Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations April 3, 2019 1
Agenda • Mural Update • N. Portal Update • Transportation Update 2 2
North Canon Artwork Mural to be installed on North side of Canon Wall • City Council (Study Session) – April 2 (Tomokazu Matsuyama) • Stakeholders and Fine Art Commissioners provide art direction • Artist will provide 3 concept designs • Stakeholders and Fine Art Commissioners select preferred concept • Preferred concept to Subway Liaison and full City Council for approval (May/June 2019) 3 Tomokazu Matsuyama
North Portal Environmental Analysis MARCH MAY EARLY 2020 Request for Contract Final document Proposal Awarded by presented to City released City Council Council for decision APRIL 1 Year Request for Environmental Impact Proposal Due Report 4
North Portal – Draft Alternatives 5
Agenda Projec ect Overv rview ew • Section on 1 Cons nstruction on • Section on 2 Pre-Con onstruction on • Updat ates Updat ates Wilshire/La Cienega • Wilshire/Rodeo Station • Station Reeves Yard Sound Wall • Excavation N. Canon Staging Yard • Business ss Inte terrupti ption Fund • Demolition Eat S Shop P p Play # y #Beverl erlyHil ills • City Utilities • N. Canon Closure • Piling • Decking • 6
Purple Line Extension Project Alignment 7
Sections 1, 2 & 3 Status *Subject to change. The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section 1 Section 2 Section 3 Section 3.92 Miles 2.59 Miles 2.56 Miles Length Wilshire/La Brea Wilshire/Rodeo Westwood/UCLA New Stations Wilshire/Fairfax Century City/ Westwood/VA Wilshire/La Cienega Constellation Hospital 2014 – 2015 2016 – 2018 2018 – 2019 Pre-Construction Activities 2015 – 2023 2018 – 2025 2019 – 2027 Construction 2023 2025 2027 Operations 8
Section 2 Wilshire/Rodeo Station 9
Purple Line Extension Section 2 Alignment 10
Wilshire/Rodeo Station Box Station Box Rendering shows length of the underground station box on Wilshire Bl from Canon Dr to Beverly Dr 11
Wilshire/Rodeo Station Schedule *As of April 2019, subject to change. Pending Council approval. 12
Wilshire/Reeves Staging Yard Sound Wall Installation *Subject to change Prep work began December 2018 • Sound wall installation to • be completed in April 2019* Work Hours: 8am – 6pm • Publi lic i inform ormation on g graph phics i installe led o on the Draf aft S Staging Y Yar ard l lay ayout exter erior o of the R Reev eeves es S Staging ng Y Yard 13
Demolition of N. Canon Properties Complete Photo from demolition 14
N. Canon Staging Yard *Subject to change • 20-foot sound wall around the staging yard will be installed to mitigate noise to adjacent properties and public ROW • Anticipated Start Date: mid-April • Completion Date: late May 2019 • Yard will contain: • Electrical substation • Ventilation system • Scrubbers • Water treatment plant • Equipment and material storage 15
Utility Potholing *Subject to change Potholing work to identify • existing utilities below the street Estimated Duration: 3-4 weeks • Anticipated Start Date: April 8, 2019* • Estimated Completion Date: • early May, 2019* Work Hours: Monday – Friday • 9:00am – 4:00pm Lane closures on Wilshire Blvd. • and adjoining streets will be required Two lanes maintained in each • direction. Impacted properties will be notified • in advance of work starting Example of potholing for water line Canon/Wilshire Crescent/Wilshire Beverly/Wilshire Reeves/Wilshire (34 potholes) (20 potholes) (13 potholes) (15 potholes) 16
Utility Potholing Stage 1: 1-2 days Work Hours: Monday-Friday, 9am - 4pm • Crosswalk closure on Wilshire Bl and Crescent Dr •
Utility Potholing Stage 2: 1-2 days Work Hours: Monday-Friday, 9am - 4pm • Crosswalk closure on Wilshire Bl and N Canon Dr •
Utility Potholing Stage 3: 1-2 days Work Hours: Monday-Friday, 9am - 4pm • No left turn on eastbound Wilshire Bl to • northbound N Canon Dr Crosswalk closure on Wilshire Bl and N Canon Dr •
Utility Potholing Stage 4: 1-2 days Work Hours: Monday - Friday, 9am - 4pm •
Utility Potholing Stage 5: 1-2 days Work Hours: Monday-Friday, 9am - 4pm • Flagger will be available for alley access •
Water and Sewer Line Replacement Anti ticipat pated ed S Star tart D t Date: ate: Early May 2019* Sewer Replacement - 10 weeks • Water Line Replacement - 12 weeks • 22 weeks total • Work H k Hour urs: Weekdays: 9am – 4pm and 8pm – 7am • Weekends: 10am – 6pm (as needed) • Trenching for waterline placement Traffic C Control ols: s: Two lanes in each direction will be maintained • for day work on Wilshire Bl One lane in each direction will be maintained • for night work 22
Sewer Line Replacement Stage 1: 5 days Work Hours: Monday - Friday, 9am - 4pm • No left turn onto N Crescent Dr from Wilshire Bl • No left turn onto Wilshire Bl from S Crescent Dr • 23
Sewer Line Replacement Stage 2: 5 days Work Hours: Monday-Friday, 9am - 4pm • 24
Sewer Line Replacement Stage 3: 5 days Work Hours: Monday-Wednesday*, 9am - 4pm • No left turns from Wilshire Bl to N Canon Dr • * Monday - Friday, 9am - 4pm if N Canon Dr is closed • 25
N. Canon Drive Closure Anticipated Summer 2019* *Dates subject to change 26
N. Canon Drive Closure Piling Set-up Example of construction area with piling set-up on the north side of Wilshire Bl 27
Pile Drilling Installation *Dates subject to change Pile ile in installa llation in inclu ludes: Drill rig to drill holes • Crane to lift piles into holes • Truck to backfill holes • All work occurs behind K-rail • Sched hedule Following utility relocation, anticipated to • start Q3 of 2019 Work Hours: • 7 days a week • 8:00am – 9:00pm, drilling • 9:00pm – 11:00pm, non-drilling • Work in certain areas restricted to • weekends Example of piling work in Century City 28
Pile Drilling Installation Example of progress on Constellation Bl 29
Decking *Dates subject to change Following Pi Piling: A Anti ticipa pated ted l late ate 2019* Construction of a concrete deck, curb-to- • curb on Wilshire Bl Decking will serve as the temporary street • surface Work H k Hour urs: Full closures Friday night at • 8pm through Monday mornings at 7am Asphalt removal on Wilshire Bl near Metro will work closely with first • Detroit St responders on emergency access and safety Additional activities under decking • closures: ground improvements, piling, temporary civil improvements, dewatering system installation Steel beams welding prior to concrete deck 30 panel installation
First/Last Mile Planning 31
Complete Streets Plan • Streets designed and operated for all road users • More travel choices • Focus on first/last mile recommendations • Blueprint for transportation planning • Separate implementation process with neighborhood- level input 32
Wilshire Blvd Streetscape Plan • Consistent, attractive streetscape • Safety for all road users • Placemaking • Tie improvements into Metro construction • Streetscape design guidelines (citywide template) • Allow for customization 33
Gale Property Planning • First/last mile study of • Mobility hub options Gale staging yard • Drop off and pick up property • Micromobility (La Cienega station) • Shared mobility • Autonomous vehicle connections 34
Metro’s First / Last Mile Plan • Recommendations for the Rodeo station • Analysis of barriers • Potential improvements • Crossings and connections • Signage and wayfinding • Safety and comfort • Allocation of street space by mode • Micromobility • Shared mobility 35
How to Get Involved • Complete Streets Plan • Review the Draft Plan in Mid-April at: completestreets.beverlyhills.org Special TPC Meeting on May 8 th at 6:00 PM • • Anticipated City Council adoption in June • Wilshire Blvd Streetscape Plan / Gale Property Planning • Anticipated release of RFP in spring/summer • Community outreach in summer/fall • Metro’s First / Last Mile Plan: • Community outreach in spring (Farmer’s Market) • Anticipated plan completion in summer 36
Section 1 Wilshire/La Cienega Station 37
Wilshire/Gale Intermittent Daily Gale Closure – North of Wilshire Bl Gale Dr will be intermittently • closed Monday to Friday, 6am to 6pm, and Saturday 6am to 6pm This closure is a public safety • measure due to high volumes of ingress/egress from the property Access to N Gale Dr will be • maintained from San Vicente Gale Dr from north of Wilshire Bl Bl 38
Wilshire/La Cienega Installing braces inside Wilshire/La Cienega Station 39
Recommend
More recommend