Stakeholder Meeting April 22, 2020
This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this presentation by anyone or entity other than FDOT staff is not official. Any questions can be sent to FDOT- D6PIO@dot.state.fl.us. This presentation may not be altered. 2
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES • Concrete pavement replacement began on Wednesday, April 15 on southbound I-95 from NW 29 Street to south of NW 20 Street * This schedule does not reflect days added to the contract for • Continuous (24/7) triple lane holidays, weather days or special events closures are being implemented to expedite work • Northbound I-95 continuous closures being considered for bridge reconstruction work at the interchange core 3
ONGOING LANE THREE MONTH LOOK CLOSURES AHEAD * This schedule does not reflect days added to the contract for ANTICIPATED LANE CLOSURES ON THE I-95 CORRIDOR: holidays, weather days or special events • Nighttime lane/ramp closure along I-95 between NW 8 Street and NW 29 Street • Closure hours have been adjusted based on current traffic conditions from 8 p.m. until 8 a.m. • Continuous lane closures (24/7) for extended periods of up to three to four weeks for both northbound and southbound I-95 4
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES • Shifted traffic on eastbound SR 836 from NW 17 Avenue to the Miami River to the right side of the roadway • Shifted traffic on westbound SR 836 from the Miami River to east of NW 17 Avenue to the left side of the roadway • Demolition of SR 836 bridge sections over NW 12 and NW 17 Streets 5
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Daytime NW 17 Avenue southbound traffic diversion for bridge demolition activities 6
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Replacement of the concrete pavement on eastbound SR 836 from NW 12 Street to I-95 with asphalt Continuous closure of one to two lanes from NW 12 Avenue to I-95. Two lanes will remain open during peak travel periods. Continuous closure of the northbound NW 12 Avenue ramp to eastbound SR 836 Anticipated duration: Four weeks 7
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES • Demolition of median section of SR 836 to begin in May • Work will begin to the east over court parking area and move to the west • Demolition work will take place at night between expanded closure hours from 8 p.m. until 8 a.m. 8
ONGOING LANE THREE MONTH LOOK AHEAD CLOSURES ANTICIPATED LANE CLOSURES ON SR 836 CORRIDOR: SR 836 UPCOMING CONSTRUCTION ACTIVITIES • Single and double lane/ramp closures along eastbound and westbound SR 836 • NW 17 Avenue under SR 836 • Arterial roads under SR 836 • Closure hours have been adjusted based on current traffic conditions from 8 p.m. until 8 a.m. • Continuous lane closures (24/7) are being implemented along SR 836 9
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES • Construction the center signature bridge foundations • Construction of westbound outside, local road bridge foundations SR 836 UPCOMING CONSTRUCTION ACTIVITIES • Demolition of portions of existing eastbound I-395 to allow for the construction of new bridge foundations • Driving of steel sheeting for foundation coffer dams 10
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES The westbound I-395 ramp to northbound I-95 has been reduced from two lanes to one lane. The reduction in lanes is necessary to reconstruct the section of I-95 where the eastbound SR 836 ramp and westbound SR 836 UPCOMING CONSTRUCTION ACTIVITIES I-395 ramp join I-95. The lane reduction is expected to be in place for approximately 18 months. 11
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Ongoing Auger Cast Pile (ACP) Operations for Segmental Bridges and Signature Bridge • * This schedule does not reflect days added to the contract for ACP Completed: 283/1948 holidays, weather days or special events o I-395 Segmental ACP – 233/857 o I-395 Signature ACP – 50/520 o SR 836 Viaduct ACP - 571 12
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Ongoing segmental * This schedule does not reflect days added to the contract for bridge column holidays, weather days or special events construction 13
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES • Westbound MacArthur Causeway Ramp to Biscayne Boulevard has been shifted to the left to allow for the construction of a new retaining wall on the right side. Only one travel lane is available on * This schedule does not reflect days added to the contract for the ramp from the MacArthur holidays, weather days or special events Causeway to North Bayshore Drive 14
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES 2 1 * This schedule does not reflect days added to the contract for holidays, weather days or special events 1 Traffic shift on Biscayne Boulevard from NE 13 Street to NE 11 Terrace. There will be three NB Lanes (two through lanes and one left turn lane onto NE 13 Street) and three SB Lanes (two through lanes and one left turn lane onto EB MacArthur Causeway). Close Bayshore loop ramp to EB MacArthur Causeway (June 2020) 2 15
ONGOING LANE THREE MONTH LOOK AHEAD CLOSURES SR 836 UPCOMING CONSTRUCTION ACTIVITIES ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR: • Lane closures along eastbound and westbound I-395 • Lane closures along Biscayne Boulevard and other arterial roadways adjacent to I-395 • I-395 to I-95 ramp closures • Closure hours have been adjusted based on current traffic conditions from 8 p.m. until 8 a.m. 16
COMMUNITY OUTREACH PROJECT WEBSITE • www.i-395miami.com • Sign-up for project alerts/updates Lane closure information Upcoming construction activities Presentations • Calendar of events OUTREACH OFFICE IN THE OVERTOWN COMMUNITY • 1035 NW 3 Avenue, Miami, Florida 33136 (CLOSED AT THIS TIME) STAKEHOLDER MEETINGS • Stakeholder meetings will be held “virtually” until further notice 17
THANK YOU! www.i-395miami.com Contact: Oscar Gonzalez 786-280-0983 OGonzalez@mrgmiami.com 18
Recommend
More recommend