SC Links Integration Point 7 3 rd HiLumi LHC-LARP – Daresbury (UK) Sylvain Weisz and Jean-Pierre Corso The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404.
Outline • Overview of Point 7 • Routing Options • Access to Point 7 for links • Hard Points • Open Points • Conclusions 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 2
Overview of Point 7 On Swiss side, but access shaft on French side (~below Ferney-Voltaire High School !) Point 7 Point 1 Point 5 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 3
Overview of Point 7 DFBA actual position DFBA actual position IP7 SC links DFB HL-LHC positions 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 4
Overview of Point 7 RR77 UJ76 R771 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 5
Assumptions retained for the SC link at Point 7 • Find a routing for a 200mm semi-rigid pipe ~500m long from service modules in RR73/77 to the DFB connections in TZ76 gallery • Minimum bending radius of 1,5m (to be experienced) • Leave free the transport areas in tunnel and in TZ76 gallery 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 6
Routing Options – RR73 & RR77 service areas • Very preliminary, need input on the design of the cryostat/service module for a detailed study (Jan 14 ?) RR77 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 7
Routing Option – R74 & R771 straight sections • Reserved space, to be implemented now SAFETY CABLING (ALARM, RED PHONE, etc… ) FIRE DETECTION TUBING SUPRA LINK R74 (left Pt7) 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 8
Routing Option – R74 & R771 straight sections • Reserved space, to be implemented now SAFETY CABLING (ALARM, RED PHONE, etc…) FIRE DETECTION TUBING SUPRA LINK R771 (right Pt7) 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 9
Routing Options – UJ76 junction • Tunnel to UJ76 service area: existing ducts are full! • New “small” ducts must be drilled • UJ76 to TZ76 gallery: 2 main options • without new long ducts • with 2 new long ducts ( ̴ 19m each) 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 10
Routing Option 1 – UJ76 • 2 ducts 3m long from LHC tunnel to service area • Without new long ducts SC Links UJ76 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 11
Routing Option 1 – UJ76 • Without new long ducts TZ76 SC Links SC Links View TZ76 UJ76 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 12
Routing Option 2 – UJ76 • With 2 new long ducts from UJ76 to the TZ76 gallery 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 13
Routing Options – UJ76 • Overview of the two options: 1 st option (no long ducts) requires more bends and smaller bending radius Option 2 Option 1 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 14
Routing Option – TZ76 • Only one practical solution: under existing cable trays SC links Racks Racks Racks Links during installation 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 15
Routing Options – TZ76 • Connection to the DFB’s 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 16
Routing Options – TZ76 • Connection to the DFB’s grouped with their corresponding power converters 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 17
Access to Point 7 for SC links Point 7 Point 8 ~3,3 km Point 6 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 18
Access to Point 7 for SC links Access Pit PM 65 Access Pit PM 85 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 19
Access to Point 7 for SC links 500m link ready for handling Space inside PM 85 Surface Building 1,8 SD8 5,5 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 20
Hard Points • RR73/77 to LHC tunnel: • Many constraints due to shieldings, metallic structures and supports • need design of the service module • Cross over the transport monorail • Only one practical solution in the LHC tunnel and in the TZ76 gallery! • Crossing of collimation doors • Action already anticipated on their design • UJ76 crossing: many bends in multiple directions 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 21
Open Points • How to connect the link to the service module ? • Vertically ? Horizontally ? • Connecting DFB’s in TZ76 gallery: • Do we install equipment close to their DFB ? • Or do we concentrate DFB’s for shorter links ? • Constraints on the SC link ? • Supporting? Fixed points? Limited space for that 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 22
Open Points • “Accessories” on the link inside the tunnel: • Instrumentation? • Services (piping for He return, controls, etc…)? • RR devices to be relocated in TZ76 ? • Inventory under progress (converters, lead control, etc… ) • Size of DFB elements to be transported? Space required for assembly and maintenance? 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 23
Conclusions • Space is very limited and constrained in the underground areas. • Further integration of the SC links requires: • D etails about service modules and DFB’s; • Details about ancillary equipment. • The real challenge is how to transport and install two ̴ 500 m long “snakes” through curved passages – We need experience there. 3rd HiLumi LHC-LARP Daresbury SW / JPC 13/11/2013 24
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404.
Recommend
More recommend