  2. Cost Summary (Forecast) • Demolition*: $1.6M • Design/CA: $87K Area of Demolition • Spec. Consult. $25K • CM: $81K Total $1.8M * Based on October 13,2014 Mercurial Consulting Estimate

  3. Valley View demolition to be considered as part of the  Facilities Master Plan sequencing and cost analysis decision-making process The following also needs to be taken into consideration   Interim campus will use portion of existing building until new construction of school  Add’l design and DSA costs would be required since demolition plans part of new construction of building  Existing campus will be monitored closely by District staff for vandalism until demolished  Board decision for interim campus did not constitute a decision to move forward with demolition and/or construction of new school