takoma to sligo
play

Takoma to Sligo Underground Line Project Presentation for City of - PowerPoint PPT Presentation

Takoma to Sligo Underground Line Project Presentation for City of Takoma Park October 2019 Overview Pepcos purpose is to provide our customers with safe, reliable, and affordable energy. We also strive to meet the growing demand for


  1. Takoma to Sligo Underground Line Project Presentation for City of Takoma Park October 2019

  2. Overview • Pepco’s purpose is to provide our customers with safe, reliable, and affordable energy. We also strive to meet the growing demand for electric service. • As part of our commitment, we are upgrading the high-voltage infrastructure to meet the growing demand in the Downtown Silver Spring Area and Takoma Park. • This project requires construction that will affect several main roads in downtown Silver Spring, Washington D.C. and Takoma Park. 2

  3. Construction Status Construction Complete Construction Complete in 2019 Construction in 2020 3

  4. Construction Overview Construction began in September 2017 in Takoma Park and is scheduled to continue until December 2020 • Duct Bank Construction: September 2017 to Spring 2020 • Electrical Cable Pulling: Fall 2019 to Spring and Summer 2020 ▪ Work Hours: • Maryland State Highway: 9:00am – 3:00pm, M-F • Montgomery County: 9:30am – 3:30pm, M-F • District of Columbia: 9:30am – 3:30pm, M-F • City of Takoma Park: 9:00am – 3:30pm, M-F • Night work and weekend work on occasion 4

  5. Construction Overview • Temporary Traffic Control with 2 lane closures Civil • Trenching and Temporary Steel Plates • Installation of duct bank and manholes Construction • Backfilling • Temporary Restoration • Temporary Traffic Controls throughout route • Work occurs at manhole locations throughout route pulling and Electrical installation of Cable • Pulling and Installation of Cable Construction • Splicing of Cable • Permanent Restoration

  6. Road Restoration ▪ Pepco will begin road restoration in Fall 2019 ▪ Restoration work in 2019 includes milling and paving in the following areas: • Albany Ave. • Buffalo Ave. • Baltimore Ave. • Piney Branch Ave. • Cedar Ave. • Colesville Rd. • Wayne Ave. ▪ Work will begin in October and Continue thru November ▪ We will take into account weather conditions that will affect road restoration. 6

  7. Road Restoration Schedule 7

  8. Project Ombudsman ▪ Project Ombudsman is Ms. Shamyra Edmonds ▪ Location: Lamond Recreation Center, 20 Tuckerman Street NW, Washington, DC 20012 (1blk from construction at Eastern and Kansas) ▪ Her office hours are: Tuesday 6:00-9:00 PM Thursday 6:00-9:00 PM Saturday 10:00-2:00 PM ▪ Customers are encouraged to contact the project ombudsman at: Email: sedmonds@cwsons.com or Phone: (202) 643-3148 8

  9. Schedule and Milestone Dates ▪ Complete civil work for first duct bank from Takoma to Sligo by – Fall 2019 Complete civil work for both duct banks from Takoma to Sligo by – ▪ Summer 2020 ▪ Cable pulling and splicing begins for First supply – Fall/Winter 2019 ▪ Cable pulling and splicing ends for Last supply – Fall/Winter 2020 9

  10. Contact Us For project updates, visit pepco.com/takoma Have questions? Contact us at takomasligo@pepco.com or 855-888-9343. Contact Shamyra Edmonds, project ombudsman at: Email: sedmonds@cwsons.com or Phone: 202-643-3148 1 0

Recommend


More recommend