port lands flood protection and enabling infrastructure
play

Port Lands Flood Protection and Enabling Infrastructure Due - PowerPoint PPT Presentation

Port Lands Flood Protection and Enabling Infrastructure Due Diligence Presentation 1/25/2017 Contents 1. 1. The he Por ort L Lands ds 2. 2. Don on R River F Flood ood Prot otection on 3. 3. The P e Pro rojec ect 4. 4. Why


  1. Port Lands Flood Protection and Enabling Infrastructure Due Diligence Presentation 1/25/2017

  2. Contents 1. 1. The he Por ort L Lands ds 2. 2. Don on R River F Flood ood Prot otection on 3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps

  3. The Port Lands

  4. The Port Lands

  5. Contents 1. 1. The he Por ort L Lands ds 2. 2. Don on R River F Flood ood Prot otection on 3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps

  6. Don River Flood Protection Flood Plain Flood Protected Flood Protection Landform

  7. Contents 1. 1. The he Por ort L Lands ds 2. 2. Don on R River F Flood ood Prot otection on 3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps

  8. The Project: The Port Lands Today

  9. The Project: The Port Lands Flood protection Project Uniqu que e and Unprec eced eden ented ed: River Mouth concept as flood protection • • No established regulatory approval process for creating a river in brownfield After er Flood ood Prot otec ection on: • New Don River mouth • Don Greenway (north of the Ship Channel) • Improved Keating Channel • Additional Infrastructure to drive development

  10. Project Scope: individual Components

  11. Contents 1. 1. The he Por ort L Lands ds 2. 2. Don on R River F Flood ood Prot otection on 3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps

  12. Why Due Diligence? Und nderstand nd the project’s u unk nkno nowns wns and nd pr prov ovide de as m muc uch assura urance e as pos possibl ble on on cost sts, s, r risk isks, s, and nd sched edule ule to red reduc uce e un uncert ertainty Develop the design concept for the project – beyond the EA design • • Define project scope • Detailed site-specific information on soils, etc. Environmental and regulatory approval requirements and processes • • Construction logistics Risk identification, assessment and quantification = contingency setting • • Implementation strategies and schedule Achiev eves es an ex excep eption onal lev evel el of of due e diligen gence e for for a larg arge pub ubli lic c inf nfrastruct uctur ure proj ojec ect

  13. Due Diligence: Deliverables Concep eptua ual d l des esigns prepared for key project components allowed for better understanding of • unknown conditions  Informed how the project will be constructed and implications for the cost, schedule and risk • Ref efined ed Pro rojec ect s scope e to better balance flood protection and development-enabling infrastructure in light of the new cost, schedule and risk information Upda pdated d const structio ion c cost st esti timate ate based on the concept design and refined project scope • • Updated ed pro rojec ect s sched edule ule that includes design, regulatory and environmental approvals and construction • Risk isk R Regist ister comprehensive list of potential risks and opportunities, • Probabil ilist istic ic r risk isk sim simulatio ion model developed using updated schedule, cost and risk register  Identified the probability of the project meeting its cost and schedule goals  Informed decision making on schedule, cost estimate and risks contingencies

  14. Contents 1. 1. The he Por ort L Lands ds 2. 2. Don on R River F Flood ood Prot otection on 3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Ques Questions

  15. Due Diligence: Key Findings Cost Estimate: $1.25 billion Probability of completion within $1.25 billion: 90% Major Risks/Cost Drivers: • Site Conditions: flowing sand, compressible peat • No established regulatory approval process for creating a river in brownfield Contingency: 30% Timeline: Seven-year construction period

  16. Due Diligence: Key Findings

  17. Due Diligence Findings: Soil and Water Contamination Profile

  18. Due Diligence Findings: Excavation and Fill Sequencing, Stage 1

  19. Due Diligence Findings: Excavation and Fill Sequencing, Stage 2

  20. Due Diligence Findings: Excavation and Fill Sequencing, Stage 3

  21. Due Diligence Findings: Excavation and Fill Sequencing, Stage 4

  22. Due Diligence Findings: Site Grading 1.0m

  23. Due Diligence Findings: Interim Road Network and Building Removal/Relocation

  24. Due Diligence Findings: Flood Protection Components

  25. Due Diligence Findings: Wetland Habitat and Park Components

  26. Due Diligence Findings: Bridges and Roads New Cherry Street Commissioners Street Don Roadway

  27. Due Diligence Findings: New and Replacement Services

  28. Due Diligence Findings: Project Scope and Cost Estimate Original Cost Estimate ($YoE): $975 million 1. Key finding that shaped revised cost estimate Site Conditions: flowing sand, compressible peat = • additional soil excavation, soil/groundwater treatment Escalation/Inflation • 2. Re-evaluated Project Scope • Three new components identified • Three components deferred Scope reductions • Current Cost Estimate ($YoE): $1.25 billion Includes: • Contingency Design Allowance • • Indirect Contractor Costs • Soft costs (legal, approvals, engineering) Non-recoverable HST • Due Diligence Report, Page 83

  29. Project Approvals and Construction Timeline Due Diligence Report, Page 101

  30. Due Diligence Key Findings: Construction Coordination 4 6

  31. Due Diligence Key Findings: Peer Review • Unprecedented Project • Important to Peer Review Independent review by qualified organizations • • Examine Report’s adequacy and accuracy The Netherlands Ministry of Infrastructure and Environment A global construction services provider specializing in water and marine-based projects.

  32. Contents 1. 1. The he Por ort L Lands ds 2. 2. Don on R River F Flood ood Prot otection on 3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps

  33. Project Benefits: Economic Impact and Jobs Source: Economic Impacts of Planned Investments, urbanMetrics, 2016

  34. Unlocking Future Development: Port Lands and First Gulf/Unilever Site

  35. Sustainable, Livable & Beautiful Communities

  36. Sustainable, Livable & Beautiful Communities

  37. Sustainable, Livable & Beautiful Communities

  38. Sustainable, Livable & Beautiful Communities

  39. Sustainable, Livable & Beautiful Communities

  40. Sustainable, Livable & Beautiful Communities

  41. Contents 1. 1. The he Por ort L Lands ds 2. 2. Don on R River F Flood ood Prot otection on 3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps

  42. Next Steps The Project: Funding: City of Toronto Council has directed staff to identify funding its one-third share through the 2017-2026 capital budget process. The Government of Canada and Province of Ontario have not yet committed funding . Start Date: The Project is not yet fully funded and, as a result, there is no official start date for construction at this time, with the exception of the Essroc Quay Lakefilling Project Essroc Quay Lakefilling: Funding: Committed Start Date: Detailed Design Starts February 2017 Construction Starts August 2017 Consultation: Stakeholder engagement in early 2017 Port Lands Framework Plan, Villiers Island Precinct Plan, and Transportation and Servicing Master Plan: Waterfront Toronto and the City of Toronto have continued to refine the plans since the public and stakeholder consultation in Fall 2015 Stakeholder update will follow in early 2017

Recommend


More recommend