projec ject t id s216 16 401r 401r e 92nd st street marin
play

Projec ject t ID: S216 16-401R 401R E.92nd St Street Marin ine - PowerPoint PPT Presentation

Projec ject t ID: S216 16-401R 401R E.92nd St Street Marin ine Transfe sfer r St Statio ion (MTS TS) Ra Ramp Over r FDR R Dri rive Borough gh of Manhat hattan tan Communi mmunity ty Board No. 8 Sch chemat ematic ic Design


  1. Projec ject t ID: S216 16-401R 401R E.92nd St Street Marin ine Transfe sfer r St Statio ion (MTS TS) Ra Ramp Over r FDR R Dri rive Borough gh of Manhat hattan tan Communi mmunity ty Board No. 8 Sch chemat ematic ic Design gn Prese sentati ntation on Communi mmunity ty Board 8 8 M Jun une e 06, , 2018 018 1

  2. Agenda: • Project Outline • Tasks Completed • Preferred Alignment • Impact on E92nd St. Entrance Ramp • Feedback/Support • Next Steps 2

  3. Project Location Project Location Aerial View 3

  4. Existing Conditions Asphalt Green Building E. 91 st Street MTS Ramp DeKovats Playground Entrance Ramp to S/B FDR 4

  5. Preferred Alignment – Southbound FDR Dr. 5

  6. Requires: Preferred Alignment • Modification of E92 nd St Entrance Ramp to S/B FDR Drive  No Build Traffic Analysis - Active • Slight Reconfiguration of FDR Drive Lanes • DOT Approved in Principle 6

  7. Tasks Completed: • Design Contract Procured/NTP • Topographic Survey/Utility Survey • Tree Survey – Assessment • Sub-surface Investigation/Test Pits • Traffic Data Collection 7

  8. Tasks Completed: • Schematic Design • Approved in Principle by DOT • Vertical Clearance 12’ - 6” • Approved by DOT 8

  9. Tasks in Progress: • Traffic Data Analysis • Maintenance & Protection of Traffic • Geometric Design Drawings • Structural Design Computations • Drawings and Details 9

  10. Next Steps: • Schematic Design Approval • Proceed to Preliminary Design • Community Board Support Letter • Present to Public Design Commission – Preliminary Approval 10

  11. Next Steps: Milestone 1: Final Design 04/30/2019 Milestone 2: Proposed Bid Date 06/30/2019 Milestone 3: Proposed Construction Start 03/31/2020 Milestone 4: Substantial Completion Date 12/31/2022 11

  12. Thank You 12