Clark County Water Reclamation District Upcoming Projects January 16, 2020 Scott Hansen, P.E. 2019 Master/Expansion Plan Efforts 19005- Preliminary and Primary Treatment Major Project elements Modification of Inlet Box New Bar Screen


  1. Clark County Water Reclamation District Upcoming Projects January 16, 2020 Scott Hansen, P.E.

  2. 2019 Master/Expansion Plan Efforts

  3. 19005- Preliminary and Primary Treatment Major Project elements • Modification of Inlet Box • New Bar Screen Facility • 4 Grit Basins • New Blower facility • Odor Control Biofilters • 3 Primary Clarifiers • Primary Sludge Pump • Reliability Centered Design

  4. 19007- Secondary Treatment Major Project elements • Tie-in at PEPS • 3 aeration basins • 3 secondary clarifiers • Blower facility • Electrical building • Tie-in at secondary effluent structure • Reliability Centered Design

  5. CMAR Project Delivery Method Cost Estimating, Value Engineering, Constructability Reviews 30% Design Select Design Design to CMAR OPCC 90% Design (Prepared) Consultant 60% (Non-Binding) CMAR Input Reconcile OPCC BOT Approval of Advertise for BOT Preconstruction Evaluate Panel RFP per NRS Services Approval of Proposals Recommendation per Agreement 338.1692 NRS 338.1693 100% Design Prepare GMP Negotiate GMP per NRS 338.1697 (Binding) BOT Award of General Manager YES Construction Construction Acceptance of 18003 GMP Contract Owner (with optional Owner Advisor) NO Owner, CMAR, Engineer Bid per NRS Design Consultant Exit 338.1385 This path requires repackaging and a bid process. It CMAR Ramp will add approximately 6-9 months.

  6. NRS 338.1692

  7. NRS 338.1692

  8. CMAR Evaluation and Selection Short List Between 2 and 5 applicants will be invited for interviews CMAR Applicant will be required to submit more information (including fee), if selected for interview

  9. CMAR Pre-construction Services Agreement CMAR Construction Services Agreement

  10. Cost Estimates Primary - $126 to $144 million Secondary - $140 to $180 million

  11. Primary Schedule Advertise – Jan. 2020 Tour – Feb. 2020 Due – Mar. 2020 Interviews – Apr. 2020 BOT – Jun. 2020 BOT – Jul. 2020

  12. Secondary Schedule Advertise – Mar. 2020 Tour – Apr. 2020 Due – May 2020 Interviews – Jun. 2020 BOT – Aug. 2020 BOT – Sep. 2020

  13. Design-Bid-Build Opportunities

  14. 17012- Sandhill Interceptor Feb. 2020 $37.6 – $43.9 M Major Project Elements • 60-inch pipe • Tunneling • Junction structures • Large, Short Bypass

  15. 18001- Manhole & Pipe Rehabilitation Apr. 2020 $15 M Major Project Elements • 275 locations • Pipe Replacements • Cast-in-place pipe lining • MH Coatings & Replacement

  16. 19010- Preloading Sep. 2020 $5.3 M Major Project Elements • Dirt Hauling & Compacting • Monitoring • Site Restoration

  17. 19002- Demolition Nov. 2020 $45 M Major Project Elements • Utility Relocations • Construction Access Road • Demolition

  18. 19003- Chemical Facility Dec. 2020 $12 M Major Project Elements • Building Str. • 11 chemical tanks • Containment • Pumps • Piping • Demolition

  19. 19104- Moapa Valley Lift Station & Force Main Mar. 2021 $14 M Major Project elements • New 1 MGD Lift Station • 7,000 ft 8-inch FM (2) • 7,000 FT 4-inch Waterline • Demolition

  20. 19008- FWRC Electrical System Rehab. Apr. 2021 $10 M Major Project elements • Several New Electrical Feeders • Breakers & Switches • Fiber Conduit Runs • Cart Charging Stations

  21. 19011- FWRC DAFT 5 Dec. 2021 $12 M Major Project elements • 64’ DIA, 12’ Depth • Utility Connections • Polymer Feed • Reliability Center Design

  22. 19102 – Sludge Thickening Feb. 2022 $48 M Major Project elements • Sludge Screening • 4 Clarifiers/Settling Basins • Sludge Pump • Odor Control Biofilter • Reliability Centered Design

  23. Upcoming Bid Opportunities https://w /www.cleanwater ertea eam.com http://www.Dem emandStar.com om