S2S Cycleway & Footway Interim Works (Bull Road to Causeway Road) Presentation to Elected Members 11 th November 2015 S2S Cycleway & Footway Interim Works 1
OVERVIEW OF THE SCHEME Cycleway and Footpaths S2S Flood Interim Defence scheme Part 8 Planning Approval New May 2013 Watermain 2
BENEFITS OF COMBINING SCHEMES Cycleway Better Value Required New for Money Sections of Seawall Less Disruption to the SAC / New watermain laid SPA and Residents during excavation Results in Greater Sea Defence Efficiency in Element Added to Planning / Design Seawalls / Procurement 3
Overview of Scheme Missing link in an overall 8km cycle track around North Dublin Bay Western Carriageway (St. Anne’s Park/Properties side) • Kerb realignment and footpath works on the western side. Eastern Carriageway (Seaward Side) • 2km of cycle and pedestrians facilities on the eastern side of the existing carriageway (4.0m wide two-way cycle track and 2m wide concrete footpath); • Improved flood defences along route and two new sections of retaining wall and works to improve existing seawall; • Proposed services include improved drainage system, watermain and upgraded public lighting. Overall • Streetscape improvement – new road surface, footpaths, traffic signals, cycle track and upgraded public lighting throughout the scheme; • Renovation of Dollymount Tram Shelter; • Enlarged and upgraded public car park at St. Anne’s Park; • Estimated Program Duration: 16+ months; • Projected completion date: Q4 2016. 4
Public Consultation Undertaken Plans and particulars Advertised: Presented to the available for public North Central Area - Dublin City Council inspection for a 6 week Committee: period up to 4 th February website 2013 at : - Irish Times Fri 14 th Dec 2012. • Dublin City Council, Public - 17 th September 2012 Counter, Planning Department. - 14 Site Notices • Raheny Library, Howth Road. - 19 th November 2012 Erected 5
Public Consultation Undertaken Public information Meeting: Follow-up meeting: Planning - 15th January 2013 at 7.30 p.m. - 10 th May 2013 in Northside in Belgrove Girls School Hall. Approval Civic Centre, Coolock. Hosted by the Clontarf Residents Engineers present and dealt Association and attended by circa 13 th May with any additional or new 180 people. queries that had not been Engineers present with drawings 2013 . addressed in the consultation of scheme to answer questions process. from members of the public. 6
7
TYPICAL CROSS-SECTION OF SCHEME 8
TYPICAL CROSS-SECTION OF SCHEME 9
UNUSED SPACE OVERLOOKING DUBLIN BAY 10
RECLAIMING AND REUSING SPACE 11
AMENITY IMPROVEMENTS Improved Access along Shoreline Tourism & Recreation Renovation of Tram Shelter 12
STREETSCAPE ENVIRONMENT IMPROVEMENTS Energy Efficient LED Lighting Reduced Noise Pollution Vulnerable Road Users 13
ST ANNE’S PARK NEW QUADRANT ENTRANCE DESIGN IMPROVE VIEW AND ACCESS TO TREE OF LIFE SCULPTURE - SCULPTURE RECOMMENCING SPRING 2016 14
PARKING PROVISIONS COMPENSATORY PARKING AT WOODEN BRIDGE DUE TO LOSS OF PARKING ON CARRIAGWAY 15
PARKING PROVISIONS • INCREASE IN PARKING SPACES FROM BAY RESTAURANT UP TO DOLLYMOUNT AVENUE • REMOVAL OF DOUBLE YELLOW ON CARRIAGEWAY AND PART OF DOLLYMOUNT AVENUE SIDE ROAD 16
PARKING PROVISIONS • UPGRADE OF ST. ANNES PARK CAR PARK • NEW STREET PARKING PROVIDED 17
SEA WALL CONSTRUCTION FOOTPATH / CYCLEWAY & ROAD PAVEMENT STILL TO BE CONSTRUCTED CURRENTLY UNDER CONSTRUCTION 18
SEA WALL CONSTRUCTION • CURRENTLY UNDER CONSTRUCTION • UNFINISHED ARTICLE • WALL FINISH OPTIONS UNDER REVIEW 19
SEA WALL CONSTRUCTION • CURRENTLY UNDER CONSTRUCTION • UNFINISHED ARTICLE • WALL FINISH OPTIONS UNDER REVIEW 20
SEA WALL CONSTRUCTION • CURRENTLY UNDER CONSTRUCTION • UNFINISHED ARTICLE • WALL FINISH OPTIONS UNDER REVIEW 21
SEA WALL CONSTRUCTION • CURRENTLY UNDER CONSTRUCTION • UNFINISHED ARTICLE • WALL FINISH OPTIONS UNDER REVIEW 22
SEA WALL CONSTRUCTION • CURRENTLY UNDER CONSTRUCTION • UNFINISHED ARTICLE • WALL FINISH OPTIONS UNDER REVIEW 23
SEA WALL CONSTRUCTION • CURRENTLY UNDER CONSTRUCTION • UNFINISHED ARTICLE • WALL FINISH OPTIONS UNDER REVIEW 24
Proposed Sea Wall Finishes Proposed wall finishes are as follows: • At sections of poured concrete wall – Smooth F4 concrete finish with new coping. • At all other sections of wall (both where existing wall is rebuilt or raised, and where new masonry wall is built) – Ready mixed smooth render finish with new coping. • Options currently being looked at to amend design to improve aesthetics of the newly completed wall. 25
Wall Heights between Junctions along Route Wall height adjustments are as follows: • Bull Island Junction to Seafield Road East Junction: Level adjustment of up to 276mm (11 inches). First 25m no level change. New average wall height = 540mm (21 inches). • Seafield Road East Junction to Dollymount Park Junction: Level adjustment up to 120mm (5 inches) and new wall construction. New average wall height = 580mm (23 inches). • Dollymount Park Junction to Doyle’s Lane Junction : New wall construction to match existing wall heights. New average wall height = 690mm (27 inches). • Doyle’s Lane Junction to Dollymount Avenue Junction : New wall construction for 55 metres to match existing levels, no level adjustment to retained wall. New average wall height = 450mm (18 inches). • Dollymount Avenue Junction to The Oaks Junction: Wall level relatively unchanged with new coping to be installed. New average wall height = 700mm (28 inches) with maximum wall height = 975mm (39 inches) – same as existing. • The Oaks Junction to Mount Prospect Avenue Junction: No level change. New average wall height = 800mm (32 inches). • Mount Prospect Avenue Junction – Naniken Stream: Level adjustment of 450mm- 690mm (18-27 inches). New average wall height = 840mm (33 inches) with maximum wall height = 1,138mm (45 inches) including 75mm (3 inch) coping. • Note: the section of wall just south of Mount Prospect Avenue which is not being adjusted is currently at a height up to 975mm (38.4 inches). The max height of our current wall north of this is 1,063mm (42 inches) excluding coping, which would be 1,138mm (45 inches) allowing for a 75mm (3 inch) coping. 26
SEA WALL HEIGHT • TIMBER BATTENS SET OUT ON SITE • BLUE SPRAY MARK = FINISHED FOOTPATH LEVEL • TOP OF BATTEN = COMPETED WALL HEIGHT 27
SEA WALL HEIGHT Opposite St. Anne's Park Lodge 28
SEA WALL HEIGHT Mount Prospect Ave Junction 29
SEA WALL HEIGHT (RELATIVE TO FOOTPATH) • WALL HEIGHT RELATIVE TO COMPLETED FOOTPATH LEVEL • 300m WITH NO RELATIVE INCREASE • ILLUSTRATES WALL HIGHER ADJACENT ST. ANNES PARK • MAX =1.138M • MIN = 0.410M 30
SEA WALL HEIGHT (RELATIVE TO FOOTPATH) 31
SEA WALL HEIGHT (RELATIVE TO FOOTPATH) 32
SEA WALL HEIGHT (RELATIVE TO FOOTPATH) 33
SEA WALL HEIGHT (RELATIVE TO FOOTPATH) 34
SEA WALL HEIGHT (RELATIVE TO FOOTPATH) 35
Howth Road to Baldoyle Road - Old Sea Wall Height for Comparison Distance from Howth Road to Baldoyle Road is 2.1km (1.3 miles) – almost identical in length to this scheme. Old sea wall is 0.7m (27.6 inches) to 1m (39.4 inches) high along the 2.1km length. Depending on the relative road level the wall does restrict views of the foreshore at times although Howth is clearly visible. This length of road is much straighter and does not have a bend or camber on the road like there near the pond at St. Anne’s Park that would restrict views for car drivers even further. 36
Average Wall Height Chart 16% 26% 34% 8% Average Wall Height 0.4m - 0.6m (16 - 24 inches): 16% Average Wall Height 0.6m - 0.8m (24 – 32 inches): 26% Average Wall Height 0.8m – 1.0m (32 – 40 inches): 34% Average Wall Height 1.0m – 1.138m (40 – 45 inches): 8% 37
SEA WALL HEIGHT (RELATIVE TO ROAD SURFACE) • ROAD SURFACE LOWER THAN FOOTPATH LEVELS (AVG. 140mm). • 150m SECTION ON BEND AT ST. ANNES PARK SUPERELEVATED RESULTING IN ROAD SURFACE LOWER RELATIVE TO FOOTPATH / WALL (Max = 0.5m). • 460m SECTION OF ROAD WHERE DRIVER EYE HEIGHT LOWER THAN WALL . • 33 SECONDS AT 50KPH. 38
SAFETY BENEFITS – COLLISION STATISTICS 1996 – 2011: 163 accidents 50% of Serious and Fatal Accidents involved Pedestrians 39
SAFETY BENEFITS Reduced Carriageway Width (2 x 3m) Removal of Upgraded Driver/Cyclist Junctions Conflict along route SAFETY Reduced speeds - Improved 85%ile Driver currently Behaviour 57.3km/h Reduced speed limit at north end 60km/h → 50km/h 40
SAFETY BENEFITS Reasons for Buildouts: • Improve visibility and safety for pedestrians crossing junctions. • Improve visibility for drivers entering or exiting side streets. • Make it easier for visually and mobility impaired people to cross the junction, as well as people will child buggies. • Prevent drivers from parking too close to corners thereby blocking visibility for pedestrians and other drivers. 41
Recommend
More recommend