Water Station 1 Project Update Presentation Title Subtitle (optional) December 8, 2014 Vancouver City Council Workshop Date Vancouver City Council Workshop/Public Hearing Tyler Clary, Staff, Title Water Engineering Program Manager Staff, Title Michelle Henry, Civil Engineer Water Station 1 Project Update - 1
Presentation Overview • Water System Overview • Water Station 1 Overview • Water Station 1 History • 2005 Site Master Plan • Current Phase • Future Phases • Ongoing Communication Water Station 1 Project Update - 2
Water System Overview • 4 th largest utility in Washington State • 72-square-mile service area • 240,000 customers • 1,000 miles of distribution pipe • 40 wells at nine water stations • 9.4 billion gallons pumped in 2013 Water Station 1 Project Update - 3
Use this blank background to display large graphics that do not easily fit on the slide layout with the CoV wave at the bottom.
Use this blank background to display large graphics that do not easily fit on the slide layout with the CoV wave at the bottom.
Water Station 1 Existing Site
Water Station 1 History • Documented water source since 1880 • 1909 - 1 MG reservoir constructed • 1937 - City took over ownership • 1938 - 4 MG reservoir and elevated tank • 1980 - Site fence removed • 1985 - Amphitheater constructed • 1998 - Swift Skate Park constructed (MG = Million Gallons) Water Station 1 Project Update - 7
Use this blank background to display large graphics that do not easily fit on the slide layout with the CoV wave at the bottom.
2005 Water Station 1 Master Plan • Old facilities • Recognized importance • Recognized vulnerability • Improve reliability through replacement of aging facilities Water Station 1 Project Update - 9
2005 Master Plan
Seismic Evaluation • 2013 evaluation of existing storage • Remove 1 MG reservoir • Replace elevated tank • Complete seismic improvements to 4 MG reservoir Water Station 1 Project Update
Current Project Status • 2013 consultant Request For Qualifications (RFQ) • August 2013 Council approved a contract with CH2M HILL • Preliminary design report (30% plans) • Preliminary design complete • Needed electrical upgrades are significant • Needed control system upgrades are significant • Treatment system upgrade Water Station 1 Project Update
Water Station 1 Phase 1 Project
Water Station 1 Future Phases
Phase 1 Consultant Contract • Final Phase 1 consultant contract with CH2M HILL consent December 15 ($6 million) • Pump Station and Operations building • Site electrical and emergency power • Treatment system building • Security improvements • Control system at WS 1 and Ops Center (SCADA) Water Station 1 Project Update - 15
Control System • Replace 1970s era equipment • Back-up server to Ops Center • Upgrades to Ops Center • New software • New fiber network • New control panels • Large portion of contract Water Station 1 Project Update - 16
Council Approval Requests 2015 • Software purchase for control system (RFP) • Control panel purchase • Construction contract to upgrade Ops Center controls • Treatment system purchase (RFP) • Right of Way vacation old East Reserve Water Station 1 Project Update - 17
Next Steps/Timeline • Phase 1 design January 2015 • Smaller contracts throughout 2015 • Phase 1 construction contract 2016 - 2017 ($18 million) • Phase 2 consultant contract 2016 • Phase 2 construction 2018 ($13 million) • Phase 3 replace 3 wells 2022 ($3 million) Water Station 1 Project Update - 18
Ongoing Communications • Central Park Neighborhood Association involvement in 2005 Master Plan effort • News articles • Current and future outreach with Central Park and other NAs • Web and Water Report updates – www.cityofvancouver.us/Water Water Station 1 Project Update - 19
Questions and Discussion • Tyler Clary, Water Engineering Program Manager (360)487-7169 tyler.clary@cityofvancouver.us • Michelle Henry, Civil Engineer (360)487-7155 michelle.henry@cityofvancouver.us To request other formats, please contact: City Manager’s Office (360) 487-8600 | WA Relay: 711 Amanda.Delapena@cityofvancouver.us Water Station 1 Project Update - 20
Recommend
More recommend