stakeholder meeting
play

Stakeholder Meeting January 28, 2019 PROJECT TEAM FDOT DESIGN - PowerPoint PPT Presentation

Stakeholder Meeting January 28, 2019 PROJECT TEAM FDOT DESIGN PROJECT MANAGER Maria I. Perdomo, PE MDX PROJECT MANAGER FDOT CONSTRUCTION PROJECT Claudio Diaferia, PE MANAGER Jacqueline Sequeira, PE OWNERS REPRESENTATIVE SENIOR


  1. Stakeholder Meeting January 28, 2019

  2. PROJECT TEAM FDOT DESIGN PROJECT MANAGER Maria I. Perdomo, PE MDX PROJECT MANAGER FDOT CONSTRUCTION PROJECT Claudio Diaferia, PE MANAGER Jacqueline Sequeira, PE OWNER’S REPRESENTATIVE SENIOR COMMUNITY OUTREACH PROJECT MANAGER SPECIALIST William Detwiler, PE Oscar Gonzalez CEI SENIOR PROJECT ENGINEER Mark Croft, PE CONTRACTOR Archer Western - de Moya Group Joint Venture 2

  3. PROJECT INFORMATION • Partnership between the Florida Department of Transportation (FDOT) and the Miami-Dade Expressway Authority (MDX) • Construction Cost: $802 million o FDOT: $616 million o MDX: $186 million • Anticipated Completion: Fall 2023* * Schedule subject to change due to weather or other unforeseen circumstances 3

  4. PROJECT MAP N Consists of three major projects to be constructed concurrently to minimize impacts to the public: • I-395 from I-95 to MacArthur Causeway Bridge • SR 836 from West of NW 17 Ave to Midtown Interchange • I-95 Pavement Reconstruction from NW 8 St to NW 29 St SR 836 IMPROVEMENTS I-95 CONCRETE PAVEMENT RECONSTRUCTION I-395 RECONSTRUCTION ENHANCEMENTS 4

  5. CURRENT DESIGN STATUS OVERALL DESIGN STATUS • • Structures – 40% • Maintenance of Traffic (MOT) – 45% Roadway - 75% MAJOR DESIGN SUBMITTALS TO DATE: • Master Plans for Roadway - Traffic Control Plans (TCP), Signing and ITS • 90% roadway plans for SR 836, I-395 • Final roadway plans for I-95 • 90% Phase I MOT plans for SR 836, I-395 and I-95 • 60% signature bridge foundation plans • TCP detour routes and generic details 5

  6. UPCOMING CONSTRUCTION THREE MONTH LOOK ACTIVITIES AHEAD * This schedule does not reflect days added to the contract for holidays, weather days or special events • Nighttime eastbound lane closures for soil boring operations (ongoing) • Westbound SR 836 widening over the Lawrence Canal near NW 17 Avenue (February) • Widening on SR 836 at NW 17 Avenue-Shift travel lanes to inside (February/March) • Bridge foundations on eastbound and westbound SR 836 at NW 17 Avenue (March) 6

  7. UPCOMING CONSTRUCTION THREE MONTH LOOK ACTIVITIES AHEAD SR 836 UPCOMING CONSTRUCTION ACTIVITIES • Exploratory test pile activity at several sites along I-395 (ongoing) • Utility relocations (ongoing) • Permanent closure of NE 12 Street between Biscayne Boulevard and NE 2 Avenue; Traffic to be routed to NE 13 Street (March) • Widening activity on NE 13 Street between Biscayne Boulevard and NE 2 Avenue (March) • Bridge foundation work for I-395 collector-distributor bridges (March/April) 7

  8. UPCOMING CONSTRUCTION THREE MONTH LOOK ACTIVITIES AHEAD SR 836 UPCOMING CONSTRUCTION ACTIVITIES Bridge foundation work for westbound Signature Bridge (March/April) 8

  9. UPCOMING CONSTRUCTION THREE MONTH LOOK ACTIVITIES AHEAD * This schedule does not reflect days added to the contract for holidays, weather days or special events • Nighttime closures for roadway surveying (ongoing) • Shift travel lanes on I-95 to the outside to set up work zone in the median from NW 17 Street to NW 29 Street (February) • Begin demolition of median barrier wall and relocation of drainage structures (March) • Relocate conflicting median overhead sign structures (March) 9

  10. UPCOMING ACTIVITIES - PROPOSED TEST PILE SITES N 10

  11. MAINTENANCE OF TRAFFIC (MOT)/HOURS SR 836 SPECIFIC I-395 SPECIFIC Mainline Nightly Closures Mainline Nightly Closures • 8 pm to 5:30 am Sunday thru Thursday • 10 pm to 5:30 am Sunday thru Thursday • 8:30 pm to 9 am Friday • 1 am to 7 am Saturday and Sunday • 8:30 pm to 11 am Saturday I-95 SPECIFIC RAMPS • 10 pm to 6:30 am Sunday thru Thursday​ Mainline Nightly Closures • 9 pm to 5:30 am Sunday thru Thursday • 11 pm to 7 am Friday and Saturday​ SPECIAL NOTES: • Special events will be taken into account when scheduling closures • Hours noted above are for single lane closures, multi-lane closures will occur later • Weekend lane closures will be permitted on I-95 from 11 p.m. on Friday to 5:30 a.m. on Monday • The contract documents allows for weekend closures on certain ramps 11

  12. TRAFFIC MANAGEMENT SYSTEM Smart Work Zone Management System (SWZMS) - The project will implement a SWZMS that will utilize Intelligent Transportation System (ITS) Devices such as traffic cameras, data collection devices and portable message signs to: • Provide drivers with real-time travel information; • Encourage motorists to take alternate routes; • Clear incidents more quickly, thereby reducing secondary incidents; and • Make work zones safer for highway workers and motorists. 12

  13. COMMUNITY OUTREACH PROJECT WEBSITE • www.i-395miami.com • Sign-up for project alerts/updates Lane Closure information Upcoming construction activities Presentations • Calendar of events OUTREACH OFFICE IN THE OVERTOWN COMMUNITY • 1035 NW 3 Avenue, Miami, Florida 33136 STAKEHOLDER MEETINGS • Ongoing individual stakeholder meetings and presentations • TPO Transportation Aesthetics Review Committee Presentation- February 6, 2019 13

  14. THANK YOU! www.i-395miami.com Contact: Oscar Gonzalez 786-280-0983 OGonzalez@mrgmiami.com 14

Recommend


More recommend