project presentation 23 02 2016 organogram
play

Project Presentation 23/02/2016 Organogram Education Funding - PowerPoint PPT Presentation

Project Presentation 23/02/2016 Organogram Education Funding Agency (Funder) 3BM Education Partners ARK Schools LBHF (Project Management/Cost (School) (Client) Management) Bowmer & Kirkland Building Services (Contractor) Design


  1. Project Presentation 23/02/2016

  2. Organogram Education Funding Agency (Funder) 3BM Education Partners ARK Schools LBHF (Project Management/Cost (School) (Client) Management) Bowmer & Kirkland Building Services (Contractor) Design Consultants Sub Contractors Utility Contractors

  3. Overview of Proposed Works Proposed Site Plan Existing Site Plan

  4. Proposed Ground Floor Plan

  5. Proposed First Floor Plan

  6. Proposed External Works

  7. 3D Visuals

  8. Works Completed to date Summary of works progress to date: • Stopping up of Hemlock Road/ The Curve • Installation of turning head • Creation of site compound • Installation of temporary classroom 1 • Implementation of temporary access arrangements • Partial completion of utility diversions * Works complete to Feb 2016

  9. Utility Diversion Update • National Grid (Gas) • All diversion works complete • UK Power Networks (Electric) • All diversion works complete • British Telecom (Phone/Broadband) • Diversion works 90% complete • Target completion March 2016 • Thames Water (Sewer & Water) • Condition surveys completed for existing infrastructure • Sewer build over approval in principle received from Thames Water (Feb 16) • Sewer build over agreement currently being progressed • Mains water diversion works anticipated March 2016 • Virgin Media (Phone/Broadband) • Enabling works complete (Duct installation) • Licence requested from TFL for foot path works (New cabinet provision) – Currently awaited • 3 Month customer notice period required prior to works commencing upon receipt of TFL licence • Works completion anticipated June 2016 *Note dates are provisional and subject to change/confirmation by statutory utility providers

  10. Anticipated Programme Key Task Date Anticipated Statutory utility diversions complete June 2016 New Build works commence on site June 2016 Installation of temporary classroom 2 August 2016 Occupation of temporary classroom 2 September 2016 (start of term) External landscape works commence July 2017 Removal of temporary classroom 1 & 2 July 2017 (end of academic year) Completion of new build August 2017 Completion of external works August 2017 Occupation of facilities September 2017 * Note timescales anticipated but subject to confirmation and change

  11. Temporary Classroom Accommodation • Additional temporary classroom required for 2016/17 academic year • Additional classroom proposed on top of existing temporary classroom • Planning application submitted 11/02/2016 • Planning determination anticipated end of April 2016

  12. Playground Wall • Request received from parents for removal of the low seating walls located in the playground • Wall’s built as part of 2011 refurbishment and now fall within the listed building curtilage • Informal advice seeked from LBHF Design & Conservation officer • Initial feedback provided verbally implies that the walls can be removed, however would require reinstatement upon completion of the new build works • Written confirmation requested from planning officers prior to removal works being undertaken

  13. St Katherine's Church MUGA • Application for permitted development submitted October 2016 to LBHF planning department • Additional information requested by LBHF Planning Xmas 2016 • Additional information provided as requested February 2016 • Feedback awaited from LBHF in relation to acceptance of additional information • Works presented to diocese board at the end of February 2016 to commence consultation period (understood to be 8-12 weeks) • Anticipated timeframe for commencing works June 2016 • New facilities likely to be available for 2016/17 academic year