port of san francisco
play

Port of San Francisco Hazardous Materials Abatement Building 49, - PowerPoint PPT Presentation

Port of San Francisco Hazardous Materials Abatement Building 49, Cranes 14 & 30 Pier 70, Port of San Francisco Contract No. 2810R August 9, 2018 1 AGENDA 1. Welcome, Introductions, & General Information Tim Leung 2. Project


  1. Port of San Francisco Hazardous Materials Abatement Building 49, Cranes 14 & 30 Pier 70, Port of San Francisco Contract No. 2810R August 9, 2018 1

  2. AGENDA 1. Welcome, Introductions, & General Information – Tim Leung 2. Project Overview – Dan Leung 3. CMD – Finbarr Jewell 4. OLSE– Anna Liu 5. ENVIRONMENTAL – Soko Made 6. Bid Documents – Tim Leung 7. Questions

  3. Work consists primarily of: Removal and disposal of hazardous materials: lead paint, asbestos- • containing materials, PCB and Mercury-containing fixtures. Seal surfaces by 3-layer application of Global Encasement Inc.’s • “LeadLock” or equivalent. Spot abatement of lead-containing paints prior to torch cutting (as • needed) for removal of pipe-rack, metal hopper, etc. From: Building 49 • Crane 14 tower • Metal hopper and pipe-rack • Shipyard Relics • Boom and Cab exterior of Crane 30 • Hazardous materials removal from Building 49 includes: Remove lead- and asbestos-containing materials as identified • in specifications, including dust on floors and interior horizontal surfaces. Remove & replace corrugated metal roof w. ACM mastic. • Characterize & dispose of debris pile. •

  4. CRANE 30 GANTRY (N.I.C.) SURCHARGE HOPPER LATHE STAMP NORTH Photographed 11/01/17 9

  5. Building 49 Roof with ACM mastic Building 49 Debris Pile 10

  6. Crane 14 11

  7. Remove & Dispose: Hopper and Pipe Rack Stabilize & Re-use Historic Shipyard Relics Stamp Lathe 12

  8. Bid Opening August 21, 2018 • Award of Contract September 2018 • NTP, Construction Start November 2018 • Construction Term 90 Consecutive Calendar Days • Substantial Completion February 2019 • Final Completion April 2019 •

  9. Presented By: Finbarr Jewell For questions email finbarr.jewell@sfgov.org Goals for Minority Participation Contractor to be chapter 12B • • in each trade = 25.8% compliant, refer to Section 00 45 70 for details. Goals for Female Participation • in each trade = 6.9% Refer to Section 00 73 41 for details. •

  10. 18

  11. Presented By: Anna Liu anna.liu@sfgov.org

  12. Presented By: Soko Made rusununguko.made@sfgov.org Construction & Demolition (C&D) Debris Management Requirements See Section 01 74 50 for details • Minimum Diversion Rate of 75% Required • Source ‐ separated C&D debris material must be taken to a facility that reuses • and/or recycles that material MIXED C&D debris material must be taken to a REGISTERED FACILITY by a • REGISTERED TRANSPORTER Diversion Reporting – Use Form C for initial, monthly, and final reports • Weight Tags are required for monthly reporting • Contractor MUST include materials from ALL Subcontractors in reports • City Representative is responsible for reviewing, signing, and approving all • reports submitted by the Contractor.

  13. QBD  Addendum

  14. Questions? 26

Recommend


More recommend