the value of commissioning in healthcare facilities
play

The Value of Commissioning in Healthcare Facilities Al Rodgers, - PowerPoint PPT Presentation

The Value of Commissioning in Healthcare Facilities Al Rodgers, LEED AP, G|PRO Todays Goals What is Cx? Cx in Healthcare Lessons Learned Value What is Cx? A quality-oriented process to verify and document performance


  1. The Value of Commissioning in Healthcare Facilities Al Rodgers, LEED AP, G|PRO

  2. Today’s Goals  What is Cx?  Cx in Healthcare  Lessons Learned  Value

  3. What is Cx?  A quality-oriented process to verify and document performance of systems and components to meet the Owner’s and Engineer’s objectives and criteria

  4. Cx Isn’t  Construction inspection  “Value engineering”  Project management  Directing contractors  Re-design

  5. Cx Authority  Technically competent  Understands systems and how they function as a whole  Understands the design intent before site visits

  6. Cx in Healthcare  Required by FGI, NYSDOH  2014 Edition “Added are requirements for developing the owner’s project requirements, preparing a commissioning plan, and developing commissioning specifications and construction checklists. The types of systems to be commissioned now include domestic hot water, fire alarm and fire protection, and essential electrical power systems and automatic temperature controls.

  7. Considerations  Pressurization  Critical power  Backflow prevention  Temperature control  Specialty gases  Nurse call  Safety eye washes, showers

  8. Path to Commissioning Authority (CxA) selected Cx Success CxA obtains project design and provides design review CxA develops Commissioning Plan  Documented Cx CxA conducts scoping meeting procedure CxA develops prefunctional checklists  Develop Cx team CxA executes checklists Deficiencies CxA approved prefunctional  Design phase Cx corrected checklists & start-up reports CxA develops functional tests  Pre-bid CxA directs and witnesses tests performed by responsible parties  Review Is equipment Yes No submittals in compliance? Approval Non-compliance  Review ongoing Corrections and re-test installation Approval CxA submits final report

  9. Path to Commissioning Authority (CxA) selected Cx Success CxA obtains project design and provides design review CxA develops Commissioning Plan  Cx Issues Log CxA conducts scoping meeting  Cx forms CxA develops prefunctional checklists CxA executes checklists  Final acceptance Deficiencies CxA approved prefunctional corrected checklists & start-up reports testing CxA develops functional tests  Training CxA directs and witnesses tests performed by responsible parties  Close-out, Is equipment Yes No including off- in compliance? Approval Non-compliance season testing Corrections and re-test  Warranty review Approval  Final report CxA submits final report

  10. Risks  If you don’t test it, how do you know it works? Wall outlets  Out of the box equipment failures  Untrained staff  Liability

  11. Risks  If you don’t test it, how do you know it works? vav  Out of the box equipment failures  Untrained staff  Liability

  12. Risks  If you don’t test it, how do you know it works?  Out of the box equipment failures  Untrained staff  Liability

  13. Risks  If you don’t test it, how do you know it works?  Out of the box equipment failures  Untrained staff  Liability

  14. Opportunities  You know it works  Patient, staff safety  Energy savings  Limit liability

  15. Retro-Cx of Existing Systems

  16. Why Retro-Cx  Buildings, systems and equipment age  Change of use  Opportunity to re-tune for operations and energy efficiency

  17. RCxA Performance  Coordinates process between Administration, Building Operators, Vendors, RCxA  Builds team of stakeholders  Controls design, implementation, and M/V process, develops long-term continuous RCx plan  Owner must implement and follow-through

  18. RCx TEAM Creation  Engage operators  Engage BMS and equipment vendors  TEAM with RCxA – Set targets – Define building or space use – Document new operation and control strategies – Make logical changes (hardware, software, equipment)  Provides a plan forward

  19. Space Use Changes

  20. RCx Results  Provides operators confidence that building will operate properly  Makes what you have work better – 70-80% of issues are controls-related – 20-30% is equipment age-related  RCx must continue over time

  21. Maintenance  Keep systems functioning as intended  Identify problems  Not letting small issues snowball to larger system malfunctions

  22. New Use  Existing building and interior space change of use  Not major demolition or system replacement

  23. Approach  Different than Cx for new construction  Review existing design, equipment  Suggest equipment changes  Generate O&M procedures

  24. The Value of Cx

  25. The Value of Cx

  26. The Value of Cx

  27. The Value of Cx

  28. The Value of Cx

Recommend


More recommend