Agenda • Introductions • Major service change process and public consultation • Local context and process • Discussion • Next steps
Observed and expected bed days by type of admission and day case numbers; NHS Highland residents by financial year end period 2000 -2013* Data source: SMR01 (Acute and General Hospital activity for inpatients and day cases) and NRS Mid-year population estimates, 2000 -2012 (revised series) * Expected activity calculated by applying age specific rates of bed day use and day case attendance of NHS Highland residents in 1999-2000 to mid-year population estimates
Is there a case for change? Strong concensus YES
Five key stages 1. Agree case for change 2. Options appraisal on models of service – Short-list of 3 possible models 3. Options appraisal on locations 4. Options appraisal on sites 5. Are changes proposed ‘ major ’
Public consultation 3 months 19 th May - 19 th August 2014 Accept responses up until end of August
Local involvement • Local steering group established following significant early work led by a Reference Group • 7 Workshops (June 13 to April 14) – Case for change – to develop and appraise options – Short list of three options – Preferred service model option proposed – Identify possible location in Skye – Identify site appraisal criteria
Activities so far …. • Media, social media & adverts etc • Drop-in events • Community Council meetings • Various other groups • Elected members • District Partnership • Walk about to check awareness • 1x public meeting so far (Broadford) • Lots of 1:1 discussions and meetings
Mail drop
Values based exercise Portree High School
Responsive process • Extra meetings • Respond to requests for information • Additional mail drop etc
Consulting on the preferred option BUT
Purpose of consultation People should be encouraged to express their views on all of the options that have been considered to date, or to make suggestions for alternative approaches Scottish Health Council Guidance
NHS Highland board will consider all views and be able to explain why any widely held views discounted
Ongoing work • Transport survey • Set up access and transport group • Equality and Impact Assessment (ongoing) • Clinical specification • Collaboration with Raigmore, Hospice, Scottish Ambulance, Council etc
The future 3 to 5 years before preferred model would be implemented
Some things that won’t change • Care homes will remain in existing locations • Dental unit remain in Portree, Dunvegan and Kyle • GP Practices, Dental and pharmacy will remain in same areas • Excellent culture of care provided by staff
Challenges • Modernise to reflect changing times • Address resources split across two centres • Increase capacity of care-at- home/community service • Reduce delays for out-of-hours medical cover for in-patients • Improve co-location/ joint working • Buildings cant be modernised
Long list of options Ranged from having NO hospitals in the area to having TWO NEW hospitals in the area; and various scenarios in between
Why have any hospitals?
Why not build 2 new hospitals ? • Affordability • Clinical pathways • Sustainability
Short list of three possible models of service
1. Do minimum 2. Community resource centre and hospital - Hub-in one village (Portree or Broadford) and scaled-down services in other – Spoke- (eg no in-patient beds) 3. Community resource centre, single campus in one village and significant rationalisation of all other health and care facilities
Scoring (out of 1,000) • Option 1 – 400 • Option 2 – 800 • Option 3 – 788
Steering group preferred model of service Option 2 3
Location of Hub and Spoke • Option 2 (a) - Hospital ‘Hub’ new build in Broadford, with ‘spoke’ in Portree Score = 766 • Option 2 (b) Hospital ‘Hub’ new build in Portree, with ‘spoke’ in Broadford Score = 702
Benefit criteria for location
What could change • Development of new community hospital with in-patient beds and resource centre in Broadford • Improved out-of-hours cover for in-patients • Develop care-at-home and care homes • Mackinnon Memorial Hospital to close • Portree Hospital redesigned once new hospital built • Plus other detail to be confirmed
Questions & Discussion
Further local meetings • 12 th Aug - Kilmuir, Uig and Staffin CC • 14 th Aug - Portree public meeting • 25 th Aug – District Partnership (Lochcarron)
Mail drop of consultation response form with freepost envelope Week beginning 11 th August
Tell us what you think • Make sure you complete a consultation response form (on line or hard copy) • Complete Scottish Health Council Evaluation • Write or email NHS Highland views • Accept responses up until end of August
Decision making • Public acceptability – Need to able to explain how any widely held views discounted • Clinical arguments • Technical considerations • Affordability
Next Steps • Responses will be considered • Director of operations will prepare a report for board of NHS Highland to consider • Board recommendation • Any final decision will be made by Cabinet Secretary • Thank you