Rehabilitation of Pedestrian Ramps at Designated Locations Project Project ID: HWPR18M Community Board 8 Transportation Committee May 1, 2019 Manhattan Borough President Gale Brewer Lorraine Grillo Commissioner Project Data Project ID:


  1. Rehabilitation of Pedestrian Ramps at Designated Locations Project Project ID: HWPR18M Community Board 8 Transportation Committee May 1, 2019 Manhattan Borough President Gale Brewer Lorraine Grillo Commissioner

  2. Project Data Project ID: HWPR18M Bid Date: March 19, 2018 Registered Date: July 23, 2018 Notice To Proceed: March 25, 2019 Contractor: Oliveira Contracting, INC. Contract Value: $6,878,230 Contract Duration: 545 days Completion date: Fall 2020 Federal/State Fund: Yes Registration No: 20191402042 261 W 35 th Street, 3 rd Floor Field Office: New York, NY 10001 Project ID: HWPR18M

  3. Scope of Work Work Will Include: Installation of: Concrete, steel-faced & granite curbs, pedestrian curbs, pedestrian ramps, • concrete sidewalks. Pavement key at pedestrian Ramps. • Restoration of: Roadway adjacent to newly constructed curbs. • Pruning and protection of: Trees • Project ID: HWPR18M

  4. Work Hours City DOT Approved Permit Hours: • 7:00 AM- 6:00 PM Monday- Friday • 9AM-2PM Near Schools • There is no weekend hours at this time. Locations within CB8 • Work will take place at various corners of 3 rd Avenue from East 65 th Street to East 90th Streets. • Locations will be added by NYC DOT as work progresses. Project ID: HWPR18M • Hours of work: As per NYCDOT permit stipulations

  5. Project Map and Locations • Locations will be added SW/NW Corner of 3 rd Avenue and E. 90 th Street. NW/SE Corner of 3 rd Avenue and E. 71 st St. SW/ Corner of 3 rd Avenue and E. 87 th St. NW/NE Corner of 3 rd Avenue and E.70 th St. NS/SE Corner of 3 rd Avenue and E.65 th St SW/SE/NE Corner of 3 rd Avenue and E. 81 st St. Project ID: HWPR18M

  6. Work Operations Type of Work: • Installation of approximately a 3’ to 6’ wide by 1 - 1/2” deep pavement key in the roadway along proposed curb and in additional areas where and as directed by the Engineer • Installation of Pedestrian Ramps with pigmented and unpigmented concrete sidewalk, embedded preformed detectable warning units and steel faced concrete curb. • Installation of approximately a 3’ to 6’ wide by 1 - 1/2” deep wearing course in the roadway adjacent to new curb, and in possible additional areas. • Possible relocation, modification and/or adjustments of existing drainage structures, hydrants, fire alarm facilities, and street lighting and traffic signal facilities. Project ID: HWPR18M

  7. Existing Picture Northwest Corner of E. 71 st Street and 3 rd Avenue W. 34 th STREET & 8 TH AVENUE LOOKING WEST Project ID: HWPR18M

  8. Final result of finished Pedestrian Ramp Example • W. 34 th STREET & 8 TH AVENUE LOOKING WEST Project ID: HWPR18M

  9. Community Impacts & What to Expect • DDC is committed to maintaining a work site that is safe and clean. • Pedestrian access will be maintained during construction. • Resident Engineer will monitor operations and work within Noise Code regulations. • Sidewalk and/or loading dock access from the curb may be temporarily restricted while work is conducted (coordination will be arranged on a case by case basis) • Parking may be temporarily restricted during construction. Maintenance and Protection of Traffic (MPT) • A minimum of three (3) Interlocking pedestrian steel barricades shall be fastened together for stabilization, as directed by the Engineer. • At heavy pedestrian traffic locations, a pedestrian walkway is to be provided. • A flag person will be present as needed • Traffic Safety Devices are to be installed prior to start of work and maintained until work is completed. Project ID: HWPR18M 9

  10. Maintenance and Protection of Traffic (MPT) W. 34 th STREET & 8 TH AVENUE LOOKING WEST Project ID: HWPR18M

  11. Community Impacts Continued NYC DDC Community Notification: • 72-Hour Advance Startup Advisory will be provided • Weekly Construction Bulletin showing an anticipated work schedule for the following week. Special Needs: • The DDC staff will work specifically with individuals that have special needs who may be uniquely impacted by the project. Please reach out to the project contact. Project ID: HWPR18M 11

  12. No Parking Notice Project ID: HWPR18M 12

  13. Community Advisory Project ID: HWPR18M 13

  14. Community Advisory Project ID: HWPR18M 14

  15. Weekly Look Ahead Project ID: HWPR18M 15

  16. Keeping You Informed • Eliana Perez-Gaviria will be the Community Construction Liaison (CCL) assigned to this project. Ms. Perez will be responsible for keeping the community engaged & informed by: – Being the first point of contact (Outreach, Communication) – Identifying & Coordinating (Attempt to mitigate construction impacts) – Providing regular updates in advance (Stakeholders may better plan) • CCL contact information: – Name: Eliana Perez-Gaviria – Email: hwpr18mccl@gmail.com 261 West 35 th Street, Suite 307, New York, NY 10001 – Field Office: – Telephone : (212) 967-1020 • DDC Website: www.nyc.gov/ddc • DDC Video: www.nyc.gov/webuild • During Non-Working hours, please call 311 and give the Project ID: HWPR18M Project ID: HWPR18M 16

  17. Thank you Lorraine Grillo Commissioner