Public Information Meeting WIS 48 (Knapp Street) Bear Paw Ave. to Hammond Ave. City of Rice Lake WisDOT Project I.D. 8120-04-30 March 7, 2017
Welcome & Introductions
Agenda for Meeting • Project Scope • 4-Lane to 3-Lane Conversion Information • Wisconsin Avenue Intersection • Hammond Avenue Intersection • Project Timeline • Construction Timeline • Questions & Comments Project ID 8120-04-30 March 7, 2017 Page 3
Project Scope • Project Limits – Bear Paw Ave. to Hammond Ave. – Approximately 1 mile long • Proposed Improvements – Rehabilitate existing pavement – Convert existing 4-lane roadway to 3-lane roadway – Install right turn lane and traffic signal at Wisconsin Ave. – Reconstruct Knapp St. & Hammond Ave. Intersection – Install traffic signal at Knapp St. & Hammond Ave. Intersection – Install several sections of sidewalk throughout the corridor – Upgrade existing curb ramps to meet current standards Project ID 8120-04-30 March 7, 2017 Page 4
Public Involvement Meeting #1 – January 22, 2015 • 4-Lane to 3-Lane conversion • Wisconsin Avenue intersection operation • Lowering the speed limit • Proposed sidewalk locations Project ID 8120-04-30 March 7, 2017 Page 5
4-Lane to 3-Lane Conversion (Road Diet) Project ID 8120-04-30 March 7, 2017 Page 6
4-Lane to 3-Lane Conversion (Road Diet) Project ID 8120-04-30 March 7, 2017 Page 7
4-Lane to 3-Lane Conversion (Road Diet) Project ID 8120-04-30 March 7, 2017 Page 8
4-Lane to 3-Lane Conversion (Road Diet) Project ID 8120-04-30 March 7, 2017 Page 9
Wisconsin Avenue Intersection Project ID 8120-04-30 March 7, 2017 Page 10
Hammond Avenue Intersection Project ID 8120-04-30 March 7, 2017 Page 11
Project Timeline • Currently 70% plans are completed • Right-of-Way acquisition starting in spring 2017 – Right-of-way impacts will be at Knapp & Hammond intersection – Right-of-way required at proposed sidewalk locations and some curb ramp locations • Final plans and specifications completed fall 2017 • Construction 2018 Project ID 8120-04-30 March 7, 2017 Page 12
Construction Timeline Stage 1 – Removal of existing islands at Hammond Avenue and installation of temporary pavement for future stages Project ID 8120-04-30 March 7, 2017 Page 13
Construction Timeline Stage 2 – Construction on eastbound WIS 48; access to business and private driveways to remain open Project ID 8120-04-30 March 7, 2017 Page 14
Construction Timeline Stage 3 – Construction on westbound WIS 48; Hammond Ave. closed; access to businesses and private driveways to remain open Project ID 8120-04-30 March 7, 2017 Page 15
Construction Timeline Stage 4 – Construction of median islands and traffic signals; temporary lane closures for construction Project ID 8120-04-30 March 7, 2017 Page 16
Questions/Comments Thank you for your Participation
Recommend
More recommend