSR Existing Air-Treatment Chamber CSO Shaft Pumping Chamber Station Main Tunnel PS Chamber PS Shaft 8
Works to date • Diversion of existing Pumping Station Outfall to new location to allow us to construct our cofferdam. • Construction of UKPN Substation for HEAPS operation. • Installation of ground water wells and pump test. 9
Marine Works • Ongoing – clearance of marine pile locations 10
Marine Works – High Water Looking West 11
Marine Works – High Water Looking East 12
Marine Works – Low Water Looking West 13
Marine Works – Low Water Looking East 14
Marine Works • Piles delivered by river – next week • Vibro piling undertaken during core working hours 08:00 – 18:00 • Impact Piling 5 hours per day – 20 hours per Week • Noise Monitoring ongoing 15
Marine Works – Interception Shaft Excavation 16
Heathwall Final Layout 17
Heathwall Street Programme • From Mid to Late June - Complete pile line clearance, pump station outfall demolition activity - Begin installation of cofferdam. • July & August - Continuation of cofferdam installation - Piling for landside CSO Shaft and chambers 18
KIRTLING STREET RECENT WORKS Al Alber erto to Gonzal nzalez ez – Civi vils ls Work rks s Site Agent nt Drive Shaft and Tunnel Boring Machine Launch Adits 19
We have a shaft 20
Launch Adit Construction 21
Launch Adit Construction 22
Breaking Out D-Wall 23
Ground-borne Vibration 24
Building an adit 25
Building an adit 26
Building an adit 27
KIRTLING STREET RECENT WORKS Russell ssell Brown wn – Tunnel nnel Senior nior Projec oject t Manager ager Tunnel Boring Machine, Gantries and Conveyor 28
Tunnel Boring Machine (TBM) Delivery 29
Tunnel Boring Machine (TBM) Delivery 30
TBM Assembly 31
TBM into the Shed 32
TBM into the Shed 33
TBM lowered into the launch adit 34
TBM lowered into the launch adit 35
TBM lowered into the launch adit 36
TBM Gantries 37
Conveyor System Install 38
Conveyor System Install 39
Kirtli tling Street eet prog ogram ramme me 40
Kirtli tling Street eet prog ogram ramme me 41
Kirtling Street Programme • From Mid June - Complete shaft to depth. - Install conveyor. • July - Complete conveyor. - Construct shaft base. - Install Segment gantry crane. • August - Construct shaft bottom ring beam. - Assemble Water Treatment Plant - Assemble Grout Plant • September - Begin tunnelling 42
AIR QUALITY REPORTING 43
Air Quality Monitor Exceedances • Heathwall Monitor Locations 44
Air Quality Monitor Exceedances • Kirtling Monitor Locations 45
Air Quality Monitor Exceedances - Heathwall • None Air Quality Monitor Exceedances - Kirtling • 23/02/18 & 14/04/18 - Caused by number of large items of plant on site restricting access for our Roadsweeper. Damping down is also carried out. • 21/04/18 - Exceedance caused by timber works underneath dust monitor to provide formwork/shuttering for a concrete slab pour. 46
NOISE REPORTING 47
Noise Monitor Exceedances • Heathwall Monitor Locations 48
Noise Monitoring Exceedances • Monitor Locations 49
Noise Monitoring Exceedances - Heathwall • None Noise Monitoring Exceedances - Kirtling • 02/06/2018 @ 19:00 & 07/02/2018 @ 19:45 - Movement of the SPMTs (Self Propelled Mobile Transports) carrying TBMs. On both occasions the SPMTs have been required to remain active in the area in front of the noise monitor 50
COMMUNITY ENGAGEMENT CAROLINE BRENNAN 51
Issues Complaints & Enquiries register February - June 2018 Noise 12 Light 13 Other 4 52
Community Survey • 0.5% surveys were returned • 64% of respondents felt we were performing better or as expected than their expectations. 24% who felt it was worse than expected. • 40% felt that the site and contractors had been considerate, whilst 28% felt that we had not been considerate with 24% being undecided • 44% of respondents either agreed or strongly agreed that they thought we were being considerate neighbours during the construction process, with 24% disagreeing • 93% of respondents who had received information about our site and activities found it either ‘very useful’ or ‘fairly useful’ 53
Community Survey Doing well Communication Keeping noise to a minimum Communication and tidiness Things are better now, less traffic coming down Kirtling Street so thank you for improving that Minimising disruption Updates Communication is excellent. Site traffic is managed well 54
Community Survey Room for improvement Changes made Digging earth at 3am in the morning. It keeps me awake. I thought Several changes made to the barge loading operation (as there was a 10pm cut off time discussed) Noise, especially during the night Night noise due to barge loading operations considerably reduced following mitigation measures Bus stop cleanliness Dedicated road sweepers clean every day Stop the noise at night after 11pm Changes made, as above Not enough information to put forward a view Proposal to change survey to capture distance from site. Info Sheets hand delivered to wider radius The construction level of noise across the water is unacceptable. Concerns from north of the river due to barge loading operations, mitigated as discussed The roads around the site are dusty and feel unsafe with the amount of Strict logistics procedure limiting delivery times, numbers, no HGVs, but I realise these are also from other sites nearby. Would like idling, vehicle routes etc more communications. Struggle in to cope with upwards light pollution. Security lighting needs Security continue to implement blackout blinds on evening to be downwards only and we have been promised hoods for the strip shifts and angle lights downward lights and trialled various blackout blinds but don’t solve the issue Working to a tighter, definite schedule Follow schedule as tightly as possible more communications with upcoming works and progress Parking. Workers who are waiting to be picked up and leave a lot of Site workers know not to wait or idle. Travel survey rubbish around where they are waiting undertaken, share results next session The main thing is the noise from the rubble landing as it drops from the Potentially work from another site OR barge loading operation conveyor belt on to the barge which was mitigated 55
Community Investment • Series of foreshore clean-ups in Battersea with Thames21 • Community Open Day at Kirtling Street with over 700 visitors • Ongoing school workshops trialling the Virtual Reality TBM • Supporting the Royal Wedding celebrations at the ROSE Clubroom with refreshments, tumblers and picnic bench donation • Funding and decorating for new Family Room at Falconbrook Primary School 56
UPCOMING ACTIVITIES • Full summer of work experience placements June – August • Further litter clean- ups taking place in June at St Mary’s Foreshore • Proposed donation of plants from a gardening show to World’s End, ROSE Centre and Falconbrook Primary School • Graduation and Celebration Event with Sprial and Students from Brixton UTC • Invitation for event to mark International Women in Engineering day for Wandsworth students • Careers workshop with Drive Forward Foundation (young care leavers) • BIG BANK Fair South (Sutton) 57
COMMUNITY INVESTMENT 2018 1932 1932 5 687 687 40 40
Other Items Justin Feltham – Environmental Advisor 59
Recommend
More recommend