SW Capitol Hwy: Multnomah Village – West Portland 95% Design Update Capitol Highway Subcommittee December 4, 2019
Agenda 6:30pm Welcome & Introductions Chris Lyons (MNA), Steve Szigethy (PBOT), Fowler Team, All 6:45pm Major Project Updates Steve Szigethy 7:00pm 95% Plans - Overview and Discussion Steve Szigethy, All Key Topics: Retaining walls and railings • Bike Lane, Sidewalk, and Multi-Use Path • Stormwater • Trees and landscaping • Public art • 8:10pm Project Construction - Updates and Discussion Steve Szigethy, Fowler Team, All Key Topics: Schedule • Sequencing/Phasing • Public Involvement • 8:30pm Adjourn
SW Capitol Hwy: Multnomah Village – West Portland Project
Refinements in 95% Design: • All walls are cast-in-place concrete • Multnomah South stormwater facility reshaped • Spot narrowing of improvements on Capitol Hwy • Longitudinal delineation between east side peds & bikes • Multnomah Blvd ped/bike improvements defined • Right-of-way certification maps • Additional detail across all elements
Cast-in-Place Concrete Walls • Smaller excavation area • Less impactful to properties • Aesthetic preference of many in neighborhood • Historical reference to neighborhood rockery walls
Multnomah South Stormwater Detention Basin • Smaller footprint • Saves 4 large Doug firs
Spot Narrowing of Capitol Highway Improvements 3’
Longitudinal Delineation of East Side Ped and Bike Ways Where No Planter Strip is Proposed
SW Multnomah Blvd Ped/Bike Improvements • 10’ concrete multi-use path on north side for 300’ west of 40 th Ave • Roadway-level protected bikeway/walkway on both sides between 40 th & 45 th Aves • Reconstruction of all 4 corners of Multnomah/40 th
Right-of-Way Certification Maps • Shows all temporary & permanent easements needed to construct and maintain the project.
Visual Preference Survey: Influence on Design Random rounded wall pattern Black bike lane Black powder-coated square tube rail Stamped concrete-style furnishing zone Various approved trees Various approved shrubs
Construction Team • Owner / Lead Bureau: • Bureau Partners: • Construction Manager / General Contractor: • Construction Public Involvement: • Contracting Equity Consultant:
Current Picture of Construction Sequencing & Schedule • CM/GC Pre-Con Deliverables Jan-Feb 2020 • Construction Open House January 30, 2020 • Early Work Packages February-March 2020 • Final Plans & Price March 2020 • Major Construction Starts March-April 2020 • Substantial Completion Summer 2021
Public Involvement Before/During Construction • Project Newsletter #4 – January 2020 • Construction Open House – Thurs., Jan. 30, 2020 – Multnomah Arts Center 6:00-8:30pm • Weekly/bi-weekly e-bulletins with maps • Residential doorhangers • Business outreach • Project newsletters at key milestones • CHS meetings and other group briefings • Lawn signs during construction • Tabling at events • Ongoing outreach and responsive support – april@jla.us.com or 503-235-5881
Agenda 6:30pm Welcome & Introductions Chris Lyons (MNA), Steve Szigethy (PBOT), Fowler Team, All 6:45pm Major Project Updates Steve Szigethy 7:00pm 95% Plans - Overview and Discussion Steve Szigethy, All Key Topics: Retaining walls and railings • Bike Lane, Sidewalk, and Multi-Use Path • Stormwater • Trees and landscaping • Public art • 8:10pm Project Construction - Updates and Discussion Steve Szigethy, Fowler Team, All Key Topics: Schedule • Sequencing/Phasing • Public Involvement • 8:30pm Adjourn
Thank You! Steve Szigethy, Capital Program Manager Portland Bureau of Transportation steve.szigethy@portlandoregon.gov 503.823.5117
Recommend
More recommend