Purple Line Extension Section 1 Construction Community Meeting July 18, 2019 1
Agenda Section 1 • Project Overview • MOW Building • Tunneling • Station Updates • Eat Shop Play • Business Interruption Fund • Questions & Answers 2
Purple Line Extension Project Alignment 3
Sections 1, 2 & 3 Status *Subject to change. The PLE project team is working to deliver the project consistent with Measure M Forecasted ed S Sched edul ule Se Sect ction Section 1 Section 2 Section 3 3.92 Miles 2.59 Miles 2.56 Miles Lengt gth Wilshire/La Brea Wilshire/Rodeo Westwood/UCLA New Sta tati tions Wilshire/Fairfax Century City/ Westwood/VA Wilshire/La Cienega Constellation Hospital Pre re-Cons nstruction on 2014 – 2015 2016 – 2018 2018 – 2019 Act ctivities 2015 – 2023 2018 – 2025 2019 – 2027 Constr structi tion Oper eratio ions 2023 2025 2027 4
Purple Line Extension Section 1 Alignment 5
Purple Line Maintenance Facility Main intenance F Facil cilit ity Located in the Arts District, north of 6 th St Bridge • 590 S Santa Fe Av • Curre rrent W t Work Parking lot paved and striped • Sidewalks and landscaping installed • Furniture being placed and assembled • Artwork installed on west wall approximately mid-June • 6
Purple Line Maintenance Facility Installing art work on the façade of the building 7
Wilshire/Western Connection Schedule Schedule *As of July 2019, subject to change 8
TBMs Break Through Soyeon and Elsie break through at Wilshire/Western 9
TBM Transport TBMs being disassembled for transport back to Wilshire/La Brea Station 10
Wilshire/La Brea Station 11
Wilshire/La Brea Station Box Rendering shows length of the Wilshire/La Brea underground station box on Wilshire Bl from Orange Dr to Detroit St 12
Wilshire/La Brea Station Schedule *As of July 2019, subject to change 13
Wilshire/La Brea Station Station Construction Constructing the interior walls Assembling TBM ring on the west end
Upcoming Work Bus Pads and Water Crossings Beginning July 2019, STS will restore bus pads at the following locations: Wilshire Bl/Bronson Av • Wilshire Bl/Lorraine Bl • Wilshire Bl/McCadden Pl • Wilshire Bl/ Citrus Av • Wilshire Bl/Cloverdale Av • Wilshire Bl/McCarthy Vista • Wilshire Bl/San Vicente Bl • Example of a Bus Pad along Wilshire Bl
Wilshire Bl/Sycamore Av Antenna Antenna • Steel pole, slightly more than 62 feet above the concrete base • Less than 12 inches in diameter • Radio antenna must be in very close proximity (300 feet maximum) to the underground station’s communications room (at the east end of the Wilshire/La Brea Station) • This eliminates the loss of signal strength. • Location provides connectivity to the various emergency response agencies’ other local and mountain top radio transmitter/receiver sites • Location allows the Purple Line radio system to have the coverage it requires for all users: • Metro Operations and Maintenance • Public safety (police, fire, Sheriff, and Transit Security) in the underground stations and tunnels
Wilshire Bl/Sycamore Av Antenna Rendering of Antenna
Wilshire/Fairfax Station 18
Wilshire/Fairfax Station Box Rendering shows length of the Wilshire/Fairfax underground station box on Wilshire Bl from west of Fairfax Av to just west of Ogden Dr 19
Wilshire/Fairfax Station Schedule *As of July 2019, subject to change 20
Wilshire/Fairfax Station Station Construction Installing electrical conduit
Orange Grove Ave. Closure Start date September 2019* *As of July 2019, subject to change STS is proposing a full • closure of Orange Grove Av just south of Wilshire Bl for the duration of the project This closure will support the • excavation of appendage structures and successor activities Outreach to the community and • the relevant city agencies has begun Closure area
Wilshire/Fairfax Station Concrete and Rebar – Ongoing 2019 Concrete and rebar (steel) work • anticipated to continue through 2019 Work will require worksite traffic • control on the south side of Wilshire Bl from Orange Grove Av to Ogden Dr Off-peak work hours • (9am – 3:30pm; 8pm - 6am) More details to be provided in future • construction notices and briefings Concrete work shown from the street level at Wilshire/La Brea. Concrete is being pumped underground from the street level. Similar work will be done at the Wilshire/Fairfax Station. 23
Wilshire/Crescent Heights Tunnel Investigation, Ongoing through September 2019 Additional investigation wells • will be installed throughout Summer 2019 Lane reductions on Wilshire Bl • are anticipated to continue in advance of the tunneling from the Wilshire/Fairfax station Extended work hours may be • required as investigation continues Additional details will be • available in future construction notices Approximate work locations at Wilshire/Crescent Heights. 24
Directional Drilling August 2019 • Beginning August 2019, STS will be investigating the locations of two abandoned oil wells • Work will be done at night, 8pm to 6am • Intermittent lane closures along Wilshire Bl will be in place to support investigative drilling Approximate work location at Wilshire Bl/ La Jolla Av
Wilshire/La Cienega Station 26
Wilshire/La Cienega Station Box Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr 27
Wilshire/La Cienega Station *As of July 2019, subject to change 28
Wilshire/Gale Intermittent Daily Gale Closure – North of Wilshire Bl Gale Dr will be intermittently • closed Monday to Saturday, 6am to 6pm This closure is a public safety • measure due to high volumes of ingress/egress from the property Access to N Gale Dr will be • maintained from San Vicente Bl Hauling operation to occur • until 10pm Gale Dr from north of Wilshire Bl 29
Wilshire/La Cienega Removing stockpiled excavation material 30
Wilshire/La Cienega – Upcoming Work Instrumentation Work & Street Maintenance When hen: Ongoi oing throu ough 201 2019 Instr trumen entati tation w work on n Wils lshire B Bl a l and nd La a Cien eneg ega B a Bl Intermittent lane reductions on • Wilshire Bl, La Cienega Bl, and side streets during off-peak hours (non-rush hour) Str treet M eet Mai ainten tenan ance, D Dew ewater atering W Wel ell Mai ainten tenan ance, an and Uti tility W Work on on Wil ilsh shir ire B Bl Intermittent lane reductions on Wilshire • Bl and side streets during off-peak hours (non-rush hour) 31 Example of instrumentation drilling
Wilshire/La Cienega – Upcoming Work City of Los Angeles When hen: Ongoi oing throu ough 201 2019 Construction activities on Wilshire Bl between Fairfax Av and San Vicente Bl may require traffic control in the City of Beverly Hills. Work includes, but is not limited to: Geotechnical instrumentation installation • Soil improvement • Magnetic surveying • Information on this work and the required traffic control will be available via construction notices. 32
Station Naming Policy Station Names will reflect the following principles Tran ansit s t system tem c contex text: t: names will reflect the property’s location, relative to the • entire transit system, and not duplicated elsewhere. Pr Proper perty ar area: ea: provide specific information about the property’s location relative to • the surrounding area. Neighbor borhood ood i identity: acknowledge the communities and neighborhoods serviced • by the station and stops. Simp Simplic icity: names will be short, easily recognizable and fit for signage and mapping. • 33
Name your next Purple Line Stations Metro staff originally developed a set of geographically-based names for the Section 1 Stations and are now seeking community input on those names. Submit your proposals at metro.net/purple 34
3875 Wilshire Bl, Suite 1401 Los Angeles, CA 90010 (562)547-8978 35
5115 Wilshire Bl, Los Angeles, CA 90036 (877) 224-0954 36
225 N Canon Dr Beverly Hills, CA 90210 (310) 860-7800 37
Helpin ing l g local bu busin siness sses a s as s we bu buil ild. Purp rple L Lin ine Ext xtensio ion U Update
BIF Information and Eligibility > Financial assistance to small “mom and pop” businesses with 25 or fewer full-time employees directly impacted by Metro Rail construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > Businesses are eligible for up to $50,000 per impact year
BIF Information and Eligibility > To date, 936 grants have been awarded with a total value of more than $22.4 million along all three project areas > Crenshaw/LAX Transit Project > Regional Connector, Little Tokyo area > Purple Line Extension Section 1 and Section 2 > February 2019 Metro’s Board of Directors authorized the expansion of the BIF to Section 3 of the Purple Line Extension
Recommend
More recommend