Points of Discussion • • Big Dig Dust Controls • • Project Schedule Contractor Parking • • Next 6 Months of Construction Web Cameras • • Site Logistics Community Communication • Truck Traffic GE Innovation Point 19 June 2017 1
Looking Back GE Innovation Point 19 June 2017 2
Big Dig! Artery/Tunnel Project GE Innovation Point 19 June 2017 3
Big Dig and GE Site GE Innovation Point 19 June 2017 4
Big Dig Fun Facts • 16 Million cy of dirt was removed to fill a • 1600 truck load if line up equal 8 miles. stadium to the rim 16 times • 17,234 cy of concrete will be placed or 53 • 541,000 truck loads if lined up equals miles of sidewalk 4,612 miles, or to Brazil as the crow flies • 3.8 million cy of concrete, enough to lay sidewalk from Boston to San Francisco. • GE Project is exporting approximately 39,000cy GE Innovation Point 19 June 2017 5
Project Schedule – 26 Months GE Innovation Point Weekly Report 19 June 2017 6
G3-Sheathing & Pile Driving – Summer - Fall 2017 GE Innovation Point Weekly Report 19 June 2017 7
Site & Pile Driving Operations Hours of operation 7:00am – 5:00pm Pre-Construction Survey Sheathing/Shoring Installation – 15 days 368 Piles – 40 Days Vibration Monitoring Dust Controls GE Innovation Point 19 June 2017 8
G3- Site Excavation/Utilities – Summer 2017 • Hours of operation – 7:00am – 5:00pm • Excavation will include soil removals of approximately 1600 truck loads of soil for 70 days or 22 trucks per day. • Necco St & Necco Ct. Utilities work will take place. • Dust Controls • Street Cleaning GE Innovation Point Weekly Report 19 June 2017 9
G3- Concrete Foundation – Fall 2017 GE Innovation Point Weekly Report 19 June 2017 10
G-3 Concrete Foundations – Fall 2017 • Hours of Operation – 7:00am – 6:00pm • Concrete placement can vary up to 250cy on a single day, this can equal to 4-5 trucks per hours. • Rebar deliveries will come trailers that equal to 1-3 per day. • Total expected manpower 30-40 men per day. • Site Utilities will continue GE Innovation Point 19 June 2017 11
G3 - Steel/Concrete/ Exterior/ Interior Winter /Spring 2018 GE Innovation Point Weekly Report 19 June 2017 12
G3 - Structural/Concrete/Exterior/Interior Winter/Early Spring 2018 • Hours of Operation 7:00am – 5:00PM • Tower Crane Usage • Expected Manpower – As steel is completed will increase up to 150 men per day • Steel delivery trucks will be done daily can be up to 5 per day. • Remaining trades will begin to arrive on site as well. GE Innovation Point 19 June 2017 13
Site Logistics – G2 Brick Building Restoration GE Innovation Point 19 June 2017 14
G2 Brick Renovation Schedule Summer – Fall 2017 • Hours of operation 7:00am – 5:00pm • Begin with interior stabilization & restoration • Foundation pile caps & Concrete Core • Street Utilities on Necco Ct • Exterior restoration will also begin • Manpower 20-30 men • Truck coordination 5-8 trucks per day GE Innovation Point Weekly Report 19 June 2017 15
GE3 Site Logistics GE Innovation Point 19 June 2017 16
Truck Routes – USE THIS FOR BOTH G2 AND G3 GE Innovation Point 19 June 2017 17
Dust Control Following the City of Boston Environment Department Guidelines for Construction: • Wheel Wash at construction entrance • Vacuum sweepers to clean streets • Wet Saws for brick and masonry cutting • For re-pointing work, grinders with water spray and vacuum systems • General housekeeping at each level. GE Innovation Point 19 June 2017 18
Public Parking https://www.google.com/maps/search/parking+lots/@42.3493513,- 71.045906,1792m/data=!3m1!1e3 GE Innovation Point 19 June 2017 19
Site Cameras GE Innovation Point Weekly Report 19 June 2017 20
Community GE Innovation Point 19 June 2017 21
Community Communication Program • Project Website – gereports.com/Boston • Email – Innovation.point@ge.com • Toll Free Hotline 617-443-3434 All construction inquires will be forwarded to the construction team and answered in 24 hours, if not critical will be answered in 48 hours. GE Innovation Point Weekly Report 19 June 2017 22
XXX GE Innovation Point Weekly Report 19 June 2017 23
GE Innovation Point Weekly Report 19 June 2017 24
Community Communication Program Community Goals • Public being to reach out during work activities • Phone inquires will be answered during initial communication. • Email inquires will be answered in 24 hours • If a complaint is critical will inform the complainant within 24 hours • If a complaint is not critical will inform the complainant within 48 hours or 72 hours over a holiday or weekend. • Once the investigation into the complaint GE will communicate the conclusions and action taken. GE Innovation Point 19 June 2017 25
Community Communication Program Project Website – gereports.com/Boston • Information about the project is available on the internet • Information about upcoming public meetings and project announcements is posted. • Links are provided to ask questions Toll Free Hotline 617-443-3434 • Established to allow communication ‘where project activities are being conducted. GE Innovation Point 19 June 2017 26
Community Communication Program Email – Innovation.point@ge.com • The public is able to communicate with the project via email • Link to email address is on the project website Community Goals • Public being to reach out during work activities • Phone inquires will be answered during initial communication. • Email inquires will be answered in 24 hours GE Innovation Point 19 June 2017 27
GE Innovation Point Weekly Report 19 June 2017 28
GE Innovation Point GE Innovation Point 19 June 2017 29
G3- Site logistics GE Innovation Point 19 June 2017 30
GE Innovation Point GE Innovation Point 19 June 2017 31
G2 Brick Building Restoration GE Innovation Point 19 June 2017 32
GE Innovation Point GE Innovation Point 19 June 2017 33
Today! GE Innovation Point 19 June 2017 34
Truck Routes GE Innovation Point 19 June 2017 35
Truck Coordination GE Innovation Point 19 June 2017 36
G3-Sheathing & Pile Driving – Summer - Fall 2017 GE Innovation Point 19 June 2017 37