public schools project cost overview by school
play

PUBLIC SCHOOLS Project Cost Overview by School Brick Township High - PowerPoint PPT Presentation

BRICK TOWNSHIP PUBLIC SCHOOLS Project Cost Overview by School Brick Township High School $ 1,182,000 Brick Memorial High School $ 1,162,000 Lake Riviera Middle School $ 1,092,000 Veterans Memorial Middle School $ 2,230,000


  1. BRICK TOWNSHIP PUBLIC SCHOOLS

  2. Project Cost Overview by School ● Brick Township High School $ 1,182,000 ● Brick Memorial High School $ 1,162,000 ● Lake Riviera Middle School $ 1,092,000 ● Veterans Memorial Middle School $ 2,230,000 ● Drum Point Elementary School $ 1,512,000 ● Emma Havens Young Elementary School $ 415,000 ● Herbertsville Elementary School $ 653,000 ● Lanes Mill Elementary School $ 1,512,000 ● Midstreams Elementary School $ 341,000 ● Osbornville Elementary School $ 1,179,000 ● Veterans Memorial Elementary School $ 1,037,000 ● Warren H. Wolf Elementary School $ 265,000 Total Pr tal Project Cost oject Cost $ $ 12,580,000 12,580,000

  3. Project Cost Overview by Type ● Building Renovations $ 8,206,415 ● Upgrade of existing Video Surveillance System $ 1,880,969 ● New Situational Awareness System (CLASS lockdown) $ 2,346,540 ● New Visitor Management System (Hall Pass) $ 146,076 Total Pr tal Project Cost oject Cost $ $ 12,580,000 12,580,000

  4. Video Surveillance System ● Upgrade of existing Video Surveillance System in 12 schools ● New interior and exterior high-def vandal resistant Network IR Dome Cameras ● Motion detection, tampering, defocus detection, hallway view support ● New Video Management System with 30 day storage

  5. Situational Awareness System (Sielox CLASS) Crisis Lockdown Alert Status System ● New interior and exterior integrated electronic lockdown door hardware in 12 schools ● Integrated alerts to police, fire, first responders, etc. ● Customizable alerts and status ● Panic buttons and strobe lights ● Browser based accessible from anywhere ● Interface to paging and mass notification system

  6. Visitor Management System (Hall Pass) ● Visitor management System installed at Main Entrance at 12 schools ● Scan Visitors government issued ID – checked against national registry lists ● Records credentials and maintains records ● Identifies teachers, staff, substitutes, visitors, contractors, etc. ● “No-ink” thermal badge printer

  7. Brick Township Public Schools Project Design/Construction Schedule (Tentative) ● November 6, 2018…………………..Referendum ● Nov. 2018 – Feb 2019……………..Architectural / Engineering Design ● March – April 2019………………….Bidding / Contract Award ● May – August 2019………………….Construction Activities

  8. Brick Township Public Schools Referendum Funding Schedule (Tentative)

Recommend


More recommend