recent experience from operation near future outlook
play

Recent Experience From Operation & near future Outlook V. - PowerPoint PPT Presentation

Recent Experience From Operation & near future Outlook V. Chohan CERN, Geneva, Switzerland Follow-up Review of Reception Tests of CryoMagnets, AT Division, 16 December 2003 Outline Operation Experience since July 03 1. Where are we &


  1. Recent Experience From Operation & near future Outlook V. Chohan CERN, Geneva, Switzerland Follow-up Review of Reception Tests of CryoMagnets, AT Division, 16 December 2003

  2. Outline Operation Experience since July 03 1. Where are we & Review of 23 July, other Stream-lining Measures � Staffing � To-do-list & Application � Constraints & Limitations in Operation 2. Results to date & explanations 3. Development of OP Tools � SMTMS � Surveillance & Displays � Faults Logging & general Logbook 4. I mprovements Foreseen & Desirable Glimpse at the future Tests Programme and Certain Proposals 16 December 2003 Follow-up Review of Reception V.Chohan tests of Cryomagnets

  3. Talk Abstract • Will attempt to : � Give CONTEXT & CONSTRAI NTS on HOW SM18 Testing Works today � Give a flavour of statistics of all tested magnets via bench occupancy times , explanations & hard limits � With a tongue-in-cheek challenge to connect, cool down & warm up a dipole in 72 hrs ( no cold tests) as expected from I CS & ACR so that we can all benefit from that experience � Forward near Look in testing of Dipoles � I mprovements that are necessary / essential for Operation within the confines of the testing programme as was foreseen. � Show Quench Limits , 2- Quench criterion if that is really the hard cryo limiting requirement & in the light of current magnet performance, � Show way forward for Magnetic Measurement if indeed time saving is desirable and the secondary benefits available if such option is chosen I n addition, will show the setting up of the OP team in staffing , OP Tools necessary, developed & ones that need further efforts to continue successful operation. 16 December 2003 Follow-up Review of Reception V.Chohan tests of Cryomagnets

  4. July 03 Review, its Implementation & other Measures in stream-lining 1. Recommendations were 5. 24 hr MTM piquet started end-Aug, implemented from 23 rd July hence further efficiency in work; this was not the case Feb-Aug 03(upto 22hr evening & To-do-List ( Test work Mon-fri ) programme) modified immediately 6. Availability of New Benches for testing ( E2 -9 Sept, F2 -9 Oct) and with similar 2. New To-do-List is stream-lined, software / hardware as in C cluster for facilitated OP work easy to understand by all OP crew , without complications of certain tests & related problems ( e.g. 7. Stream-lining of magnet tests results storage directly in MTF database 4.4K , many special MM’s, etc..) brought further simplicity in OP work & approach to tests - D.Tommasini 3. Thanks to stream-lined To-do- deserves the exclusive thanks for that. List, the knowledge base required by OP is also reduced and 8. ‘Jackie-boxes’ & trotinette , Ohmic consolidated on the most M’ment ease important tests & principles 9. Traveller clarifications & move of certain HV tests to I CS in Oct 03 4. Availability of Sufficient OP staff to permit 7 day, 24 hr operation ( 10. Establishment of Team Spirit & 6 newcomers from I ndia in July,2 Cohesion amongst Op crew of various in Sept, 2 in Nov & 1 AB recruit in backgrounds & cultures. ( & resolution Oct ) of other problems in housing, transport etc for I ndian Associate ) 16 December 2003 Follow-up Review of Reception V.Chohan tests of Cryomagnets

  5. Staff Issues Shift Personnel Availability 32 TOTAL 28 24 INDIA total no of OP 20 16 AB Div 12 8 Experinced if Tests 4 frozen & systems 0 Consolidated b y g h l y e t t v c i p c r a l e c n u o e u p e O F r m u a n d j a a s j M Month in 2003 16 December 2003 Follow-up Review of Reception V.Chohan tests of Cryomagnets

  6. Staffing Profile 2003 Y e a r2 0 0 3 F e b M a rc h a p ril m a y ju n e ju ly a u g s e p t O c t n o v d e c 1 k e v in k e v in k e v in k e v in k e v in k e v in k e v in k e v in k e v in k e v in k e v in 2 G -H H G -H H G -H H G -H H G -H H G -H H G -H H G -H H G -H H G -H H G -H H 3 J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie J a c k ie 4 Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l Is m a e l 5 N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille N iq u ille 6 F lo r e n c e F lo r e n c e F lo r e n c e F lo r e n c e F lo r e n c e F lo r e n c e F lo r e n c e J a k o b 7 A B 7 A B 7 A B 7 8 J a c q u e s O J a c q u e s O J a c q u e s O 9 D a v e D a v e D a v e 1 0 G .A d r ia n 1 1 1 2 1 3 g a n d h i g a n d h i g a n d h i g a n d h i d a n ie l d a n ie l d a n ie l d a n ie l d a n ie l d a n ie l d a n ie l 1 1 4 m a ra th e m a r a th e m a r a th e m a r a th e u tta m u tta m u tta m u tta m u tta m u tta m u tta m 2 1 5 p r a m o d p ra m o d p r a m o d p r a m o d p r a m o d p r a m o d p ra m o d M 2 2 M 2 2 M 2 2 M 2 2 3 1 6 m a d h u m a d h u m a d h u m a d h u m a d h u m a d h u m a d h u M 2 3 M 2 3 M 2 3 M 2 3 4 1 7 s a n ja y s a n ja y s a n ja y s a n ja y s a n ja y s a n ja y s a n ja y s a n ja y s a n ja y M 2 4 M 2 4 5 1 8 M 2 5 M 2 5 6 1 9 s h e tty s h e tty s h e tty s h e tty s h e tty s h e tty s h e tty 7 2 0 ra m r a m r a m r a m r a m ra m r a m 8 2 1 K h a r e K h a r e K h a r e K h a r e K h a r e 9 2 2 P a r e e k P a r e e k P a re e k P a r e e k P a r e e k 1 0 2 3 K a s liw a l K a s liw a l K a s liw a l K a s liw a l K a s liw a l 1 1 2 4 S r id h a r S rid h a r S r id h a r S r id h a r S r id h a r 1 2 2 5 2 6 2 7 G re e n M e a n s E x p e rie n c e d Y e llo w M e a n s N e w A rriv a ls F e b M a r c h a p r il m a y ju n e ju ly a u g s e p t O c t n o v d e c T O T A L 1 3 1 2 1 0 1 0 1 3 1 3 1 7 1 7 1 8 2 0 2 2 IN D IA 5 5 5 5 7 7 1 1 1 1 1 1 1 2 1 2 A B D iv 8 7 5 5 6 6 6 6 7 7 1 0 E x p e rin c e d if T e s ts fro z e n & s y s te m s 5 5 5 7 6 8 1 0 1 1 1 1 1 4 1 6 C o n s o lid a te d 16 December 2003 Follow-up Review of Reception V.Chohan tests of Cryomagnets

  7. Power & MM Tests pre-23July03 ol d_t est s P T 3 0 P T 2 9 M M 1 5 M M 1 4 M M 1 3 P T P T 1 4 P T 1 3 P T 1 2 P T 1 1 P T 1 0 P T 9 M M 6 M M 5 M M 4 P T 8 M M 3 M M 2 P T 7 P T 6 M M 1 P T 5 M M 0 t est s r emoved P T 4 P T 3 P T 2 P T 1 0 2 0 0 4 0 0 6 0 0 8 0 0 1 0 0 0 1 2 0 0 1 4 0 0 T i me i n M i n u t e s 16 December 2003 Follow-up Review of Reception V.Chohan tests of Cryomagnets

  8. Power & MM Tests post-23July03 New_t est s P T 0 9 P T 3 0 P T 1 1 M M 4 P T 8 M M 3 P T 6 P T 1 6 P T 5 M M 0 P T 4 P T 3 P T 2 0 2 0 0 4 0 0 6 0 0 8 0 0 1 0 0 0 1 2 0 0 1 4 0 0 T i me i n mi n ut e s New 16 December 2003 Follow-up Review of Reception V.Chohan tests of Cryomagnets

  9. To Do List Dipoles(1) post-23July03 Connection 720 1440 Prep ICS ICS ICS Lyre test 30 120 Prep 5 MTM IAP at WARM : Conf Res meas CDW1 120 60 Prep 6 MTM HV Insulation Test w arm after Bolting 90 90 Prep 7 MTM Electrical connection of TRU w ith the mobile rack 60 30 Prep 9 MTM Leak Test 72 720 Launch cycle to cool dow n Prep 12 2160 2160 cryo IAP at cold 180 180 PT 2 MTM HV tests at cold & QH res. Meas CDAP. 90 90 PT 3 MTM slow pow er abort check 1KA (125 A/s) 30 30 PT 4 MTM Shaft alignment, MMPChecks at 1500 A 90 90 MM0 MTM Provoked Quench at 1.5 kA; ALL LF, All HF 360 240 PT 5 MTM Diode Test Min NRJ at 3KA 180 180 PT 16 MTM Interbench recuperation time (8 quenches) 480 Training Quenches at 1.9K (4) 1200 1200 PT 6 MTM PT 7 PT 7 16 December 2003 Follow-up Review of Reception V.Chohan tests of Cryomagnets

  10. To Do List Dipoles(2) post-23July03 LHC cycle 150 150 MM3 MTM MM1 Check of detraining effect : 30 30 PT8 MTM MM4 Full load line & Joints Meas 180 180 MTM MM2 PT 11 Ramp to 12850 A and fast de-excitation test 30 30 MTM PT 9 HV Insulation Tests at 1.9 K 90 90 PT 30 MTM PT 10 Minimum Energy Quench @ 6.5 KA + RRR and final w arm up. 240 240 PT 09 MTM PT 11 Launch Thermal cycle w arm up 720 1440 cryo cryo PT 31 PT 12 Electrical disconnection of TRU and mobile rack. 30 30 PT 13 PT 13 IAP at w arm Conf Res meas CDW2 30 60 PT 15 Final HV & Disconnection 720 1440 PT ICS2 ICS ICS Time for tests and prep 53.5 60 Miscellaneous( Shafts issues, cryo, faults, etc….) ~10% 5 6 ESTIMATE COLD TESTS (1.9K) Time HOURS 58.5 66 Time for connection/disconnection -ICS [12 +12 hrs] 24 24 48 48 Time for w armup/cool dow n - cryo [ 36 +12 ] 48 48 60 60 Total time in hours 130.5 174.0 Total Time In DAYS 5.4 7.3 16 December 2003 Follow-up Review of Reception V.Chohan tests of Cryomagnets

Recommend


More recommend